cost estimation project

Page 1


Project Cost Estimation

Course Number

BLDG 6851

Professor: Dr. Po-Han Chen

Group 11

Final report

Preetam Ola (40233353)

Winter 2023

1. Introduction

Cost estimation is the process of estimating the amount of money and other resources required to finish a project within a specific time frame. Cost estimation generates a total sum that establishes a project's budget by taking into account all project-related requirements, including labor and supplies. An early cost estimate can help an organization decide whether to approve a project, and if the project proceeds, it can help define its scope. A company may decide to scale back the project to match what they can afford if the cost estimation is too high (it is also required to begin securing funding for the project). The cost estimate is used to control all associated costs once the project is underway in order to keep it under budget. Should the cost estimation be over the budget, the owner’s specifications must be altered in accordance with the target budget.

2. Objective

This report aims to calculate detailed estimation for a prospective two-story building to be constructed in Toronto. For its cost estimation to report to the owners, we have considered these steps:

✓ Quantity Take-off (QTO)

✓ Pricing

✓ Master Format conversion

✓ Detailed estimation

3.

Project Description

A two-story residential building to be constructed in Toronto, Ontario in 2023 with a Gross Floor Area of roughly 5,500 Square Feet is a significant undertaking that requires careful planning and attention to detail. The preliminary design, which includes a basement, a ground floor, and a second floor, suggests that the building will have ample space for living, entertaining, and storage. The conceptual structural framework is envisioned as being made of steel. Steel's high strength-to-weight ratio and versatility make it an ideal material for use in conceptual structural frameworks. It can support heavy loads without adding unnecessary weight to the structure, and it can be easily fabricated into various shapes and sizes to suit the needs of a particular design. Steel is also resistant to fire and pests, making it a

safe choice for buildings that require high levels of protection. Moreover, steel is an environmentally friendly material, as it can be recycled and repurposed after its initial use, reducing waste and minimizing the environmental impact of construction projects.

The exterior finishes for the building will be covered by masonry bricks. Masonry is a durable and long-lasting building material, that provides great insulation and fire resistance. It also adds an aesthetic appeal to the building, creating a classic and timeless look. Masonry bricks come in a wide range of varieties, each with its own unique characteristics, colors, and textures. The choice of masonry brick will depend on the design aesthetic, budget, and other factors.

4. Detailed Estimation

In order to do the detailed estimation, the following steps should be undertaken:

• Work Breakdown Structure (WBS) use (Uni Format approach)

• Quantity Take-Off (QTO)

• Pricing

4.1.

Work Breakdown Structure (WBS)

Utilizing the work breakdown structure (WBS), which is a project management tool, helps large projects to be completed step-by-step. The WBS allows integrating the scope, cost, and deliverables into a single tool by dividing the project into smaller components. Albeit most WBSs are deliverable-based (Master Format), they can also be phase-based (Uni Format).

A Substructure B Shell

A10 Foundations

A1010 Standard Foundation

A1020 Special Foundations

A1030 Slab-on-Grade

A20 Basement Construction

A2010 Basement Excavation

A2020 Basement Walls

C Interior

C10 Interior Construction

C1011 Partitions

C1020 Intr. Doors

C1030 Fittings

C20 Stairs

C2010 Stair Construction

C2020 Stair Finishes

C30 Interior Finishes

C3010 Wall Finishes

C3020 Floor Finishes

C3030 Ceiling Finishes

B10 Superstