feed more than 3 radiators together off 15mm pipe. I used to ask “Why? What happens if I have 3 large double radiators?” I was just told “just do it, that is how it WHAT CIPHE INSURANCE is”. SERVICES As I progressed towards being a CAN DO FOR YOU Chartered Engineer, I started to realise how dangerous these rule of thumbs can be, especially for apprentice plumbers. Lets not forget!
10
20
CPD – CONSULTATION; THE KEY TO BOILER SELECTION
January/February 2017
“theory alone is useless” “practical alone is dangerous” Imagine your customer complaining about excessive noise within the heating system that you have just fitted, or the radiators or underfloor heating are not delivering enough heat to the For plumbing & heating room. Well it could actually be down to engineering professionals incorrectly sized pipework! “Why is this?” Pipework, fittings and other ancillary equipment that are fitted within a system create a resistance to the flow of water, which in turn creates a pressure loss through friction. Dependant upon the amount of flow required to deliver a specific amount of heat, the correct selection and design of pipework is critical to ensure that the heat emitter (e.g a radiator or floor heating system) is supplied the correct volumetric flow of heated water. In addition to the effect on the delivery of heat, incorrect or undersized pipework can lead to excessive flow velocities which in turn creates noise. These high velocities can also cause cavitation at elbows, pumps and valves, which can ultimately lead to the system failure.
Formula
V T h Cp
ρ
V=
h (Cp * ρ * T)
(1)
(1)
Volumetric flow rate Temperature difference (oC) Heat flow rate (kW) Specific Heat Capacity (kJ/kg.K) Density (kg/m3)
techtalk −
take the ‘pressure’ out of pipe design
13
© CIPHE
The amount of volumetric flow rate required to deliver a specific amount of heat is calculated using the simple formula (1) .
Question Calculate the required volumetric flow rate based upon the following system parameters; (1) 18 kW heat load (2) Specific heat capacity of water 4.19 kJ/kg.K (3) Temperature difference of 10 o C. (4) Density of water 0.977 kg/m3.
Answer 0.44 l/sec =
18 (4.19 * 0.977 * 10)
Tip When designing a heating pipe system, the plumbing and heating engineer must design the pipework to ensure water velocities do not exceed recommended levels. Pipe Diameter (mm) 15 - 50
Velocity (m/s) 0.75 - 1.15
Table 1: Typical water velocities for small bore pipework (BSRIA)
A starting point could also be to limit the pressure loss per metre of pipe
to between 250 to 350 Pa m. However, you must understand the theory before making such assumptions Pipe sizing is an easy process when you know how, although it is important to understand some simple housekeeping rules. Before you calculate the pipe flow velocity, it is important to ask the manufacturer for the “internal” diameter of their pipework.
The CIPHE is putting the spotlight on professionalism within the industry, with a view to attracting more school leavers to recognise the life-long career opportunities presented by apprenticeships in © CIPHE the/ 25.6mm sector ID 28mm OD
Once the internal pipe diameter is Page 08 known, the flow area is then calculated with formula (2).
Formula
Area (m2) = 3.142 * r 2
(2)
r = Internal pipe radius (m)
Proud to be a Professional www.ciphe.org.uk
p01_phe_Jan17.indd 2
03/01/2017 17:00
CO2
Unique Efficiency is an air-to-water heat pump which uses CO2 gas as a natural refrigerant and delivers industry leading coefficient performance of 4.3* with a minimal carbon footprint. Q-ton is ideal for heating water up to temperatures of 90°C, which is suitable for a wide range of applications. With a Global Warming Potential (GWP) of 1 & Ozone Depletion Potential (ODP) of 0, Q-ton is already future proven.
High Performance
High Efficiency
Environmentally Responsible
Easy Operation
Long-term Reliability
For more information, please visit www.mhiae.com call us on 0207 025 2774 or email enquiries@mhiae.com *At 65°C water supply
p02_phejan17.indd 1
12/12/2016 10:06
CONTENTS
12
CIPHE 04 08 09 10 12 17
with Paul Harmer Technical Director, CIPHE
TT/B/001
Take the “pressure” out of pipe design! I never forget those days as an apprentice plumber, where I was bombarded with `rule of thumbs`, One being don`t feed more than 3 radiators together off 15mm pipe. I used to ask “Why? What happens if I have 3 large double radiators?” I was just told “just do it, that is how it WHAT CIPHE INSURANCE is”. SERVICES As I progressed towards being a CAN DO FOR YOU Chartered Engineer, I started to realise how dangerous these rule of thumbs can be, especially for apprentice plumbers. Lets not forget!
10
20
CPD – CONSULTATION; THE KEY TO BOILER SELECTION
January/February 2017
Imagine your customer complaining about excessive noise within the heating system that you have just fitted, or the radiators or underfloor heating are not delivering enough heat to the For plumbing & heating room. Well it could actually be down to engineering professionals incorrectly sized pipework! “Why is this?” Pipework, fittings and other ancillary equipment that are fitted within a system create a resistance to the flow of water, which in turn creates a pressure loss through friction. Dependant upon the amount of flow required to deliver a specific amount of heat, the correct selection and design of pipework is critical to ensure that the heat emitter (e.g a radiator or floor heating system) is supplied the correct volumetric flow of heated water. In addition to the effect on the delivery of heat, incorrect or undersized pipework can lead to excessive flow velocities which in turn creates noise. These high velocities can also cause cavitation at elbows, pumps and valves, which can ultimately lead to the system failure.
Formula
V T h Cp
ρ
V=
h (Cp * ρ * T)
(1)
(1)
Volumetric flow rate Temperature difference (oC) Heat flow rate (kW) Specific Heat Capacity (kJ/kg.K) Density (kg/m3)
24
techtalk −
take the ‘pressure’ out of pipe design
“theory alone is useless” “practical alone is dangerous”
13
© CIPHE
The amount of volumetric flow rate required to deliver a specific amount of heat is calculated using the simple formula (1) .
Question Calculate the required volumetric flow rate based upon the following system parameters; (1) 18 kW heat load (2) Specific heat capacity of water 4.19 kJ/kg.K (3) Temperature difference of 10 o C. (4) Density of water 0.977 kg/m3.
Answer 0.44 l/sec =
18 (4.19 * 0.977 * 10)
Tip When designing a heating pipe system, the plumbing and heating engineer must design the pipework to ensure water velocities do not exceed recommended levels. Pipe Diameter (mm) 15 - 50
Velocity (m/s) 0.75 - 1.15
Table 1: Typical water velocities for small bore pipework (BSRIA)
REGULARS
to between 250 to 350 Pa m. However, you must understand the theory before making such assumptions Pipe sizing is an easy process when you know how, although it is important to understand some simple housekeeping rules. Before you calculate the pipe flow velocity, it is important to ask the manufacturer for the “internal” diameter of their pipework.
The CIPHE is putting the spotlight on professionalism within the industry, with a view to attracting more school leavers to recognise the life-long career opportunities presented by apprenticeships in © CIPHE the/ 25.6mm sector ID 28mm OD
Once the internal pipe diameter is Page 08 known, the flow area is then calculated with formula (2).
Formula
A starting point could also be to limit the pressure loss per metre of pipe
Area (m2) = 3.142 * r 2
(2)
r = Internal pipe radius (m)
Proud to be a Professional www.ciphe.org.uk
p01_phe_Jan17.indd 2
Message from the CEO CIPHE Apprentice Awards 2017 CIPHE membership matters CIPHE insurance services CIPHE National President CIPHE Director of International Development awarded Fellowship by University of Worcester Welcoming our new members
03/01/2017 17:00
06 13 16 18 25 25 28 29
News Techtalk − take the ‘pressure’ out of pipe design Smarttalk – product liability Training Matters – apprenticeship funding CIPHE External Affairs making a case for MOTs CIPHE Industrial Associates get it right first time Branch news What’s new
29
@CIPHE
www.linkedin.com/ groups?home= &gid=7467910
27
CPD − Consultation; the key to boiler selection Strategic alliance between CIPHE and the Builders Merchants Federation (BMF) Obituary: James Sydney Walley, Eng Tech, LCGI, Hon FCIPHE, Hon MCIPHE, MCIPHE, RP
20
Please make sure we have your up-to-date email address. Send your details, including your membership number, to admin@ciphe.org.uk
ciphe.org.uk
www.facebook.com/ CIPHE.UK
20 26
CIPHE technical advice The email address for any technical advice is technical@CIPHE.org.uk
27 PUBLISHER: Chartered Institute of Plumbing & Heating Engineering (CIPHE) 64 Station Lane Hornchurch Essex RM12 6NB T: +44 (0) 1708 472791
FEATURES
PUBLISHING EDITOR: Juliet Loiselle Warners Group Publications T: 01778 391067 E: julietl@warnersgroup.co.uk
SUBSCRIPTIONS: p&he is free to members of
EDITOR: Nicky Rogers Warners Group Publications T: 01778 391128 E: nickyr@warnersgroup.co.uk
or £170.00 by airmail.
the CIPHE. Non-members – £115.00 per year (six issues). Overseas – £115.00 by surface mail
READERSHIP: There are around 7,200 members of the CIPHE. The membership is made up of
ADVERTISEMENT ENQUIRIES: James Knight Warners Group Publications T: 01778 395029 E: jamesk@warnersgroup.co.uk
plumbing and heating professionals specifiers, college lecturers, plumbing designers, manufacturers, engineers and consultants.
MULTIMEDIA ACCOUNT MANAGER: James Knight Warners Group Publications T: 01778 395029 E: jamesk@warnersgroup.co.uk
© 2017 The Chartered Institute of Plumbing & Heating Engineering. Rights of translation and reproduction are reserved.
PRODUCTION: Sue Ward Warners Group Publications T: 01778 392405 E: production@warnersgroup.co.uk
Copyright notice No article may be reproduced in full or part without the written permission of the editor. In some instances, there may be a reproduction fee.
DESIGN: Amanda Clare COMMUNICATIONS GROUP Barbara Field, Paul Harmer, Juliet Loiselle, Jo McCarthy, Allan McIntosh, Nicky Rogers, Richard Soper, Robert Stockley, Catherine Swain, Kevin Wellman, Paul Williams
Disclaimer Publication of an article or inclusion of an advertisement does not necessarily imply that the Institute is in agreement with the views expressed or represents endorsement of products, materials or techniques, nor does the Institute accept responsibility for errors or omissions.
PRINTED BY WARNERS 01778 395111
January/February 2017
CIPHE_CONTENTS_01_2017.indd 3
|
journal
|
3
05/01/2017 09:45
MESSAGE FROM THE CEO
EXCITING CIPHE PROJECTS FOR 2017
Proud to be a Professional The CIPHE has been on a mission to champion the efforts of plumbing and heating engineers across the UK. Kevin Wellman, CIPHE CEO kevinw@chipe.org.uk
T
his time last year, the Institute launched the ‘Proud to be a Professional’ campaign, aimed at highlighting the essential services that plumbing and heating engineers provide for the general public. It has also served to encourage fully qualified installers to take pride in the work they carry out daily. My thanks go to the trade press who have provided excellent support through their magazines by publicising CIPHE activities. Over the past 12 months, we have introduced a variety of initiatives that support our objectives, with an overview of the success charted here:
TECHTALK Paul Harmer, CIPHE Technical Director, has been working on a series of webinars, which are open to both members and non-members of the Institute and participation is free. This strengthens our commitment to collaborate with representatives from the wider industry in order to deliver the most up-to-date and worthwhile CPD experiences possible. With the aim of raising awareness and explaining various technical topics, the Institute has introduced ‘techtalk live’, with our most recent webinar exploring the topic ‘A realistic approach to saving carbon’ in conjunction with the Worcester, Bosch Group. This video received over 3,500 views in its first week, which is a strong indication there is a real appetite for this type of
4
4_ceo.indd 4
|
journal
|
accessible, online learning. We have also launched ‘techtalk – the apprentice’, which sees the CIPHE go on the road to film a day in the life of an apprentice.
SMARTTALK Alongside this educational webinar series, we have developed ‘smarttalk’; which focuses on the vital soft skills that plumbing and heating engineers require. Topics cover three key areas – legal, finance and marketing, with the first ‘smarttalk’ addressing good business practice. This will explore the Consumer Rights Act and how it affects the industry in their day-to-day roles and responsibilities, to help protect both the installer and the consumer. At the year end we launched an extremely competitive range of insurance services which will be advantageous to those of you involved in running plumbing and heating businesses. (See page 10 of this issue.) Watch this space for more news of additional and exciting new membership services in the months ahead.
INCREASED SUPPORT A huge amount of work has also taken place during 2016 to re-engage with Industrial Associate (IA) members and encourage participation in events like the quarterly IA Development Group meetings to ensure everyone’s voice is heard. As an Institute, we are particularly keen to highlight
how leading manufacturing brands and merchants can help shape the future of the plumbing, bathroom and heating industries. Our discussions have centred on the role that IA members have to play in supporting the CIPHE to raise the industry’s profile and encouraging the need for quality products to be designed and installed by quality professionals. It’s been refreshing to see the number of representatives from IA members in attendance at our meetings and I look forward to meeting many more new faces in 2017.
VOLUNTEERS The CIPHE has been fortunate to receive immense support from volunteers including Trustees, Branch supporters, Committee Representatives, Professional Standards Inspectors, Membership Ambassadors, Marketing and Communications Group supporters and all those involved in our technical activities. My immense thanks and appreciation go to you all. The CIPHE has had a substantial increase in membership enquiries in recent weeks, from both individuals and companies who are employing plumbing and heating professionals. This has put the Institute in good stead for 2017, as we embark on a sustained membership drive. We anticipate a busy and successful year ahead and I look forward to your continued support throughout the year.
January/February 2017
05/01/2017 09:58
a
company
a
company
POWERFULL Your local branch is now in your hand... 24/7. Our impressive range of FREE* online tools, lets you identify parts FAST, check live stock availability, view your prices, create your own handy lists and manage your account wherever you are, whenever you want. Register at plumbcenter.co.uk and save time, save money and save hassle this heating season.
*
Free access to PartsArena at Plumbcenter.co.uk for registered trade credit account holders
PartsArena is a Registered Trademark of Infomill Ltd
Your No.1 heating destination
plumbcenter.co.uk l partscenter.co.uk p05_phejan17.indd 1
09/12/2016 11:15:49
NEWS
TheNEWS
ALL THAT’S HAPPENING IN THE PLUMBING & HEATING WORLD
TALENTED APPRENTICE IS BEST IN REGION A talented apprentice has beaten hundreds of others to be recognised as the best plumber in the North East. Daniel Gowland, an apprentice at Mears and Gateshead College, has been recognised by the Newcastle Branch of the CIPHE for his hard work and expertise in his field. The prestigious JB Wilkinson Shield, which was established in 1913 by the Master of The Worshipful Company of Plumbers, recognises outstanding apprentices as well as outstanding teaching. Both Daniel and Gateshead College were presented with the two-part award by Erica Stary, current Master of The Worshipful Company of Plumbers, which works closely with the CIPHE. Daniel who is 27 and from Gateshead, said: “I have always wanted to be a plumber
after watching my dad work in the industry. He would teach me how to do certain tasks when I was young and I always really admired the work he did. Now, thanks to Gateshead College and Mears, I can work in a job that I enjoy while training to qualify. “The award is also a fantastic accolade to put on my CV as well as a great confidence boost. It was a surprise to hear I had won. My college tutor put me forward so it was really assuring to know that they believe in me and that I have great support from them.” The JB Wilkinson Shield is awarded following the assessment of the nominee’s portfolio, which includes written and photographic evidence of their work and understanding of plumbing and heating. Each regional branch, in this
case Newcastle, collects and assesses the information ahead of the regional awards. The JB Wilkinson Shield for the best plumbing college 2016 award marks the fourth Gateshead College student to collect the accolade in its 103 year history, with wins in 2014, 1936 and 1931.
Daniel Gowland and his college tutor, Brett McClain
2016 COLLEGES SCOTLAND PARLIAMENTARY RECEPTION
YVONNE GETS SHIRTY!
CIPHE Approved Training Centre, West College Scotland (WCS) took part in the 2016 Colleges Scotland Parliamentary Reception. The event themed, ‘Colleges − Delivering a Stronger Economy and a Fairer Society’ was hosted by MSP James Dornan at the Scottish Parliament in Edinburgh last September. Blair Martin (19), a first year apprentice plumber from Neilston Glasgow said: “I really enjoyed demonstrating the skills that we have gained in class. It’s not every day you get to go to Parliament and meet the Head of Education so I really enjoyed it.” Curriculum and Quality Leader for Engineering at the Colleges Greenock campus, Harry Hunter said: “I was extremely impressed with the enthusiastic manner that the apprentices engaged with the Scottish ministers. They are a credit to their companies and great ambassadors for the college. “The students were extremely proud to represent the college at such a prestigious event and took great pride in showcasing the wonderful work they have done.”
Shower designer and manufacturer, Roman, has presented Yvonne Orgill with a gift to celebrate her 30 years at the Bathroom Manufacturers Association (BMA). As a mark of Roman’s appreciation for Yvonne’s dedication and hard work, she was presented with the Welsh Rugby shirt signed by each current squad member. Outside the BMA, Orgill is a passionate supporter of Welsh Rugby, which makes it the perfect gift. David Osborne, Managing Director of Roman, commented: “We have greatly valued Yvonne’s support throughout the years and we wanted to show our appreciation by presenting her with a signed rugby shirt by her beloved Welsh Rugby team.”
(L-R) Ross Hutchison, the Deputy First Minister and Cabinet Secretary for Education and Skills, John Swinney, Kerr McMahon. Blair Martin and Harry Hunter (CQL for Engineering at WCS)
6
6_news.indd 6
|
journal
|
Yvonne Orgill with David and Gerry Osborne
January/February 2017
05/01/2017 10:03
NEWS
‘ROADMAP’ FOR HEATING EFFICIENCY A new report issued by the Government’s official climate advisors has been welcomed. Neil Schofield, Head of Government and External Affairs at Worcester, Bosch Group – one of several stakeholders consulted as part of the report’s research – believes the Committee on Climate Change’s ‘Next steps to UK heat’ policy report offers clear direction for the heating industry to follow in its bid to green Britain’s heating supplies. Neil said: “We appear to have robust advice for the Government to follow which acknowledges that energy policy needs to be about more than simply switching the lights off. Heat represents 40 percent of the energy we consume and 20 percent of our greenhouse gas emissions, so it is pleasing to see the Committee on Climate Change produce such a welcome roadmap for heating efficiency. “By indicating that hydrogen could prove to be a sustainable long-term alternative to natural gas, the report effectively advises the
Government to stay faithful to our hugely successful and accessible gas grid, which has to be the most practical route towards our 2050 climate targets.” Neil goes on to stress his expectation that it is this decarbonisation of the grid at source – rather than the report’s other proposed Neil Schofield, Head option, the increased use of heat pumps – that of Government and will have the greatest impact on greening UK External Affairs heating supplies. at Worcester, Bosch Group “The new ministers in position at the Department for Business, Energy and Industrial Strategy (BEIS) have a fantastic opportunity to drive these recommendations forward. All we need from them now is the political will to make a real difference.”
5 REASONS
CIPHE MEMBER INVESTS IN STAFF TRAINING CIPHE Industrial Associate member, Salamander Pumps is (L-R) Gareth Richards, Lewis Wilkes, Ken Vance, strengthening its commitment to customer service, innovation Stephanie Clark and and product development, with an in-house apprenticeship Jayson Shepherd programme that has seen its first student graduate into a permanent role, while seven of its staff are combining work with studying for qualifications. Salamander has appointed 22-year-old Jayson Shepherd as a Research and Development Engineer, following a successful three-year apprenticeship to complete his HNC in Mechanical Engineering and an NVQ level three in Engineering Technical Support. Stepping into Jayson’s shoes is Lewis Wilkes, who is studying for an HNC in Mechanical Engineering and becomes the company’s second full time apprentice. Gareth Richards, Technical Director at Salamander Pumps said: “We committed to an apprenticeship programme several years ago, to encourage young people into the industry and promote a ‘grow our own skills base’ culture. As an ex-apprentice, I have first-hand experience of the value of this method of kick-starting a career, and the opportunities it presents for young people and their employers.” As part of Salamander’s pledge to continuous training for its staff, seven members of the technical, administration and support teams are combining their roles with studying for a range of qualifications including manufacturing engineering, sales, business administration and contact centre operations. Among them are Marketing Assistant Stephanie Clark, who joined the company as a graduate intern in 2014, and ex-plumber Ken Vance who recently completed an HNC in Manufacturing Engineering.
TOP MARKS FOR WORCESTER’S TRAINING ACADEMIES The CIPHE has awarded ApprovedTraining Centre status to Worcester, Bosch Group’s, training facilities. Located in Worcester, Clay Cross, Wakefield and West Thurrock, the Training Academies are designed, in partnership with CIPHE, to promote excellence within the industry. Paul Harmer, Technical Director at the CIPHE said: “The high quality of training opportunities, such as those offered by Worcester, can only benefit the safety of the public.” Nick Fothergill, Training Manager at Worcester commented: “This accreditation recognises the outstanding resources we have across all of our academies as well as our commitment to making sure our installers are up to date on the latest legislations and product procedures.”
TO BELONG: BEING A MEMBER OF THE CIPHE MEANS...
1 2
You have access to the best training, technical support and CPD in the industry. You are proud to be part of a network of over 7,200 plumbing and heating professionals and support a Code of Professional Standards.
3
There is an organisation behind you that is dedicated to professionalism and excellence in plumbing and heating engineering.
4 5
You have direct contact with consumers via the ‘Find a Plumbing and Heating Engineer’ online search facility.
You are recognised through your experience and qualification as amongst the best in the industry.
www.ciphe.org.uk
(L-R) Paul Harmer, CIPHE Technical Director, Nick Fothergill, Training Manager at Worcester and Paul Williams, President of CIPHE
January/February 2017
6_news.indd 7
|
journal
|
7
05/01/2017 15:49
CIPHE APPRENTICE AWARDS
CIPHE APPRENTICE Proud to be a Professional AWARDS 2017 The CIPHE is putting the spotlight on professionalism within the industry, with a view to attracting more school leavers to recognise the life-long career opportunities presented by apprenticeships in the sector.
T
o highlight the excellent work of young people who have already found their vocation in the plumbing and heating sector, the CIPHE launched its very own Apprentice Awards last year. The awards initiative aims to help raise the profile of apprenticeships by recognising both the technical and ‘soft’ skills of young people starting out in the trade.
CATEGORIES There are three categories in total, including an award for heating work, which is sponsored by the Heating and Hotwater Industry Council (HHIC), an award for plumbing, sponsored by the Bathroom Manufacturers Association (BMA) and an award for those apprentices who are able to demonstrate how they are protecting vulnerable people in society. The ‘vulnerability’ award is sponsored by the CIPHE and will recognise how young installers are able to make a difference to the health and wellbeing of the general public as a direct result of their work from a very early stage.
8
|
8_apprenice awards.indd 8
journal
|
2017
To help recognise this, the judging process will be carried out by members of the CIPHE Education & Training Group and structured to review the workmanship, examination attainment and consumer interface skills of apprentices through customer feedback.
PROFESSIONALISM Kevin Wellman, CEO of the CIPHE, said: “These awards seek to champion professionalism and best practice at apprentice level and we are appealing to anyone who might be working with an apprentice − from business owners to colleges − to get in touch and enter. So, if you are ‘Proud to be a Professional’ and know an apprentice who is too, please get involved.” More information about how to get involved and enter this year’s awards can be found on the CIPHE’s website:
<H
<A <L
<I and
<S (HHI
<S indu care
www.ciphe.org.uk The closing date for entries is Monday 31st July 2017. The winning apprentices will be invited to attend a special awards ceremony in November.
January/February 2017
12/01/2017 09:14
MEMBERSHIP MATTERS
READY FOR A CPD CHECK UP? As a professional in our industry, when it comes to keeping up-to-date with the latest developments, you’re probably ahead of your game. But do you keep a record of your Continuing Professional Development?
P
art of the CIPHE Code of Professional Standards states that: All individual members...must broaden, improve and maintain their skills, knowledge and personal qualities… by keeping…up-to-date with developments in the plumbing mechanical engineering services industry by attending and participating in Continuing Professional with Paul Harmer Technical Director, CIPHE Development (CPD) and other relevant smarttalk-ciphe.org.uk training activities. Indeed the Engineering Council, as the The Chartered Institute of Plumbing licensing the CIPHE, has stated and Heating body Engineering is for pleased to launch its “smarttalk” series aimed at communicating information that that all registrants effects our members on a daily basis.(EngTech, IEng and The smarttalk series is delivered in 3 keysmust CEng) be prepared, when called upon, areas - Legal, Finance and Marketing
Its time to talk “Smart”!
- and will endeavour to help equip our members with vital skills that support the delivery of a first class service for the consumer.
26
professionals
Smarttalk also
aims to educate on the importance THE TECH of good financial NICA L ISSUE skills, whether it be as simple as controlling cashflow on a project, or even just ensuring that you have a sufficient pension pot to support you in your later years.
Finally, smarttalk will cover different apsects of marketing and how our members can benefit from marketing themselves effectively. This could be as simple as having the correct soft skills required when dealing with the consumer, or even how to sell your services through a well branded website. For further information about carrying out a smarttalk, then please contact Marie Mcaffrey, Membership Manager on: mariem@ciphe.org.uk
The Institute is currently seeking volunteer members who would be willing at this stage to have their CPD records assessed on an informal basis. You will of course be given feedback on your assessment.
CPD CPD
INTRODUCTION TO AIR ADMITTANCE VALVES (AAVs)
Steve White, Technical Director at Studor Ltd, says that although there is a growing awareness of the risks to health from the drainage system, it is often given little thought, despite it being one of the few building systems that is integrated throughout the whole building.
T
he water trap seal
is the only barrier between the drainage system and the living and/ or working space; it is therefore Steve White, Technical Director at essential that this Studor Ltd is maintained at all times. The loss of a trap seal results in unwanted smells, noise and, importantly, the risk of pathogens/disease spreading from the drainage system into the inhabited space. While these are unpleasant in a domestic environment, there are serious health and safety concerns in a commercial environment, where the building owners, landlords and/or occupiers have a duty of care.
WHAT AFFECTS WATER TRAP SEALS? Drainage venting is all about preventing the system pressure from exceeding -400 Pa (40mm Wg), i.e. the pressure at which water trap seals will be affected. This would be mostly due to pressure fluctuations (self siphonage, induced siphonage, positive pressure and wind effect) and thermal depletion. A negative pressure transient occurs when there is a discharge of the fixture to which the trap seal is connected. This can have the effect of reducing the trap seal (or pulling the trap). This occurs as the momentum acquired by the waste passes through the fixture and down the trap seal. This momentum is transferred directly into the trap seal and trap seal loss occurs (self siphonage). Other fixtures discharging in the building can also affect the trap seal. This occurs when there is a pressure fluctuation caused by a discharge of another fixture in the system, other than the fixture to which the trap is connected. This is known as ‘induced siphonage’, which is very common in multi-storey/multi-use buildings.
Defective water trap seal: RISKS HEALTH
KEY VENTING COMPONENTS OF A DRAINAGE SYSTEM 1. Trap venting: Venting of a single fixture. 2. Group venting: Venting of a group of fixtures, using one vent on the wet side of the last fixture. 3. Branch venting: Ventilating pipe connected
to a branch discharge pipe. 4. Stack venting: Extension of the vertical discharge pipe above the highest
Perfectly functional trap seal: PROTECTS HEALTH
26
|
journal
|
AAVs work by utilising a reverse lift membrane. When there is water movement in the system, the valve will open; when the movement of water stops, the AAV will seal airtight by gravity. AAVs have the effect of slowing down pressure transients
Direction of air entrainment
Direction of air entrainment
branch discharge pipe connection that terminates at an end, open to atmosphere or with an AAV. 5. Ventilating stack: Main vertical ventilating pipe, connected to the discharge stack to limit pressure fluctuations within the discharge stack. 6. Drain venting: Venting near the end of a main drain or branch drain, the vent being installed on the wet-side of the last fixture. A combination of the above can be used on larger projects, but these methods have limitations, as open vents require penetrations through the roof, to allow the atmospheric air to balance the pressure transients within the sanitary drainage system. The larger or more complex the system, the longer it takes for the vent at the top of the building to react, leading to depletion of the water trap seals. You know when this occurs by just watching and listening. For example, if you see the water in the WC pulling, or listen to the P-trap gurgling, this is an indication venting is inadequate, as the traps are being pulled due to the pressure in the system. Alternatively, AAVs can be installed at the ‘point of need’ (PON), near the trap seals that require protection. This has the benefit of eliminating the vent pipe network, the space required and the roof penetrations.
WHAT IS AN AAV? An AAV is a valve that limits pressure fluctuations within the sanitary drainage system, by allowing air to enter the system, but not to escape. It draws the air, which is
in the building and providing air at the PON, eliminating the risk of pathogens leaving the sanitary drainage system and entering the living and/or working space. Most important is that the AAVs are sealed airtight when there is no movement of air in the system.
CRITICAL ASPECTS OF AN AAV’s OPERATION 1. The need to respond quickly to changes in pressure, every time. 2. The necessity to seal completely tight with no leakage whatsoever. 3. Longevity of operation (as long as the drainage system itself).
Discharging appliance increases entrained airflow and generates
negative transients Trap seal depletion
Mini-VentTM Local inwards relief airflow maintains trap seal
CHOOSING THE RIGHT AAV
Choosing the correct AAV is important. In the UK, AAVs must conform to BS EN 12380, they must display the correct information and the CE mark. To further ensure that the
AAV airflow reduces demand
required to maintain the trap seals, from the living space where it is installed. An AAV should open before -75 Pa, allowing air into the system and relieving the negative transient pressure. This keeps the pressures in the system for discharges
between 0 and -250 Pa. If the system goes above these pressures, this can lead to the depletion of the trap seals. A typical P-trap will suck dry in less than one second, if the pressure in the system reaches above -500 Pa (50mm Wg).
AAV Classification under BS EN 12380 Determining Factor Permitted to be located below flood level of connected appliances
Temperature
November/December 2016
Range/Position
Designation
YES
AAV is of verified appropriate quality, it is recommended that the valves also have a third party accreditation, for example, a BBA certificate or KEYMARK approval.
AAVs that utilise springs, O-rings or clip fit lids should be avoided, as these generally inevitably lead to leakage at low pressures. Under BS EN 12380, AAVs are rated for performance. An ‘A’ rated AAV can be installed up to one metre below the appliance’s flood level and a ‘I’ rated AAV has been proven to operate in extreme temperatures from -20°C to +60°C. Having an AAV that meets the ‘AI’ or the ‘AII’ classification will ensure the product is of sufficient quality and performance to provide full protection.
A
NO
B
-20°C to +60°C 0°C to +60°C 0°C to +20°C
I II III
Studor Ltd is a CIPHE Industrial Associate. For more information visit www.studor.net
November/December 2016
|
journal
|
27
CPD from p&he Journal Nov/Dec16
You can reclaim tax you pay on fees or subscriptions to some approved professional organisations − but only if you must have membership to do your job, or it’s helpful for your work. The CIPHE is an approved professional organisation and with the tax relief you are eligible for, it ensures CIPHE membership is even greater value for money. Visit https://www.gov.uk/tax-relief-for-employees/professional-fees-and-subscriptions for further details. When you next file your Annual Return don’t forget to record your CIPHE subscription amount as an allowable expense.
smarttalk
The law is there to help protect both the installer and the consumer, therefore having this valuable knowledge in your toolbox, will in certain circumstances be the most For important plumbing &tool heating in your possession. engineering
SO ARE YOU READY FOR A CPD CHECK UP?
If you would like to take part, please email your details to Marie McCaffrey, Membership Manager at mariem@ciphe.org.uk or send a hard copy to Marie at Head Office.
DID YOU KNOW?
Smarttalk will be initially concentrating on highlighting good business practice. For example, TECHNICAL understandin g the Consumer Rights CPD: THE CONSTRUCTION PRODUCTS REGULATIONS Act and how it effects the plumbing AIR ADMITTANCE VALVES and heating engineer during their daily lives, or even the risk of November/December 2016 Business skills: manslaughter through an unsafe Talk smart with CIPHE’s new installation.
20
to submit a record of their CPD to their Professional Institute. Sounds daunting? It needn’t be. There are many ways of achieving CPD including reading technical journals, attending seminars and exhibitions and also by studying modules via our e-learning portal.
10
Law & Regulations Sales & Marketing Finance & Accounts Proud to be a Professional
with knowledge from smarttalk
TM
It’s time to talk technical with CIPHE’s new
Proud to be a Professional
www.ciphe.org.uk p01_phe_Nov16.indd 1
HARD COPY OR ONLINE EDITION: YOU DECIDE
10/11/2016 10:51
Whether you prefer to browse your edition of p&he on paper or online is up to you but both are readily available. The online version now has a page turning facility to make life easier. To access your on-line copy, go to http://www.ciphe.org.uk/ professional-members/publications/
January/February 2017
9_memberbenefits.indd 9
|
journal
|
9
12/01/2017 09:50
CIPHE INSURANCE
Insurance Services by United Insurance Brokers Ltd.
What CIPHE Insurance Services can do for you and your business: • Public Liability insurance • Van & Fleet insurance • Breakdown cover • Own plant, tools and equipment • Employers’ Liability • Personal Accident & Sickness • Contract Works • Hired-in-plant • Professional Indemnity • Shop insurance • Commercial Property insurance • Directors & Officers Indemnity
• Private Household • Private Motor • Travel insurance • Private Healthcare • Life Assurance / Keyman • Residential & Commercial landlord insurance
Speak to an advisor today Business Insurance Call 0330 159 6211 and quote CIPHE Van Insurance Call 0330 159 6211 and quote CIPHEV We’re open Monday to Friday, 8am to 8pm and Saturday, 9am to 2pm
Email: ciphe@uib.co.uk Buy online: www.uibdirect.co.uk UIB Direct is a trading name of United Insurance Brokers Ltd. Registered office is 69 Mansell Street, London, E1 8AN, UK (company registration no. 2034497). The company are regulated by the Financial Conduct Authority (registration number 307812).
10
|
10_insurance.indd 10
journal
|
January/February 2017
12/01/2017 12:10
CIPHE INSURANCE
Public Liability Why use CIPHE Insurance Services: Insurance: • The only insurance partner recommended by CIPHE • Preferential premiums for CIPHE members • Cost-effective premiums first time, every time • No fees of any kind • Market leading policy wordings • Available to buy: – – – –
online 24 / 7; through UK based call centres; via email; or Face-to-face
• Online customers are supported by functionality such as “Live chat” and “Click to call” • Payments securely made online in full or over instalments • Service and skills are reflected in customer satisfaction: Feefo rating 97% • Our “Business Wizard” facility is a small business diagnostic tool that helps better understand your insurance needs
• Choose the level of cover required from £1m up to £5m and any optional extras (1) • Cover for legal defence costs and compensation • Temporary staff covered – up to 50 days a year free • £250 compensation per day for court attendance to defend a claim made against you • 24-hour legal hotline • Make changes online – when and where it suits • Award winning customer service • Instant documentation with the added benefit of storing them online, making them available 24/7 • Online claim tracking (1) Optional covers: – Employers’ Liability – Professional Indemnity – Tools, plant and equipment – Hired-in plant equipment – Business equipment – Contract works – Personal Accident – capital benefits – Personal Accident – weekly benefits
Van Insurance: • All level of covers • Insurer approved repairs – nationwide • 10% discount when you buy online, as well as no claims discounts of up to 60% • Roadside accident repairs • Lifetime guarantee on repairs – for as long as you own your van • Guaranteed courtesy van – when your van’s under repair at an approved garage • Uninsured driver promise* • Cover for the little things that matter – your in-built Sat Nav and music players, wrong fuel, lost keys and more • Cover for 93 days’ EU travel
* If you need to claim for an accident caused by an uninsured driver – you won't lose your no claims discount or have to pay an excess. Valid only for uninsured drivers we can trace.
I bought van insurance online. It was easy and straightforward and very competitive. I would recommend it to anyone.
January/February 2017
10_insurance.indd 11
|
journal
|
11
12/01/2017 12:11
NATIONAL PRESIDENT
PRESIDENT’S DIARY
Proud to be a Professional
Paul Williams
Paul Williams, CIPHE National President, combines running his own business with his CIPHE duties, So this is a particularly busy time of year for him.
O
ver the last couple of months, I have had the pleasure in presenting awards to members at both ends of their careers. First there was the Wilkinson Shield, which itself has been presented for over 100 years, this is awarded to students in the North East of England and the winner of this award this year was Daniel Gowland, an apprentice at Mears and Gateshead College. I attended the Lincolnshire presentation evening and the winners from each college are young plumbers making a start in their careers. Following conversations with them regarding our profession and their enthusiasm, I believe that these young plumbers will have very successful careers and I wish them all the best.
CIPHE MEMBER FOR 60 YEARS At the other end of their career, I had the honour of presenting an Exceptional Service certificate to Stan Rawcliffe from Lancashire Branch, who has been a member of our
Institute for 60 years. It was interesting to listen to Stan talk about his career and how he has developed over the years and the changes he has seen in the trade. Stan joined the Institute back in 1956 and became a fellow in 1975, he also received his Master Plumber status in 2003, it was a wonderful afternoon and I would like to thank the Lancashire Branch for their welcome.
JIM WALLEY Mr Jim Walley was given the Honorary Fellowship Award, I have known Jim for many years and have had the pleasure of many conversations with him. Due to his ill health, Jim was not able to attend the presentation on the night so I presented the certificate to his daughter. Since the presentation, Jim has sadly passed away, this is such a huge loss to everyone who knew him and I know that I will miss him and our little chats. I would like to give my condolences to his family. (See Jim’s obituary on page 27 of this issue.)
On 16th November, I attended the British Automatic Fire Sprinkler Association Conference in Cardiff. This was a very interesting day and as fire sprinklers are now a regulation in domestic dwellings in Wales, a feature on this will be published in a future issue. I attended PHEX in Chelsea where we did presentations and I met some CIPHE members. Finally, I attended the SNIPEF President’s evening where I met nominees of their awards and I offer many congratulation to the winners.
Paul Williams, Daniel Gowland and Erica Stary
CIPHE Members! Do you really trust where you buy your plumbing and heating products? 5 key reasons to buy from a BMF Member 1. 2. 3. 4. 5.
Guaranteed product quality Standard sizings and fittings High level of service through the BMF Customer Charter Product advice from experienced teams Structured credit facilities Look out for the BMF Charter logo The BMF Charter logo is your assurance of the highest standards throughout the plumbing and heating materials supply chain. Why buy from anyone else?
For more information call the BMF on 02476 854980 or email info@bmf.org.uk
www.bmf.org.uk
12_np and bmf ad.indd 12
05/01/2017 11:16
TT/B/001
with Paul Harmer with Paul Harmer Technical with PaulDirector, HarmerCIPHE Technical Director, CIPHE Technical Director, CIPHE with Paul Harmer with Paul Harmer with Paul Harmer Technical Director, CIPHE Technical Director, CIPHE with Paul Harmer
Take TT/B/001the 'pressure' out of pipe design! TT/B/001 TT/B/001 I never forget those days as an apprentice TT/B/001 plumber, where I was bombarded TT/B/001 TT/B/001
Technical Director, Technical Director, CIPHECIPHE
Take out pipe design! Takethe the 'pressure' 'pressure'out outofof ofpipe pipedesign! design! the 'pressure' Take the'pressure' 'pressure' out of pipe pipe design! Take out design! Take the 'pressure' ' 'pressure' 'p ressure'' out of of pipe design! Takethe the out of pipe design!
with `ruleTT/B/001 of thumbs`, One being don`t with Paul Harmer feed more than 3those radiators off I never forget days together as an apprenTechnical Director, CIPHE 15mm pipe.forget I used to ask “Why? What II never forget those days asan an apprenthose as apprentice plumber, where Idays was bombarded happens if I of have 3 largeI Iwas double tice`rule plumber, where tice plumber, where wasbombarded bombarded with thumbs`, One being don`t never forget those days as an apprenII never forget those days as an never forget those days as anapprenapprentice I never forget those days as an apprenwith `rule of thumbs`, One being don`t radiators?” withmore of thumbs`, One being don`t feed than 3 radiators together off Itice never forget those days as an apprenTT/B/001 tice plumber, where I was bombarded plumber, where I was bombarded plumber, where I was bombarded with `rule tice plumber, where was bombarded feed more than 33where radiators together feed more than radiators together off tice plumber, I “Why? was bombarded I was just told “just do it,Iask that isbeing how it off 15mm pipe. I used to What with `rule ofof thumbs`, One don`t with `rule thumbs`, One being don`t of thumbs`, One being don`t feed more than with `rule of thumbs`, One being don`t 15mm pipe. IIthan used to ask “Why? with `rule of thumbs`, One being don`t 15mm pipe. used toradiators ask “Why? What feed radiators together off ifmore I have 33large double is”.happens As I progressed towards being aWhat feed more than 3 together off three radiators together off 15mm pipe. I feed more than 3 radiators together off happens ififpipe. II have 33large feed more 3large together off 15mm Ithan used toradiators ask “Why? WhatWhat happens have double radiators?” 15mm pipe. I used to double ask “Why? Chartered Engineer, I started to realise 15mm pipe. askask “Why? What used to ask “Why? What happens ifWhat I have happens ifI Iused have 3tolarge double 15mm pipe. I used “Why? radiators?” radiators?” happens if I have 3it,to large double I was just told “just do that is how it how dangerous these rule of thumbs radiators?” happens if I have 3 large double three large double radiators?” happens if I have 3 large double I never forget those days as an apprenwasradiators?” just told “just do it,it,that is how it IIbe, was just told “just do that how is”. As Iwas progressed towards being ait it can for apprentice Iespecially just “just it,it, that is is how tice plumber, where I do was bombarded radiators?” Iradiators?” was justtold told “just do that is how is”. As I progressed towards being a I was just told “just do it, that isa how is”. As IAs progressed towards being a it is”. IEngineer, progressed being Chartered Itowards started to realise with `rule thumbs`, being plumbers. Lets forget! was just told “just do it, that isdon`t how IChartered was told “just do it, that is being how ita it itI just is” . of As Inot progressed towards Engineer, IOne started to realise
Take the 'pressure' out of pipe design!
is”. Asthan I progressed towards being a Chartered Engineer, Irule started to realise Chartered started to realise feed more 3these radiators together off how dangerous of thumbs is”. As I Engineer, progressed towards being a how is”. As I progressed towards being arealise how dangerous these rule of thumbs Chartered Engineer, Irule started to realise how dangerous these of thumbs Chartered Engineer, I started to 15mm pipe. I used to ask “Why? What how dangerous these rule of thumbs can be, especially for “theory alone is useless” Chartered Engineer, I started tocan realise Chartered Iapprentice started to can be, especially for apprentice can be, especially for apprentice dangerous these rule of thumbs be, how dangerous these rule ofrealise thumbs happens if I Engineer, have 3 large double can be, especially for apprentice how dangerous these rule of thumbs plumbers. Lets not forget! “practical alone is dangerous” plumbers. Lets not forget! how dangerous these rule of thumbs plumbers. Lets not forget! especially for apprentice plumbers. Let's radiators?” can be,Lets especially for apprentice plumbers. not forget! canespecially be, especially for apprentice can be, for apprentice I was just told “just do it, that is how it not forget! plumbers. Lets not forget! “theory alone useless” “theory alone is plumbers. Lets not forget! “theory alone isisuseless” useless” plumbers. Lets not forget! is”. As I progressed towards being a “practical alone is dangerous” Imagine your customer complaining “theory alone is useless” “practical alone isisdangerous” “practical alone dangerous” “theory isisuseless” “theory alone useless” Chartered Engineer, Ialone started to realise “theory alone is useless” “practical alone isisuseless” dangerous” about excessive noise within the “practical alone “theory alone is how dangerous these rule ofdangerous” thumbs “practical alone is dangerous” “practical alone is dangerous” Imagine your customer complaining can be, especially for apprentice “practical alone is dangerous” heating system that you have just Imagine your customer complaining Imagine your customer complaining about excessive noise within the fitted, Imagine your customer complaining plumbers. Lets not forget! complaining Imagine your customer Imagine your customer complaining orabout the radiators or underfloor heating about excessive noise within the heating system that you have just excessive noise within Imagine your customer complaining about excessive noise within thefitted, heating about excessive noise within the “theory alone is useless” Imagine your customer complaining or the radiators or underfloor heating about excessive noise within the heating system thathave youjust have areheating not delivering enough heat to the system you have just fitted, about excessive noise within the system that that you fitted, orfitted, the “practical alone isyou dangerous” are not delivering enough heat to the heating system that have just fitted, excessive noise within the heating system that you have just fitted, or the radiators underfloor heating heating system that you have just fitted, orabout the radiators oror underfloor heating radiators or underfl oor heating are not room. Well it could actually be down to room. Well it could actually be down to or the radiators oryou underfloor heating heating system that have fitted, or the radiators orenough underfloor heating are not delivering enough heat toheating the ordelivering the radiators or underfloor delivering enough heat toheat thejust room. Well it ©© CIPHE are not incorrectly sized pipework! “Why isto CIPHE incorrectly sized pipework! “Why is the Imagine your customer complaining are not delivering enough heat tothe the or the radiators orbeunderfloor heating are not delivering enough heat to room. Well it could actually be down to are not delivering enough heat to the could actually down to incorrectly sized this?” room. Well it could actually be down to about excessive noise within the to betweento 250between to 350 Pa m. However, this?” room. Well it could actually be down to The amount flow rate 250 to 350 Pa m. However, of volumetric flow rateyou must understand ©amount CIPHEof volumetric are not delivering enough heat to the to room. Well it pipework! could actually be down to The incorrectly sized “Why is room. Well it “Why could be down pipework! isactually this?” the theory before heating system that you have just fitted, © CIPHE incorrectly sized pipework! “Why is required to deliver a specific amount of Pipework, fittings and other ancillary you must understand the theory before ©CIPHE CIPHE incorrectly sized pipework! “Why © incorrectly sized pipework! “Why isisto room. Well itsized could actually be down making such assumptions required to deliver a specific amount of this?” © CIPHE Pipework, fittings and other ancillary incorrectly pipework! “Why is or the radiators or underfloor heating to between 250 to 350 Pa m. However, heat is calculated using the simple flow rate The amount of volumetric that are fitted within a this?”equipment to between 250 to 350 PaHowever, m. However, making such assumptions this?” The amount of volumetric flowrate rate © this?” between 250 to 350 m. Pipework, fittings andwithin other ancillary Pipe sizingto isto an easy process when you incorrectly sized is of are not delivering enough heat the between 250 to 350 Pa m. However, you must understand thePa theory before heat isCIPHE calculated using the simple The amount volumetric flow this?” equipment that are fitted atoflow formula (1) . to deliver The amount ofof volumetric flow raterate system create apipework! resistance to“Why the to between 250 to 350 Patheory m. However, required a specific amount of Pipework, fittings and other ancillary The amount of volumetric flow you must understand the before knowofhow,you although itunderstand isunderstand important toprocess you must the theory before room. Wellfittings it could actually be down to equipment that are creates fi ttedother within a system required to deliver a specific amount must the theory before Pipe sizing is an easy when you Pipework, and other ancillary making such assumptions this?” water, which in turn a pressure required to deliver a specific amount of to between 250 to 350 Pa m. However, Pipework, fittings ancillary required to deliver a specific amount of Pipework, and other ancillary formula (1) . you must understand the theory before system create a resistance to the flow of The amount of volumetric flow rate heat is calculated using the simple Question equipment that are fitted within a understand some simple housekeeping making such assumptions required to a specific amount Pipework, fittings and ancillary making such assumptions © CIPHE making such incorrectly sized pipework! “Why create athat resistance to other the flow ofis The amount of deliver volumetric flthe owsimple rate required of Pipe 250 to 350 Pa.m. However, mustbefore know how, although itthe isyou important heat isisiscalculated using the simple loss through friction. equipment are fitted within awater, you must understand theory sizing isassumptions an easy process when youto heat calculated using simple equipment that fitted within heat calculated using the equipment are fitted within aa of Calculate making such assumptions rules. formula (1) . required to deliver a specific amount of water, which in turn creates a pressure system create a resistance to the flow Pipework, fittings and other ancillary the required volumetric flow this?” heat is calculated usingofthe simple equipment that are fitted within a of Pipe sizing is an easy process when which in turn creates a pressure loss to deliver a specifi c amount heat is understand the theory before making such you to between tosimple 350 m. However, Pipe sizing is250 an easy when you Question Pipe sizing isalthough an easy process when you understand some housekeeping The amount of flow rate making such assumptions how, itprocess is Pa important to formula (1) .. . volumetric system create ainupon resistance to formula (1) formula (1) system create athe resistance to the flowof ofrate system resistance to the flow Dependant amount of flow Before youknow calculate the pipe flow based upon the following system Pipe sizing is an easy process when you heat is calculated using the simple water, which turn creates athe pressure equipment that are fitted within aflow loss through friction. you must understand the theory before know how, although it is important to know how, although it is important to know how, although it is important to formula (1) . through friction. calculated using the simple formula (1) . assumptions system create a resistance to the flow of Question required to18 deliver a specific of some simple housekeeping Pipework, fittings and ancillary velocity, itunderstand isrules. important to ask the required to deliver aother specific amount of parameters; (1) kW heat load (2) amount water, which in turn creates a pressure water, creates a pressure Pipe sizing is an easy process when you water, which in turn creates a pressure Calculate the required volumetric flow know how, although it is important to making such assumptions formula (1) . loss through friction. Question Question system create aare resistance to the Question understand some simple housekeeping understand some simple housekeeping understand some simple housekeeping Pipe sizing is an easy process when you heat is calculated the simple equipment that fitted within a flowofof Specific rules. water, in turn creates adesign pressure manufacturer for the “internal” diameter heat capacity ofusing watervolumetric 4.19 heat, the correct selection and know how, although it is important to losswhich through Calculate the required flow loss through friction. Dependant upon the amount of flow 1 Question loss through friction. Before you calculate the pipe flow rate based upon the following system understand some simple housekeeping Pipe sizing is an easy when rules. rules. water, whichupon turn creates athat pressure of their pipework. rules. kJ/kg.K (3) Temperature difference of 10 flow formula (1) upon .the Dependant upon the amount offlow fl ow of know how, although itthe isprocess important to you Calculate volumetric system create ain resistance to the Calculate therequired required volumetric flow pipework is critical to ensure the Question Dependant the amount of flow loss through friction. Calculate the required volumetric flow Before you calculate pipe flow understand some simple housekeeping rate based the following system o parameters; (1) 18 kW heat 3load (2) know how, although itpipe isto important to velocity, it is important ask the required to deliver a specific amount of rules. C. (4) Density of water 0.977 kg/m . Dependant the amount of flow Dependant upon amount of flow Before you calculate the flow loss through friction. rate based upon the following system Calculate the required volumetric flow Before you calculate the pipe flow water, which in turn creates a pressure rate based upon the following system required to deliver a specifi c amount of Calculate the required volumetric fl ow rate understand some simple housekeeping rules. heat emitter (e.g aaradiator oramount floor Dependant the amount of flowof Before calculate pipe rate based upon following system velocity, it isyou important tothe ask the flow required toupon deliver specific parameters; (1) 18 the kW heat load (2) Question rules. understand some simple housekeeping Calculate the required volumetric flow manufacturer for the “internal” diameter heatthe capacity ofheat water 4.19 velocity, it is important to ask Dependant upon the amount of flow required a and specific amount parameters; (1) 18 kW (2) heat, the correct design ofof velocity, itcalculate is to ask the required toselection deliver specific amount of Specific parameters; (1) 18the kW heatload load (2) Before you the pipe flowit loss through friction. rate based upon following system system) isa supplied the correct heat, correct selection and design ofof based upon following system parameters; Before you the pipe flthe ow velocity, Answer manufacturer for the “internal” diameter velocity, itimportant iscalculate important to ask the required deliver specific amount Specific heat capacity of water 4.19 rules. parameters; (1) 18 kW heat load (2) heat,heating thetothe correct and design of Dependant uponselection the amount of flow Calculate the required volumetric flow Before you calculate the pipe flow rate based upon the following system 18 manufacturer for the “internal” diameter Specific heat capacity of water 4.19 of their pipework. manufacturer for the “internal” diameter kJ/kg.K (3) Temperature difference of 10 heat, selection and design of Specific heat capacity of water 4.19 volumetric flow ofensure heated water. velocity, it is important to ask the heat, the correct selection and design of required to deliver a specific amount of parameters; (1) 18 kW heat load (2) pipework is critical to ensure that the heat (a) 18 kW heat load (b) Specifi c heat capacity of is important to ask the manufacturer for the pipework is critical to that the ofvelocity, their pipework. kJ/kg.K (3) Temperature difference of 10 Dependant upon theatoamount of flow manufacturer for the Specific heat ofdifference water 4.19 0.44 l/sec =(1)capacity you the pipe flow diameter based upon thekW following system heat, the correct selection and design pipework critical ensure that the ofof o rate it iscalculate important to“internal” ask the required tois deliver specific amount parameters; 18 heat load (2) 3of 10 ofBefore their pipework. kJ/kg.K (3) Temperature of their pipework. kJ/kg.K (3) Temperature difference pipework to ensure that the C. (4) Density of water 0.977 kg/m owater 3 . of 10of manufacturer for the “internal” diameter Specific heat capacity of water 4.19 pipework is critical ensure that the emitter (e.g a radiator or fl oor heating 4.19 kJ/kg.K (c) Temperature difference ‘internal’ diameter of their pipework. (4.19 * 0.977 * 10) heat, the correct selection and design of velocity, is important to ask the Inemitter addition to the effect on the delivery C. of18water 0.977 kg/m required to (e.g deliver specific amount parameters; (1) kW heat load (2)3. 3 of 10 heat emitter a radiator orand floor of theirit pipework. kJ/kg.K (3) Temperature difference oo(4) Density heat (e.g aato radiator or floor manufacturer for the “internal” diameter pipework critical ensure that theofof Specific heat capacity of water 4.19 C. (4) Density ofofwater 0.977 kg/m . heat, the is correct selection design water 0.977 kg/m o C. (4) Density 3 heat aundersized radiator or floor of their pipework. (3) capacity Temperature difference heat emitter (e.g radiator orvolumetric floor for the “internal” diameter system) iscritical supplied the correct 10 C. (d)Density Density of water kg/m . .3.of 10 manufacturer o kJ/kg.K Specific heat of0.977 water 4.19 of heat, incorrect or heat, the correct selection and design of pipework is to ensure that the C. (4) of water 0.977 kg/m heating system) is supplied the correct of their pipework. Answer kJ/kg.K (3) Temperature difference of 10 heating system) is supplied the correct Answer heat emitter (e.g a radiator or floor Tip pipework is critical to ensure that the o 3 of their pipework. heating system) is supplied the correct (3) Temperature difference of 10 Answer Density of water 0.977 kg/m . pipework can lead to excessive heating system) is supplied the correct kJ/kg.K fl ow is of critical heated water. pipework to ensure that the Answer o C. (4) 18 heat emitter (e.g aheated radiator or flow floor kg/m33.. o C. (4) Density of water 0.977 18 volumetric flow ofsupplied water. volumetric flow(e.g of heated water. C. (4) Density of water 0.977 kg/m 18 heating system) is the correct When heat emitter (e.g floor Answer volumetric flow of heated water. 1 designing a heating pipe system, velocities which inradiator turn creates noise. heat emitter a aradiator oror floor volumetric flow of heated water. 0.44 l/sec 0.44 l/sec ==== 0.44 l/sec heating system) is supplied the correct Answer 18 * 10) 0.44 l/sec and heating engineer These high can also cause heating system) issupplied supplied the correct of the plumbing volumetric flow ofthe heated water. Answer system) is the correct (4.19 0.977 Answer In addition to effect on the delivery In addition to velocities the effect on the delivery (4.19 ***0.977 (4.19 0.977 18 * *10) Inheating addition to the effect on the delivery In addition to the effect on the delivery (4.19 *18 0.977 10) 0.44 l/sec = volumetric flow of heated water. must design the pipework to ensure In addition to the effect on the delivery 18 cavitation at elbows, pumps and valves, volumetric flow ofofor heated water. volumetric flow heated water. heat, incorrect undersized pipework can water velocities 0.44 l/sec = of heat, incorrect or undersized 0.44 l/sec = of heat, incorrect or undersized (4.19 * 0.977 * 10) do not exceed recom0.44 l/sec = ofIn heat, incorrect or effect undersized addition toincorrect the on the of heat, orlead undersized which can ultimately to thedelivery system Tip Tip (4.19 * 0.977 * 10) lead toto excessive flow velocities which in mended (4.19 * 0.977 * 10) In addition to the effect on the delivery levels. InIn addition the effect on the delivery Tip Tip pipework can lead to excessive flow (4.19 * 0.977 * 10) pipework can lead to excessive flow addition to can the effect the delivery failure. pipework toon excessive flow of heat, incorrect orlead undersized pipework can lead to excessive flow turn creates noise. These high velocities ofof heat, incorrect or undersized heat, incorrect or undersized When designing a aheating pipe system, © CIPHE velocities which inor turn creates noise. Tip When designing pipe system, velocities which in turn creates noise. 28mm OD / 25.6mm ID of heat, incorrect undersized When designing aheating heating pipe system, velocities which in turn creates noise. Tip pipework can lead to excessive flow When designing a heating pipe system, velocities which in turn creates noise. Tip Formula pipework can lead to excessive flow can also cause cavitation elbows, Tip the plumbing and heating engineer hat also the plumbing and heating engineer Velocity pipework can lead to excessive flow These high velocities can also cause These high velocities can cause Pipe Diameter the plumbing and heating engineer pipework can lead to excessive flow These high velocities can also cause V = Once the internal pipe diameter is When designing a heating pipe system, velocities which inturn turnwhich creates noise. the plumbing and engineer When designing aheating heating pipe system, velocities which in creates noise. These high velocities also cause pumps and valves, ultimately When designing athe heating pipe system, the plumbing must design pipework toto ensure (m/s) must design the pipework to ensure (mm) (1) cavitation at elbows, pumps and valves, cavitation at elbows, pumps valves, When designing aheating heating pipe system, (Cp *creates ρcan *and T) velocities which incan turn noise. must design the pipework ensure known, the flow area is then calculated When designing aheating heating pipe system, velocities which in turn creates noise. cavitation at elbows, pumps and valves, must the plumbing and engineer the plumbing and engineer These high velocities can also cause design the pipework to ensure These high velocities can also cause water velocities do not exceed recomlead to the system failure. and heating engineer must design the pipework to water velocities do notnot exceed recomcavitation at elbows, pumps and valves, which can ultimately lead to the system (1) water velocities do exceed recomwith formula (2). the plumbing and heating engineer which can ultimately lead to the system These high velocities can also cause 15 50 0.75 1.15 the plumbing and heating engineer must design the pipework to ensure which can ultimately lead to the system These high velocities can also cause V at must design the pipework torecomensure cavitation elbows, pumps and valves, Volumetric flow rate mended levels. water velocities do not exceed mended levels. ensure water velocities do not exceed cavitation at elbows, pumps and valves, mended levels. failure. which can ultimately lead to theand system must design the pipework torecomensure water velocities do not exceed failure. must design the pipework to ensure cavitation atelbows, elbows, pumps and failure. Temperature difference (ovalves, C)valves, Table which can lead to the system T ultimately cavitation at pumps water velocities do not exceed recom1: Typical waterlevels. velocities for small bore Formula© recommended mended levels. CIPHE which can ultimately lead to the system ©© CIPHE mended levels. 25.6mm IDID water velocities do not exceed recom2 // water velocities do not exceed recomCIPHE failure. Heat flowlead rate (kW) 28mm pipework (BSRIA) h ultimately Area (m2)28mm = 28mm 3.142 OD *OD rOD failure. which can ultimately lead to the system /25.6mm 25.6mm ID mended levels. which can to the system Formula Formula h (2) Velocity Formula failure. Pipe Diameter mended levels. h Cp Specific Heat Capacity © CIPHE mended levels. Velocity h (kJ/kg.K) Pipe Diameter 28mm OD // 25.6mm ID Velocity A starting point could also be to limit V = Once the internal pipe diameter is 28mm OD 25.6mm ID Pipe Diameter failure. failure. V = Once the internal pipe diameter is Formula © CIPHE 3 (m/s) V(kg/m = (Cp r = Internal pipe internal radius (m) Once the pipe diameter is (mm) ρ Formula Density h) * ρ * T) (1)(1) the pressure 28mm OD / 25.6mm ID (m/s) Velocity (mm) loss per metre of pipe Pipe Diameter (m/s) known, the flow area is then calculated h © CIPHE (mm) © CIPHE * ρ ** ρ *T) T) (1) Velocity Pipe Diameter Once the internal pipe diameter is known, the flow area is then calculated Formula VV== (Cp(Cp 28mm OD / 25.6mm Once the internal pipe diameter is known, the ID 28mm OD / 25.6mm ID known, the flow area is then calculated (m/s) (mm) Once the internal pipe diameter is Velocity (1) Formula V = (Cp * ρhh*h T) (1) Formula Pipe Diameter with formula (2). 15 -Diameter 50 0.75Velocity 1.15 the flow areapipe is then calculated (m/s) with formula (2). (mm) flknown, ow area is then calculated with formula (2). Once the internal diameter is V with formula (2). Pipe Pipe Volumetric rate (1)(1) (1) 15 -Diameter 50 0.75 --1.15 15 - 50 0.75 -Velocity 1.15 (Cp *flow ρ *flow T) V V (m/s) known, flow isdiameter then calculated VVVolumetric = Once thethe internal pipepipe is is Volumetric rate =(Cp Once the internal diameter (mm) (1) with formula (2). area flow rate * ρ * T) 15 50 0.75 1.15 o(1) (m/s) (m/s) known, the flow area is then calculated V Temperature difference ( oC)(1) (mm) T Volumetric flow**rate (Cp ρρ ** T)T) Table 1: (mm) Typical water velocities for small bore Formula (Cp known, the the flow areaarea is then calculated difference (o(1) C)((1) with formula (2).flow known, is then calculated T T Temperature Temperature difference C) Table 1: Typical water velocities forfor bore Formula 15 - 50 0.75 -small 1.15 Table 1: Typical water velocities small bore Formula Heatflow flow rate (kW) (oC) (1) Temperature difference with formula (2).(m2)2=2 3.142 * r 2 22 VT pipework (BSRIA) hVolumetric Area rate Table 1: Typical water velocities for small bore 15 50 0.75 1.15 Formula (1) with formula (2). HeatHeat flowflow rate (kW) (1) rate (kW) V h h Heat with formula (2). pipework (BSRIA) Area (m ) = 3.142 * r(2) pipework (BSRIA) Volumetric flow rate Area (m ) = 3.142 * r 2 15 50 0.75 1.15 2 15 - 50 0.75 - 1.15 flow rate (kW) V pipework (BSRIA) Cp Volumetric Specificdifference Heat Capacity flow rate Volumetric flow rate(o(kJ/kg.K) C)(o(kJ/kg.K) A1:starting point could alsofor besmall to limit Specific HeatCapacity Capacity CpTemperature Specific Heat Capacity (kJ/kg.K) Table Typical water velocities bore Temperature difference 3 Heat (kJ/kg.K) oC) AA starting point could also to limit A starting point could also be to limit o ρ Specific Table 1:Typical Typical water velocities for small bore Density (kg/m ) starting point could also bebe to limit the Temperature difference ( C) A starting point could also be to limit Temperature difference ( C) the pressure loss per metre of pipe Table 1: water velocities for small bore 3 3 flow rate (kW) Table 1: Typical water velocities for small bore 3 ) pipework (BSRIA) ρHeat Density (kg/m Density (kg/m ) Heat flow rate Density (kg/m )(kW) the pressure loss per metre of pipe the pressure loss per metre of pipe pipework (BSRIA) the pressure loss per metre of pipe pressure loss per metre of pipe to between Heat flow pipework (BSRIA) HeatHeat flowrate rate(kW) (kW)(kJ/kg.K) pipework (BSRIA) Specific Capacity Specific Heat Capacity (kJ/kg.K) point could also bebe to to limit Cp Specific A starting point could also limit Cp SpecificHeat HeatCapacity Capacity(kJ/kg.K) (kJ/kg.K) A starting
V T TCp Cp TT h ρh ρ h CpCp h h
ρ ρρ
ρ
3 3 Density (kg/m ) 3) Density (kg/m
Density Density(kg/m (kg/m)3)
p13 and 14 new techtalk.indd 13
A starting point could also be to limit
Area (m ) = 3.142 * (2) r(2) (2) 2 Formula r= pipe radius =Internal Internal pipe radius (m) Formula Area (m ) =2 (m) 3.142 rr = Internal pipe radius (m) * r 2 2
Formula r = Internal pipe radius (m) Formula
A startingloss point could also be to limit 2017 January/February the pressure per metre ofofof pipe the pressureloss loss per metre pipe the pressure per metre pipe the pressure loss per metre of pipe
Area r 2 2) = 3.142 Area (m2(m )(m = 3.142 * r 2 **(2) Area ) = 3.142 r (2) (2) (2) r = rInternal pipe radius (m) = Internal pipe radius (m) |r = Internal journal | 13 pipe radius (m) r = Internal pipe radius (m)
05/01/2017 11:34
with Paul Harmer Technical Director, CIPHE
hin the have just fitted, floor heating h heat to the ly be down to TT/B/001 © CIPHE k! “Why is
Take the 'pressure' out of pipe design!
The amount of volumetric flow rate required to deliver a specific amount of her ancillary heat is calculated using the simple within a I never forget those days as an apprenformula (1) . e to the flow of tice plumber, where I was bombarded es a pressure with `rule of thumbs`, One 2 being don`t Question
to between 250 to 350 Pa m. However, you must understand the theory before making such assumptions
Pipe sizing is an easy process when you know how, although it is important to understand some simple housekeeping rules.
feed more than 3 radiators together off Calculate the required volumetric flow 15mm pipe. I used the to ask “Why? What Calculate internal flow area of a ount of flow Before you calculate the pipe flow rate based upon the following system happens if28mm I havecopper 3 large double pipe. velocity, it is important to ask the ific amount of parameters; (1) 18 kW heat load (2) radiators?” manufacturer for the “internal” diameter Specific heat capacity of water 4.19 n and design of 2 that is how it I was just told “just do it, of their pipework. kJ/kg.K (3) Temperature difference of 10 ure thatis”. theAs I progressed towards being a o 3 C. (4) Density of water 0.977 kg/m . or or floor Chartered Engineer, I started to realise ed the correct how dangerousAnswer these rule of thumbs 18 d water. can be, especially for apprentice 0.44 l/sec = plumbers. Lets not forget! (4.19 * 0.977 * 10) n the delivery “theory alone is useless” rsized Tip is dangerous” alone essive flow “practical Once both the internal flow area and the When a heating pipe system, eates noise. flow rate designing are known, the water velocity the plumbing andusing heating engineer Imagine your customer complaining can then be calculated formula (3). also cause must design the pipework to ensure about excessive noise within the mps and valves, 3 have water velocities dojust notfitted, exceed recomheating system that you d to the system mended levels. or the radiators or underfloor heating © CIPHE are not delivering enough heat to the 28mm OD / 25.6mm ID h room. Well it could be down to Velocity Pipeactually Diameter Once the internal pipe diameter is (m/s) © CIPHE sized pipework! (mm) “Why is (1) ρ * T)incorrectly known, the flow area is then calculated this?” to between 250 to 350 Pa m. However, (1) The amount with of volumetric flow rate formula (2). 15 50 0.75 1.15 3 w rate youFigure must understand the theory before A typical valve could be a thermostatic 3: Grundfos pump curve with the required to deliver a specific amount of Pipework, fittings and other ancillary fference (oC) mixing valve used within an underfloor making such assumptions example system duty point Table 1: Typical water velocities for small bore Formula heat isheating calculated using the simple equipment that are fitted within a system, or even a magnetic lter. kW) pipework (BSRIA) Area (m2) =fi3.142 * r 2 sizing is an easy process when you Pipe The pressure loss through a formula (1) . system create a resistance to the flow of (2) apacity (kJ/kg.K) know how, although it is important to pointacould also be to limit thermo-static mixing valve varies water, whichAinstarting turn creates pressure = Internal pipe radius (m) understand some simple housekeeping dependant upon rthe flow rate, however, the pressure loss per metre of pipe Question loss through friction. with a flow rate of 0.44 l/s, this could Referring to figure (2) and the rules. Calculate thetorequired volumetric equate a pressure loss of in flow excess of previous calculations, a 28mm copper Dependantpipe upon amount of with flow a flow rate based Before you calculate the pipe flow upon system 40,000 Pa inthe the following valve alone. willthe deliver 0.44 l/s m/s and create velocity, it is important to ask the required tovelocity deliverofa 0.86 specific amount ofa pipe parameters; (1) 18 kW heat load (2) To heat ensure that your is ‘fit for pressure loss of 300 Pa.m. manufacturer for the “internal” diameter Specific capacity of system water 4.19 heat, the correct selection and design of purpose’, always ensure that you request of their pipework. kJ/kg.K (3) Temperature difference of 10 pipework is critical to ensure that the the technical datasheet of any product o 3 C. (4)from Density of water 0.977 kg/m . the manufacturer prior to installing heat emitter (e.g a radiator or floor and designing a system. heating system) is supplied the correct Answer 18 volumetric flow of heated water.
0.44 l/sec =
(4.19 * 0.977 * 10) In addition to the effect on the delivery Once your heating pipework system is of heat, incorrect or undersized designed and you have calculated your Tip pipework can lead to excessive flow system “Index circuit” pressure loss, duty point is then plotted onto a Whenthe designing a heating pipe system, velocities which in turn creates noise. suitable pump curve figure (3). the plumbing and heating engineer These high velocities can also cause Always ensure that the system duty must design theunderneath pipeworkthe to ensure point falls pump curve cavitation at elbows, pumps and valves, to ensure correct operation.The index water velocities do not exceed recomwhich can ultimately lead to the system pressure levels.loss in this example Figure 2: Limited data taken from the mended failure. is 25 kPa or 25,000 Pa pipe pressure loss table for copper pipe i/B/002 Based Formula‘Heating pipe design’ upon the Haalandhequation method.
V=
Velocity Heating design is a complex subject, Pipe Diameter therefore, not be (m/s) (mm) this article must
However, when (1) (Cp *designing ρ * T) a complete used as a design guide. If you have heating system, it is not only the any- 50 questions on the0.75 article, then (1) pipework that you need to consider, 15 - 1.15 Volumetric flowvalves rate also please email Paul Harmer on pipe fittings and paulh@ciphe.org.uk Temperature difference (oC) need consideration. Table 1: Typical water velocities for small bore
V T h Cp
ρ 14
Heat flow rate (kW)
pipework (BSRIA)
Specific Heat Capacity (kJ/kg.K) Density (kg/m3)
A starting point could also be to limit the pressure loss per metre of pipe
|
p13 and 14 new techtalk.indd 14
journal
|
Figure 4: CIPHE i/B/002 (Design Guide) ‘Heating Pipe Design’ Planned publication 2017. © CIPHE
28mm OD / 25.6mm ID
Once the internal pipe diameter is known, the flow area is then calculated with formula (2).
Formula
Area (m2) = 3.142 * r 2
(2)
r = Internal pipe radius (m)
January/February 2017
05/01/2017 11:34
p15_phejan17.indd 1
09/12/2016 11:05:06
with Peter Adkins Solicitor, Emms Gilmore Liberson Solicitors icitors
What happens when things wrong? Liability Don’t lose your coolgowith theProduct consumer! You may have last year about We all know howseen important plumbing the to Consumer and extension heating systems are to our‘cooling lifestyle. off’ periods 7 to 14 days.or Whether it is afrom home installation
for commercial everyone who is to What may notuse, have been obvious involved from manufacturer, supplier those in the trade is how important to installer wants every system to work this piece of legislation is to you. perfectly. But, what happens when Ignore it at your peril – do so and it things go wrong? could cost you money (and reputation)! Problems can occur with all types of installations from boilers, unvented hot In a nutshell, if you do not comply water cylinders, thermostatic control with the requirements of the new valves to risk simple A the Act you notsanitary gettingfittings. paid for faulty product or installation can work you do and also prosecution cause damage to other objects (e.g. by by your local Trading Standards.
flooding) or in the worst-case scenarios,
Many think that off personal injury or the evencooling death. These mercifully rareapplies events to cangoods. cause aIt also period only multitude legal claims. of services’. applies toof ‘the provision This includes plumbing, building Thereelectrical is no substitute and works. for seeking legal advice as early as possible, but
Consumers have 14 days from theon we set out below, some comments date they placed an order by common claims. phone, internet, by mail order or at their home, to cancel with you. Civil liability The firstcancel area ofwithin claim isthis based on If they period, civil liability (as opposed to criminal). they have a right to a refund of Problems arising may lead to claims monies paid. for breach of contract, in Tort or for
As the statutory businessduty supplying breach for the the cost of remedying repairs and service youthe areproblem, required to provide possible consequential loss. of your the customer with details business including address, phone The Tort (civil wrong) will normally numbers, their cancellation rights be either negligence or specific and how to cancel. manufacturer’s liability. Where there
If do not, then thebetween cooling off areyou intermediate parties period is extended 14 days from the manufacturer andtoconsumer, the manufacturer may escape liability. This the day the information is supplied. may involve questions around training Well worded terms of business and and inspection, overall quality control order forms are an absolute as well as processes used to select must here.intermediaries. competent
What about emergency repair There are statutory duties imposed in work? You are contacted by a the construction industry, which can homeowner by telephone to carry result in liability to contract and out urgent workakin to stop flooding, Tort. There could also be a claim in sort out faulty heating or clear a negligence for general damages for drain. The work is carried out personal injury and past and future within the 14 day period. The repair financial losses. work having been completed, the consumer mayathen to arise cancel Most seriously, claimtry may the contract. do you under the FatalWhat Accidents Actdo? 1976 for Maybe the work but the bereavement andisn’t loss urgent of dependency, or a claim for general damages for consumer wants it started within personal injury. the 14 days?
p16_smarttalk.indd 16
Criminal liability But what about any criminal liability? The answer is yes, often the They may want to could fit in with circumstances of ayou claim possibly other tradesmen, or have work lead to criminal proceedings.the Trading finished before a deadline they Standards will normally become have? Or perhaps job involved where thereanother are claims involving potentially unsafewith products cancels and you arrange the and any breaches legislation arethan customer to startofwork earlier often ‘strict’ liability. you expected?
What dodoyou do? Ideally you wait Can you anything to mitigate until the 14 days period has expired this possibility? Trading Standards but that is often departments have impractical. a limited budget and generally as a last resort In allenforce of these cases you should but don’t assume this will leave you ensure that before you start work, free of prosecution. Speak to your the consumer has been given all the legal advisers and insurers as soon as relevantWe information about possible. often consider it isyour best to business, and notice of their rights engage with Trading Standards as soon to cancel and signed authority as you are aware of any potential orto carry out the work within the 14 actual problem. days period.
its directors may be prosecuted and fined and a director can be imprisoned. Criminal liability for a director generally The consumer should sign an order involves acting knowingly or with form confirming the work to be neglect. This is a tricky area and you carriedseek outurgent and the price. The form should advice.
should also contain your terms and
Accidents conditions and give the details of Accidents at work/on cancellation rights. a construction site must be reported and may be If they needbythe carrying out investigated thework Health and Safety urgently, then signing the form Executive. They also can prosecute will confirm they beenIf agiven the companies andhave directors. fatality notice,the and, despite that, they want occurs, Crown Prosecution Service youlikely to start are to bework. involved with the HSE.
This will make it far easier to deal
Imprisonment up to life is available for with attempted cancellation and some offences or a charge of Corporate you should normally the full Manslaughter under therecover 2007 Act.
amount agreed for emergency works,both or otherwise a sum Under manslaughter and dependent upon how the much Corporate Manslaughter, linkof the works were carried out before between the faulty product and death only has to be ‘a’ cause and not cancellation.
Whether youby arereviewing an installer,your supplier or How? Start order manufacturer, it is helpful to show safe necessarily ‘the’ cause. Even a minimal forms urgently. practices, good training and awareness causal link may be enough even where of Peter relevant consumer and safety there is more thanSolicitors one cause.based In a faulty Adkins is a Solicitor with Emms Gilmore Liberson in regulations. Further that you have product case, the immediate cause Birmingham. Peter has been involved with the CIPHE for many years and identified any issues and taken action may be a failed component and so the regularly advises CIPHE members of all types of legal issues. He can be to prevent further breaches. This may supplier may be responsible, but the contacted at padkins@egl-law.com 0121 314 0000 well assist in avoiding prosecution. producer of the product may also be For some offences, a company and involved if its quality control is poor.
Proud to be a Professional with knowledge from smarttalk
This overview is to be treated as an illustration of what can arise in any situation and should not be treated as specific legal advice, every case is different. Should TM you experience any of these issues you should seek immediate legal advice.
12/01/2017 09:54
CIPHE NEWS
RICHARD SOPER AWARDED FELLOWSHIP
BY THE UNIVERSITY OF WORCESTER With a career spanning four decades, Richard Soper has been presented with a Fellowship by the University of Worcester, in recognition of his dedication to the plumbing and heating industry.
R
ichard has always maintained his roots in the Worcester area and has devoted a huge amount of personal time, energy and business expertise to the plumbing and heating sector, as well as in the wider community. Having started his working life at what he likes to call ‘the sharp end of the heating industry’, Richard joined West Midlands Gas in the early 1960s, where he embarked upon a ‘hands on’ technical apprenticeship. Further into his career, Richard joined Worcester Heat Systems Ltd as Sales and Marketing Director and in 2001 he became Managing Director of Bosch Thermotechnology Ltd. During this time, he became the Grantee for Bosch Thermotechnology Ltd.’s Royal Warrant;
an accolade the company still proudly upholds today. This was shortly followed by a CBE for Richard in The Queen’s Birthday Honours List, for services to the heating and renewable technologies industries.
NO REST… Following his retirement from the position of CEO at Bosch Thermotechnology, Richard took on the voluntary role as Director of International Development at the CIPHE. Beyond this role, Richard has also taken on a number of other positions including Chair of the Worcester Community Trust and School Governor at Regency High School, which provides care and support for students between age 11 and 19 years with a range of additional needs.
Richard Soper and his wife, Sandy
MEMBERSHIP SERVICES
CAN YOU BE AN AMBASSADOR
FOR THE CIPHE? Marie McCaffrey, Membership Manager and Exhibition Liaison
This year, the CIPHE will have a presence at a number of high-profile industry exhibitions across the country, including PLUMBEXPO, PHEX and Installer.
I
f you are a CIPHE member who has a talent for speaking to like-minded industry professionals and the ability to promote professionalism, then we’d like to hear from you with the potential of working together to represent the Institute at these events.
PLUMBEXPO Kick-starting the year, the CIPHE will be attending PLUMBEXPO, which is opening its doors for the first time at Alexandra Palace on the 1st and 2nd of February and again at EventCity in Manchester from 9th − 10th March. The exhibition has been developed to provide installers
and contractors in the plumbing and heating sectors with a dynamic, regional tradeshow where they can speak to industry professionals face-to-face and check out product benefits in a hands-on environment.
PHEX We are also gearing up to be at all three PHEX exhibitions taking please at Alexandra Palace, London (9th − 11th May), Manchester (4th – 5th October) and Chelsea (15th – 16th November). These will be fantastic events and provide a great platform to highlight what the CIPHE has been doing and outline future plans.
INSTALLER Installer, the heating and plumbing show is taking place between 9th and 11th May. This too is the perfect opportunity for the Institute to reach installers who are keen to meet face-to-face with industry bodies and leading manufacturers, merchants and suppliers from across the industry
If you would like to be involved in any of the above events, please contact Marie McCaffrey at the CIPHE on +44(0)1708 463 104 or email your interest to mariem@ciphe.org.uk
January/February 2017
|
journal
|
17
TRAINING MATTERS
TRAINING MATTERS
ALL THAT MATTERS IN THE TRAINING WORLD
WINTER OF DISCONTENT As Carol Cannavan is now enjoying her retirement, writing the Training Matters column has fallen to me. Hopefully, I’ll live up to expectations (Carol still reads the p&he Journal…), but like anything new, there is a learning process to go through.
Jenni Preston
T
alking of new things, apprenticeship funding is having a rather turbulent time. In mid-November, members of the Welsh Assembly joined the Northern Ireland Executive in giving outright opposition to the introduction of the Apprenticeship Levy. Likewise, big business in Scotland is calling for greater clarity on the scheme, which is set to be introduced on 6th April 2017. The Levy is all part of Government plans to raise the number of apprenticeships and plug the skills gap. The Levy requires all employers operating in the UK, with a pay bill over £3 million each year, to invest 0.5 percent of their total annual pay bill in apprenticeships. A £15,000 allowance means that employers over the £3 million mark get £15,000 off their 0.5 percent bill. Employers who are too small to pay the Levy will only have to pay 10 percent of apprenticeship costs, with 90 percent of the costs of training paid for by the state. It all sounds good in theory. However, there are concerns that in many areas (due to other cuts) the new funding system won’t actually increase apprenticeship budgets. With two of the UK’s devolved assemblies rejecting the scheme, and Welsh Labour Skills Minister, Julie James, exclaiming, that: "The
18
|
18_training matters.indd 18
journal
|
levy is nothing more than a UK Government employment tax which directly conflicts with areas of devolved competence," it seems there could be a winter of discontent ahead...
QUALITY APPRENTICESHIPS ON A GLOBAL STAGE As if there wasn’t enough going on in the training industry already, the Policy Exchange has issued its latest white paper entitled, ‘Need, And Why We Don’t Have Them: How Apprenticeships should be reformed to make the UK compete on the global stage.’ The White Paper blasts the current standard of apprenticeships, claiming that the Government is wasting up to half a billion pounds on sub-standard training. We all know that the apprenticeship framework had its issues, which is why the new Trailblazers are being put in place. However, the White Paper raises concerns that even the new frameworks are not hitting world-class standards – they simply cannot compete on an international level. Locally, learning via the apprenticeship route may be improving in leaps and bounds, but we still fall far short of a world-beating system. Interestingly one of the key recommendations is to move away from the target of having three million apprenticeships by 2020. Instead, the emphasis should be on quality of the training provided, not the quantity of
learners passing through the system. It goes further to say that, apprenticeships should only receive government money if they are high quality. In essence, the bar has to be raised, but will it be enough to create an internationally renowned system? It will be a while before we know which way apprenticeships will go, but in the meantime, the new plumbing and heating Trailblazer courses look set to make a big impact on the quality of learning in our industry.
APPROVED TRAINING CENTRES It’s been a double whammy of high-profile, training centre approvals from the CIPHE of late. Pegler Yorkshire gained Approved Training Centre accreditation for their new state-of-the-art Doncaster training centre, and Worcester, Bosch Group has received Approved Training Centre status across its four Training Academies at Worcester, Clay Cross, Wakefield and West Thurrock. Congratulations to everyone involved.
Don’t forget that if you are involved in training, you can have the opportunity to have your facility approved by the CIPHE too, please email the Membership Department at membership@ciphe.org.uk
January/February 2017
05/01/2017 12:13
THE BONFIELD REVIEW
THE BONFIELD REVIEW – EACH HOME COUNTS Almost when no one was looking, The Bonfield Review – Each Home Counts, was published the week before Christmas.
T
he review into the Government’s energy efficiency policy by BRE Chief Executive, Peter Bonfield, was due to be published in March 2016, but was repeatedly pushed back. So was it worth the wait? The review was launched in 2015 by the Department of Energy and Climate Change (DECC), after the failure of the Green Deal. It was to make recommendations about how consumers can be protected and advised when installing energy efficiency and renewable energy measures in their homes. Although acknowledged by industry that the crux of the Review is admirable in its drive to protect consumers and encourage industry compliance and innovation to help to make renewable energy measures ‘commonplace’ − the recommendations of the Review, for a new ‘quality mark’ for all energy efficiency and renewable energy measures, and for ‘all companies operating in this area’ is all well and good, but it must have real weight behind it. As some commentators have said, if it simply becomes a badge for installers to win more work, the Bonfield Review will have been for nothing.
YOUR VIEWS
Each Home Counts
CIPHE CEO, Kevin Wellman, said: ‘I appreciate why the review was required as measures to reduce fuel poverty and UK carbon emissions should be encouraged. The report refers to the need to promote customer service and enhance skills, training and competency, which are all matters close to the heart of the CIPHE. It is worth remembering that the Code of Professional Standards that all individual members sign up to covers all aspects of plumbing and heating engineering and is underpinned by a robust complaints procedure Each Home Counts administered by the An Independent Review of Consum er Advice, Protection, Standards and Enforcement for Energy Efficiency and Registration Authority. The Renewable Energy CIPHE is intending to respond to the report and if you have any comments or observations please do write to me. To read the Bonfield Review, visit https://www.gov.uk/ government/publications/ each-home-counts-review-ofconsumer-advice-protectionstandards-and-enforcementfor-energy-efficiency-andrenewable-energy CH
HOM E COU
N
TS
EA
Dr Peter Bonfield, OBE, FREng
December 2016
January/February 2017
plumbexpo 110x297 ad.indd 19
|
journal
|
19
09/01/2017 14:02
CPD
CONSULTATION;
THE KEY TO BOILER SELECTION With well over 1.5 million domestic boilers being replaced every year, out with the old and in with the new will be a familiar concept to most heating engineers.
S
o how do you ensure the heating system you specify and install is the perfect fit for your customers’ needs, and what happens Martyn Bridges, Director of Marketing when you can’t and Technical Support at Worcester, simply replace a boiler Bosch Group like-for-like? Martyn Bridges, Director of Marketing and Technical Support at Worcester, Bosch Group, explains: When a combi boiler needs replacing, the task in hand will be reasonably simple. Generally, your customer will be perfectly happy with the performance of their combi boiler but is simply in need of a new one, which makes a like-for-like replacement the most appropriate option. While the technology itself may be relatively straightforward to replace with another equivalent model however, there is still a degree of consultancy needed with the homeowner to ensure their needs are being met. Generally, there are four key factors to take into account with the homeowner before making any firm decision on the model of boiler required.
rerouting pipework or the relocating the flue and of course the new boiler will have a condensate discharge pipe, which the outgoing boiler is unlikely to have had. For the new condensate pipe, it must also be remembered that the preferred termination route is internally, via the waste water system.
BUILDING ALTERATIONS With the typical boiler expected to last around 15 years, there is every chance the homeowner may have had work done to their property since the outgoing boiler was fitted. The addition of an extra bathroom or shower will affect the level of hot water performance required, which is also likely dictate the most suitable boiler for the job.
HEAT LOSS It is also advisable to run a heat loss calculation on the property as the insulation values may have changed since the original boiler was fitted.
BACK TO BACK A much more complex scenario is when an existing boiler which isn’t a combi has to be replaced. It is not uncommon for a heating engineer to come across a back boiler
installed within a fireplace, behind a gas fire. Having been very popular in the 1970s, there is now little option other than to replace this type of boiler with a different type, sited elsewhere within the property and with homeowners occupying a property for an average of seven years, there is every chance your customer didn’t arrange for the original boiler to be installed and will be happy to consider change. In these instances, your customer will be used to a hot water storage system, so it is important to ask whether they are keen to continue in the same vein with their new boiler, or whether they would prefer to have a combi boiler and save space. Given modern lifestyles and the performance of the latest boilers, it tends to be the case that most back boilers are replaced by a combi model. Again, before sourcing and fitting a new combi boiler, it is important to take a number of considerations into account: Showers Is a shower fitted and is the shower mixing valve suitable for the mains pressure that the combi will generate? If not, and the homeowner does have a desire for all of the benefits of a combi, the shower may need to be replaced by a more suitable model at the same time.
The level of hot water performance required is also likely dictate the most suitable boiler for the job
FLOW RATE The first thing to establish is whether your customer is happy with their existing flow rate. Any dissatisfaction with the performance of their hot water is likely to mean the new boiler will have to be of a greater output than its predecessor. There may be more people now living in the house than when the original boiler was specified, meaning simultaneous draws of hot water are required more often than before.
LOCATION The second question to ask is whether or not the new boiler will need to be sited in exactly the same location as the outgoing appliance. Your customer may want to relocate their boiler, which will in turn affect the extent of any remedial work required − such as
20
20_cpd.indd 20
|
journal
|
January/February 2017
05/01/2017 12:32
CPD Your customer may say they want to move their boiler, which will affect the extent of any remedial work required
Taps How many taps are used within the property? Are any of these taps likely to be used simultaneously? An assessment of these factors will also help to inform a decision on the most suitable boiler for the property in question. Water meter Is a water meter fitted? If so, you may need to fit an expansion vessel to absorb the expansion created in the cold water mains, when an occupant runs a hot water tap. The fireplace With the back boiler being removed, an empty space will be left in the fireplace, which will need rectifying. Does the homeowner want to have a new gas fire fitted in its place? Would they prefer a wood burning stove? In the case of either, the chimney will need to be lined with a suitable new flue liner. The sealed system Replacing a hot water storage system with a combi boiler means the property will be using a sealed system, so it is important to check whether the radiators and radiator valves can handle the higher water pressure. It is generally good practice to replace the radiator valves at the same time as the heating system being altered – particularly if there is scope to replace an old wheel head radiator valve with a more modern thermostatic radiator valve (TRV).
It should go without saying that before the system is ultimately sealed, the water cleanliness needs checking and either a chemical flush or power flush procedure carried out. Storage-based systems So what about those instances where there are issues with water pressure and a combi isn’t necessarily the best option? In a property known to experience poor water pressure, a low pressure hot water storage system is likely to still be best suited, which can give rise to further considerations needing to be made prior to the installation. If a regular boiler is being installed, a heat loss calculation becomes much more important because of the fact that the outputs of most boiler ranges will go up in 3kW increments. While a boiler which is slightly oversized will always find its correct output level so won’t necessarily hamper efficiencies, a larger output boiler will be more expensive to the homeowner. The hot water storage cylinder The performance of the property’s hot water storage cylinder is also hugely important if a regular boiler is being installed. Offer the opportunity to have a new cylinder fitted with better insulation and faster re-heat times than the previous model.
Controls A boiler replacement will often present a need for new heating controls and again, consultation with the homeowner is key. A timer and a room thermostat may be the minimum requirements laid out by the building regulations, but with a vast number of options available from the most basic mechanical timer to weather and load compensating, internet-connected smart controls, it has never been so important to match the controls you specify to the requirements of the homeowner. A misplaced assumption that an elderly homeowner couldn’t possibly be internet savvy may lead to them failing to capitalise on the gains offered by the latest technology. Similarly, a mechanical time clock would be unsuitable for those wishing to benefit from different heating programs at the weekend compared to weekdays, for example.
For more information on Worcester, Bosch Group’s installer training courses, visit www.worcesterbosch.co.uk/training
January/February 2017
20_cpd.indd 21
|
journal
|
21
05/01/2017 12:33
With our technical support, you can be face to face with an expert in seconds. This year we are celebrating 30 years of unrivalled technical support. Our team of 40+ technical advisors take immense pride in delivering you world class technical support that is second to none in the industry â&#x20AC;&#x201C; striving to answer your calls in seconds while providing the best advice possible. 0330 123 3366
You can contact us in the following ways: technical-advice@uk.bosch.com
@WorcesterBosch
To find out more visit worcester-bosch.co.uk/techsupport
p22_phejan17.indd 1
09/12/2016 11:14:25
CPD
BOILER SELECTION QUESTIONS 1.
Specifically where in a property might you find a back boiler?
2.
How long is the typical boiler expected to last for? a. 12 years
3.
b. 15 years
c. 20 years
Please give an example of one piece of remedial work required in the event the new boiler needs to be installed in a different location to its predecessor.
4.
On a new boiler, what is the preferred termination route of a condensate disposal pipe? a. Internally discharged into the waste water system
To participate, simply return this assessment using any method you wish, such as fax, scan, email, photocopy, etc, (attach an additional A4 sheet if necessary). Your name:
b. Externally discharged into a drain
__________________________________
c. Discharged into an external soakaway 5.
CIPHE members are expected to complete 30 hours of CPD each year. Completion of these assessments can count towards this requirement and CPD.
If a water meter with a non-return valve fitted is in place and the homeowner is having
__________________________________
a combi boiler installed for the first time, which accessory should also be installed? CIPHE membership number: 6.
Before the heating system is sealed, what is it hugely important to do?
__________________________________
7.
If a back boiler is replaced by a wood burning stove, what else needs to be installed
Email: ___________________________
within the chimney?
8.
__________________________________
If a regular boiler is being installed, which procedure is of even greater importance to the specification of the boiler?
9.
On an open vented system, the insulation levels and re-heat times of which appliance will impact on overall efficiency?
__________________________________ Return to: CIPHE, 64 Station Lane, Hornchurch, Essex RM12 6NB Fax to: + 44 (0) 1708 448987 Email: info@ciphe.org.uk or please visit the members only area of the CIPHE website.
10. Why are high water content boilers ideal for district heating networks?
www.ciphe.org.uk/cpd Whatâ&#x20AC;&#x2122;s in it for you? As part of our work to improve your Journal, the CIPHE Communications Team wants to know how you view our CPDs. Email us with your comments to: kevinw@ciphe.org.uK
January/February 2017
23_cpd questions.indd 23
|
journal
|
23
05/01/2017 12:38
WELCOME OUR NEW MEMBERS
Proud to be a Professional We are very proud to welcome all the new members who have recently joined the CIPHE.
B
ecause all our members are vetted before being accepted into the CIPHE, the public can be confident that the person entering their premises has the necessary skills and commitment to high standards. In addition, employers can be confident of the integrity of prospective employees. Individuals have different reasons for applying for membership, but what they all have in common is a commitment to on-going training and professionalism at all times.
OUR NEW ASSOCIATE MEMBERS Wai Po Cheung Wing Hei Ho Yan Tak Hui Ho Yin Ng Wayne O'Mara George Sandu
Cheuk Ki Tai Kam Wai Tam Stephen Williams Man Kin Yan Siu Kei Yeung
OUR NEW MEMBERS Ho Leung Chan Hong Ting Chan Kwok Leung Chan Siu Wai Chan Yiu Man Chan Kin Sang Franki Cheng Chi Hang Cheung Yat Sing Cheung Kam Leung Chiu Chi Ho Chu Wai Chun Chun Stephen Crutcher Chun Ho Wilfred Fok Wing Leung Fok Mohammed Tajamul Ghazi Chun Kit Ho Ka Yee Ho Shing Chi Hui Yan Hin Hui Po Lung Ken Hung Yuk Keung Jay Ip
Hoi Chi Kwok Man Chun Lai Yan Kau Leung Siu Yuen Li Wai Kit Li James Lindley Siu Wing Lo Chan Yiu Ma Sze Yu Ma Chi Hang Angus Mok Richard Moore Siu Hong Pang Wai Lam Poon Glenn Paul Scholfield Ka Chun Wan Chung Yuen Wong Tsz Tat Wong Wai Kin Thomas Wong Yuke Lun Yip Yiu Chung Yiu
OUR NEW TRAINEE MEMBERS Alan Auld Kyle Barden Csaba Besze Michael Biggins James Ian Boxall Jordan Bull Aaron Butler Daniel Chadney Malcolm Clark Matthew Coles Devon Couper Daniel Croarkin Kimarni Daley Alfie Davies William Davies Ryan Deans Hugh Dickson Cameron Dowdall Harry Dunn Simbarashe Dziruni William Exall Marc Ferreira Jakob Foster Joshua Foster Sean Paul Gallagher Thomas Game Callum Genus Ryan Gillan Jack Graham Luke Gray Harry Grice David Holmes Fred Howlett Keegan Hynd Ahmed Jamal
Michael Johnston Lee Jones Charlie Keil Agostin Kola Andrew Lange William Lawrence Jacob Lengthorn Ruaridh Maciver Scott John McCafferty Kaleem Mura Jay Panesar Michael Pantrey Gregor Peacock Morgan Pearson Robbie Peebles Ashleigh Plested Nicky Poile Shane Powell David Peter Rook Sophie-Marie Rush Harvey Ruske Ben Sheppard Adam Siad Joshua Stagg Reece Stewart Billy Sykes Gabrielle Turney Aaron Vella Adam Walford Harry Walkinton Thomas Ward Nicolas Warden Thomas Woolcott Craig Young
PROFESSIONAL COMPETENCE Proud to be a Professional The Engineering Council is the UK regulatory body for the engineering profession. The CIPHE is licensed to provide Incorporated Engineer (IEng), Chartered Engineer (CEng) and Engineering Technician (Eng Tech) registration.
The members opposite have met the internationally recognised standards of professional competence and are now registered with the Engineering Council.
24
|
24_council members.indd 24
journal
|
Hong Ting Chan CEng, New Territories, Hong Kong Jonathan Edward Miller CEng, Ipswich Chi Hang Angus Mok CEng, New Territories, Hong Kong Tsz Tat Wong CEng, North Point, Hong Kong
January/February 2017
12/01/2017 10:26
CIPHE EXTERNAL AFFAIRS
CIPHE INDUSTRIAL ASSOCIATES
Proud to be a Professional Proud to be a Professional
MAKING A CASE FOR MOTs Roger Webb, Director of External Affairs at the CIPHE, comments on the case for annual MOT style checks to be introduced for British homes.
“
Every year, thousands of consumers around the UK invest money in improving their homes. From having new boilers installed to replacing complete bathroom suites, transformations are happening and being made possible by professional Roger Webb, CIPHE Director of plumbing and heating engineers around External Affairs the country who are doing a great job. “While that’s all well and good, and homeowners are immediately left with a shiny new shower or a more efficient heating system, this newness can soon start to wear off if aspects of the installation work are left unchecked and not maintained on a regular basis. “One of the best ways I have heard this issue being described by colleagues at the Institute is to liken the need for allencompassing home health checks to the requirement for vehicle MOTs. “After decades of education, the general public is well aware of the need to have their cars checked annually in order to tax, insure them and be roadworthy. By comparison, little thought is given to whether or not the safety critical products in our homes are especially ‘roadworthy’ and there’s no pressure for anyone to be overly concerned either. “While the situation is far from ideal, there is clearly a job to be done to spread the word that ‘prevention is better than cure’ when it comes to keeping our homes in perfect working order. As well as ensuring running costs and utility bills are kept to a minimum, safety is paramount, especially where the elderly and vulnerable are concerned; so during the course of this year expect to hear more from the CIPHE on this issue. It’s not one that’s going to go away.”
GETTING IT RIGHT FIRST TIME Paul Massey, Chairman of the Institute’s Industrial Associates (IA) Development Group, explains why getting it right first time is a win-win situation.
S
ince launching the ‘Proud to be a Professional’ campaign in early 2016, the Institute has focused on developing its network of Approved Training Centres (ATCs) and wider training material, to help both members Paul Massey, and non-members of the Institute Chairman of the Industrial Associates deliver the best possible solutions and Development Group service for customers. Most recently, the CIPHE launched a new series of ‘techtalk’ and ‘smarttalk’ webinars and technical papers, which tackle some of the latest installation and business challenges faced by plumbing and heating engineers and apprentices today. While this investment is supportive of the trade, one of the main aims of developing such resources is to have a positive impact on the end-customer too. Sadly, not all homeowners have a fantastic experience when work is carried out on their properties. From poor installation practices to unreliable tradesmen, instances still occur that are less than satisfactory. What we’re endeavouring to do at the CIPHE is build a 360 degree programme that includes the consumer and the plumbing and heating engineer, to increase instances where work is delivered correctly and is right first time. With around 7,000 installer members and over 180 Industrial Associate members − including some of the UK’s leading manufacturers and merchants − plus excellent links to trade and consumer associations, who else is better placed to deliver this support than the CIPHE? In this respect, we are working towards achieving a win-win situation for all parties. By providing easy access to varied educational content, the aim is to help more plumbing and heating engineers specify suitable products and deliver a job that’s done correctly, without the need for costly call-backs. This has to be a good thing because the implications of going back to correct poor work can be far-reaching. As well as being an inconvenience to the consumer − who is the most important person at the end of the supply chain − getting it wrong can lead to a loss of recommendations because the trust, respect and confidence that might otherwise have been there, quickly disappears. Through membership of the CIPHE and getting it right first time, there is more to gain and a lot less to lose!
January/February 2017
25_roger web paul massey.indd 25
|
journal
|
25
23/12/2016 15:39
CIPHE NEWS
CIPHE AND BMF ANNOUNCE
COLLABORATIVE ALLIANCE
The CIPHE and the Builders Merchants Federation (BMF) have agreed a strategic alliance that will see the two organisations collaborating in key areas.
T
he CIPHE and the BMF are both committed to raising quality and standards within their respective industries and progressing this ambition is one of the main objectives of their new alliance. They have also committed to have one voice on mutually agreed topics to government and other relevant bodies and to add value to both existing memberships through guidance, training and standards. As the professional body for the UK plumbing and heating industry, CIPHE has over 7,000 members including consultants, specifiers, designers and practitioners, as well as some 170 manufacturers and distributors, which support its work as Industrial Associates.
26
26_bmf.indd 26
|
journal
|
WORKING TOGETHER In recent years, the BMF has strengthened its support for specialist plumbing and heating merchant and supplier members. Initiatives include a bi-annual P&H Forum that has been instrumental in encouraging many more P&H specialists to play an active role in the BMF. CIPHE CEO, Kevin Wellman said: “There are a great many synergies between our two organisations. Working together, we can more effectively promote the need for professional plumbing and heating engineers to install quality products supplied by stockists who really understand the process. We are also looking to engage in campaigns to help
domestic end-users, for example on low carbon solutions, and to support vulnerable members of the public.” BMF Managing Director, John Newcomb, said: “Our collaboration with the CIPHE offers exciting possibilities for both organisations. The key driver is to raise the respective quality and standards in both sectors. In addition to reciprocal promotions, we will be investigating various training opportunities and are already planning a series of practical skills days next year, where merchants can gain hands on experience of typical plumbing installations.”
January/February 2017
12/01/2017 09:57
OBITUARY
JAMES SYDNEY WALLEY, ENG TECH, LCGI, HON FCIPHE, MCIPHE, RP 1924 TO 2016
It is with great sadness that we have to announce the death of Jim Walley, one of the stalwarts and supporter of the Institute over many years. Jim died on Saturday 12th November 2016.
J
im came from a family with a background in building, his father was a builder his brother was a carpenter, but Jim always wanted to be a plumber so he served an apprenticeship with an old, established Manchester plumbing company. He attended evening classes to achieve his City and Guilds Certification and when he finished his apprenticeship, he was drafted into the Army. When his basic training was complete, he was very proud to serve the rest of his Army time in Burma as one of the famous ‘Chindits’, as a muleteer, transporting Spitfire spare parts through the jungle to their destination. After his demobilisation he returned to plumbing, working on new housing projects and many large commercial contracts, these projects were revolutionary for the time and
Jim had to acquire many new skills, which he did with his usual enthusiasm. When natural gas was imported into the country, he worked on conversions with the Humphrie and Glasgow Organisation where his talents were quickly recognised. His first appointment there was as a rate fixer for every aspect of the work required to change over all the gas appliances in a dwelling from the old ‘towns gas to the new natural gas; this required him to have some delicate negotiations with the employees’ union. Later, he became the North of England Area Manager, covering North Lancashire, Cumbria and North Yorkshire. He was very proud of the fact that they never missed a ‘change-over’ date, which meant 1,000 dwellings were converted at the same time. When all the gas conversions were completed, he left the company to start up his own plumbing business. His biggest client was British Gas where he looked after the water supplies in their premises in the North West. He became an expert in the chemical cleaning of water supplies particularly in ensuring the water was clear of the microorganism, legionella pneumophila, which causes Legionnaires' disease.
He unstintingly passed on his knowledge to many other plumbers. The greatest interest in his spare time was his membership of the CIPHE. For more than 30 years, he was a member of the Manchester Branch of the Institute, where he was Branch Secretary, Chairman and subsequently President. For many years, he held the position of Vice Chairman of the North West Area Committee. A number of years ago he received the award of Honorary Member of the Institute and then followed this by becoming a Licentiate member of City and Guilds. The Institute’s Board of Trustees awarded Jim Honorary Fellowship and a presentation evening was arranged for 6th October 2016 in Manchester. Unfortunately, Jim was too ill to attend, so in his absence, the CIPHE National President, Paul Williams, made the presentation to Jim’s daughter, Yvonne. When Yvonne delivered the Award to Jim, although he was very ill, he was able to express his pride in receiving the Institute’s highest award. It is fitting that for all his work on behalf of the Institute that Jim left this world knowing his efforts had been recognised at the highest level, the certificate is now proudly displayed in Yvonne’s home. R.I.P. Stan Tildsley, EngTech, Hon FCIPHE, MCIPHE, RP
Jim’s knowledge, enthusiasm, technical capability and support for the Institute was second to none and having known Jim for over thirty years, I know how highly regarded he was throughout the industry. The CIPHE and the plumbing and heating industry has lost a great friend and unique character. Kevin Wellman, CIPHE CEO.
January/February 2017
27_obituary.indd 27
|
journal
|
27
23/12/2016 15:44
BRANCH NEWS
Branch NEWS SUFFOLK
LANCASHIRE
A MEMBER FOR 60 YEARS
CPD EVENING
The Branch was pleased to welcome National President, Paul Williams, who presented Stan with a framed certificate.
Suffolk Branch’s final CPD evening of 2016 was held at Westgate Ward Social Club on 1st November 2016. Stephen Pelling and Peter Mara from Impey gave a talk and demonstration on the conversion of a standard bathroom into a wetroom.
Branch committee member, Stan Rawcliffe, recently marked 60 years as a CIPHE member.
2017 CPD evening dates: 10th January 7th March (including the Branch AGM) 4th May 5th July 7th September 7th November Do please come along and support your local Branch.
NORTHAMPTON
P&HE JOURNAL SPREADS ITS WINGS Its time to talk “Smart”! with Paul Harmer Technical Director, CIPHE
smarttalk-ciphe.org.uk
INTERNET-BASED DOMESTIC CONTROL SYSTEMS The next meeting of the Northampton Branch will be on Thursday 2nd February at 7.30 pm at the Holiday Inn Milton Keynes East M1, London Road, Newport Pagnell MK16 0JA (just off Junction 14 of the M1). Our guest presentation will be by NEST, the internet-based domestic control systems that are selling fast into the domestic heating market. This event is to explore a joint venture of Northamptonshire, Bedfordshire and Milton Keynes (MK postal code) area members. All are welcome. Please RSVP by email to Northampton Branch Secretary, Nick Blount, at: nick.blount@rfblount.co.uk
The Chartered Institute of Plumbing and Heating Engineering is pleased to launch its “smarttalk” series aimed at communicating information that effects our members on a daily basis.
Your p&he Journal is now available to non-members via a page-turning version on the CIPHE website. It is also circulated 20 26 by CIPHE Industrial Associates who add the link to their websites and to their customers via mailshots etc. THE TECHNICAL ISSUE 10 This increases the visibility and brand Law & Regulations awareness of the CIPHE exponentially, Sales & Marketing to consumers as well as the trade Finance & Accounts and in turn, highlights its members Proud to be a Professional with knowledge from smarttalk as professionally adept and forwardthinking installers. It’s time to talk technical with CIPHE’s new This is just one new and innovative Proud to be a Professional way that the CIPHE gets its voice heard. The smarttalk series is delivered in 3 keys areas - Legal, Finance and Marketing - and will endeavour to help equip our members with vital skills that support the delivery of a first class service for the consumer.
Smarttalk will be initially concentrating on highlighting good business practice. For example, TECHNICAL CPD: understanding the Consumer Rights THE CONSTRUCTION PRODUCTS REGULATIONS AIR ADMITTANCE VALVES Act and how it effects the plumbing and heating engineer during their November/December 2016 daily lives, or even the risk of Business skills: Talk smart with CIPHE’s new manslaughter through an unsafe smarttalk installation. The law is there to help protect both the installer and the consumer, therefore having this valuable knowledge in your toolbox, will in certain circumstances be the most
For important plumbing &tool heating in your possession. engineering professionals
Smarttalk also aims to educate on the importance of good financial skills, whether it be as simple as controlling cashflow on a project, or even just ensuring that you have a sufficient pension pot to support you in your later years.
Finally, smarttalk will cover different apsects of marketing and how our members can benefit from marketing themselves effectively. This could be as simple as having the correct soft skills required when dealing with the consumer, or even how to sell your services through a well branded website. For further information about carrying out a smarttalk, then please contact Marie Mcaffrey, Membership Manager on: mariem@ciphe.org.uk
TM
www.ciphe.org.uk
p01_phe_Nov16.indd 1
10/11/2016 10:51
CIPHE NEEDS YOU!
CIPHE is seeking members who would like to act as technical mentors for registration as EngTech, IEng and CEng applicants and/or CPD assessors. You will be supporting other individuals in their professional development, either by helping them as they apply for Incorporated Engineer or Chartered Engineer registration via the individual or technical report route options, or more generally, as an assessor of Continuing Professional Development, checking and approving members’ anonymised CPD records. Full training will be given for all the above roles. If you would like to become a mentor or assessor (which will also count towards your own CPD), please contact Marie McCaffrey at mariem@ciphe.org.uk with a copy of your CV.
28
|
28_branch news.indd 28
journal
|
January/February 2017
12/01/2017 09:59
WHAT'S NEW
What’sNEW
This guide features the latest product launches and the most recent applications of plumbing and heating technology. To advertise your product or project please contact Theresa Geeson on 01778 392046 or email theresag@warnersgroup.co.uk
JOIN DEVI INSTALLERS
THE FASTEST WAY TO INSTALL M&E SERVICES
DEVI, part of Danfoss Electric Heating Systems, has launched the DEVI Elite benefit programme. The new rewards scheme helps installers of DEVI intelligent floor heating systems to expand their skills and business potential. As members of DEVI Elite, installers earn points every time they participate in activities and support services available through the programme. Qualifying activities include mobile web tools, e-learning courses and competitions. DEVI Elite installers can even collect points when they introduce a friend to Elite or visit the company’s stand at a trade show.
Gripple has provided the fastest and easiest method of installing suspended pipe and electrical services with Gripple QT Trapeze Plus – it enables quick twist attachment to a Gripple Universal Bracket. The latest addition to the Gripple Trapeze Plus range also integrates an easy-to-use adjustment button to ensure perfect levelling and a locking screw, which provides ultimate security. The incorporated fail-safe clip secures the new Trapeze to the bracket, preventing unexpected movement. The QT Trapeze Plus is supplied in a ready-to-use kit with no cutting required. Brackets can be prefabricated prior to site installation and only a standard size spanner is needed for installation.
08451 217400 enquiries@devi.co.uk www.devi.co.uk
0114 228 8617 www.gripple.com
SMALL THINGS MATTER
COMPREHENSIVE GRAB RAIL RANGE
Emmeti has added the EWC-4, four channel wiring centre into its zone controls range, to complement the existing EWC-1 and EWC-2 products. Its more compact shape saves on installation space and is cost effective for small-scale underfloor heating and wall hung radiator systems. For applications where independent zone control is required, the EWC-4 provides central electrical control to all system components. It features external timer/night setback inputs, four thermostat channels with dedicated electrothermic head wiring terminals, 230v UFH pump terminal and a volt free boiler terminal for interlocking a mains or low voltage heat source. In addition, it incorporates power and operating LEDs within a solid compact case.
Inclusive bathroom solutions supplier, AKW, offers a comprehensive range of grab rails in many configurations for installation as a mobility support in bathrooms. The grab rails include fixed and fold-up steel and plastic versions, some fluted for additional grip and others with a smooth grip and can support loads up to 15.5 stone (100kg) with heavy duty versions rated to a maximum load of 30 stone (190kg). AKW fold-up support rails are available in white or blue for users with impaired vision. Newel rails offer a 90 degree turn around the newel post and provide additional grip while using stairs. Other versions in AKW’s inclusive range include flat end, angled (90 and 135 degrees) and floor-to-ceiling grab rails.
01993 824900 www.emmeti.co.uk
http://bit.ly/2ejEhlH
January/February 2017
29_products.indd 29
|
journal
|
29
05/01/2017 12:22
WHAT'S NEW
INTUITIVE SHOWER SPRAY SELECTION
SWEET SMELL OF EXTERNAL VENT PIPES
Mira Showers has introduced a new, innovative showering experience with the new Mira Switch, a contemporary handshower that delivers four spray modes, which are chosen simply by pressing a button at the base of the showerhead. With each press changing the pattern, users can be invigorated by ‘Stimulate’; get drenched by ‘Saturate’; luxuriate in ‘Soak’, and relax in ‘Soothe’. In Soothe mode, the Switch has been independently accredited by the Skin Health Alliance for users with sensitive skin. Switch works on all systems and pressures, is compatible with all hoses and is a quick tool-free fit. It delivers installers a great opportunity to ‘sell up’ while providing the consumer with a ‘custom’ shower experience.
The Maxi-Filtra is the innovative solution to eliminate noxious smells from external vent pipes. Manufactured by Studor, expert in drainage ventilation, it is ideal for a wide range of applications including septic tanks, grease separators, rain water tanks, STPs, lifting equipment and building drainage open vents etc. It can be installed quickly both vertically or horizontally, using the push-fit connector provided. The integral two-way activated carbon filter is easily replaceable when required by simply removing the cap of the Maxi-Filtra. As air moves in both directions the Maxi-Filtra eliminates all smells without compromising the operation of the drainage system.
0844 571 5000 kohlermira@linney.com mirashowers.co.uk
01986 784759 www.bystudor.com/maxi-filtra
SENTINEL JetFlush Rapid® CLEANS UP
FANS DETAINED IN POLICE STATION
Water treatment specialist, Sentinel, has introduced a new powerflushing machine, the JetFlush Rapid®, to its comprehensive range. It boasts a range of innovative features that help installers to save time and hassle on the job, while improving heating system efficiency, minimising the risk of boiler failure and preparing systems for protective inhibitor. The JetFlush Rapid delivers thorough removal of magnetic and non-magnetic debris, while restoring heat and efficiency to domestic heating systems. This is thanks to the unit’s high flow rate of 90 litres/minute (more than twice that of the previous model, the JetFlush4), made possible by a bespoke pump that couples a large, high-efficiency impeller with a powerful motor. Instant flow reversal adds extra cleaning power, helping to shift even the most stubborn dirt by disturbing water flow.
Polypipe Ventilation, manufacturer of energysaving domestic ventilation systems, has had its Silavent Sapphire dMEV (Decentralised Mechanical Extract Ventilation) centrifugal fans specified and installed into an unusual new residential conversion − a former police station in Harrogate. The UK-manufactured Silavent Sapphire centrifugal dMEV fans boast excellent performance and contemporary design, at an affordable price. With a low Specific Fan Power (SFP) down to 0.29W/ (l/s) and very quiet operation down to 18dB(A), the Sapphire dMEV was the natural choice for a project where the latest ventilation technology and heritage are paramount. Sapphire dMEV units form part of Polypipe Ventilation’s Silavent range, which also features the award-winning HRX (Mechanical Ventilation with Heat Recovery) and compact CMX (Mechanical Extract Ventilation) appliances.
01928 704330 www.sentinelprotects.com
03443 715523 www.polypipe.com
MONARCH WATER LAUNCHES NEW SCALE PREVENTION SYSTEM
SMALLER IS EVEN MORE BEAUTIFUL IN THE MIRA MINILITE
Through extensive product research and development, Scaleout XP has been designed to give extra power, performance and protection to permanently prevent limescale for the whole house and its appliances. Scaleout XP, the next best alternative to a water softener, introduces its new advanced technology to permanently remove and prevent the damage caused by hard water. Whilst reducing the impact of scale, it is now more powerful in its performance and protection to remove existing scale and prevent new scale forming. Compact and easily installed, it uses no electricity and is the only scale inhibitor giving permanent treatment.
Mira showers has revised its popular range of Minilite concentric mixer showers. The new Minilite has a smaller body size making it ideally suited for smaller enclosures or new en suite applications. There are three showers in the collection: the exposed valve Minilite EV, and built-in Minilite BIV, both with a 90mm multi-function showerhead with rub clean nozzles; and the built-in Minilite BIR, which offers a generous rigid 200mm drench head. That the Minilite packs such a showering punch within its small body is thanks to the company’s patented Magni-flo™ technology. Mira Magni-flo™ is a uniquely engineered technology that enables its shower mixers to deliver up to three times more flow than competing products, even at low pressure.
01986 784759 sales@monarchwater.co.uk www.monarchwater.co.uk
30
|
29_products.indd 30
journal
0844 571 5000 kohlermira@linney.com mirashowers.co.uk
|
January/February 2017
30/12/2016 15:09
YOUR INSTITUTE NEEDS YOU! The CIPHE appreciates the sterling work done on behalf of the Institute by its volunteers. If you would like to take an active role in one or more of its working groups and committees, we would love to hear from you. Alternatively, you may wish to consider becoming a CIPHE Membership Ambassador – helping to promote the professional Chartered status and the many benefits and services CIPHE membership can provide. We welcome the opportunity to discuss the requirements further with you. Please contact Lesley Challis for details of our current voluntary positions. Lesley Challis Comp CIPHE AMInstLM, PA to Chief Executive Officer DIRECT LINE TEL: 01708 463115 EMAIL: lesleyc@ciphe.org.uk
FIND URINAL CONTROLS FRUSTRATING TO FIT?
COMBINATION BOILERS-FAULT FINDING & REPAIR John Reginald, author of the highly successful Central Heating - Fault Finding & Repair, has now released Combination Boilers - Fault Finding & Repair. The 150-page, A4 spiral-bound book with laminated front and back cover, is written in an easy-toread, easy-to-understand format, which takes the reader through the background and operation of each major component within combination boilers past and present. The comprehensive fault-finding logic guides provide professional solutions allowing you to repair and service combi boilers with a greater understanding and with more confidence.
Priced at £26.00, incl. P&P. To order your copy visit any leading online retailer, highstreet bookshop or order from the publisher at: www.combiboilerrepair.co.uk
New DUDLEY KINETIC® intelligent urinal flushing control NEW DC PIPE INTERUPTER ALSO AVAILABLE FOR USE WITH DIRECT FLUSHING URINAL CONTROLS TO PREVENT MAINS SUPPLY CONTAMINATION
Reassuring warranty*
Made in the UK
Save time, money and water Easy to set up correctly Cut water use by 80%
Call 0121 530 7000 or visit
www.dudleybathroomproducts.co.uk
Easy to fit and service
*Terms apply, see website for details
CENTRAL HEATING-FAULT FINDING & REPAIR From simple to more complex faults, author John Reginald, takes the reader on a journey through central heating and domestic hot water sysytems. The manual’s aim is to instil a better understanding of the systems to achieve professional solutions to professional standards. Central Heating-Fault Finding & Repair consists of logical stepby-step guides that take the reader through the fault finding and repair process. The fault logic guides are easy to read and indicate which section of the manual deals with the background and repair of that fault.
Priced at £26.00, incl. P&P. To order your copy visit any leading online retailer, highstreet bookshop or order from the publisher at: www.centralheatingrepair.co.uk
January/February 2017
p31_phejan17.indd 31
|
journal
|
31
09/12/2016 11:40:04
NOW HETAS LISTED Advance Appliances universal multi fuel thermal store system works with all heat sources including wood burning stoves, gas or oil boilers and solar thermal, as well as electric and other solid fuel appliances. • Pre plumbed and pre wired for simple installation • Mains pressure hot water • Sealed central heating
YEAR
GUARANTEE
10
FOR MORE INFORMATION CONTACT
01543 377723 www.advanceappliances.co.uk p32_phejan17.indd 1
09/12/2016 11:07:25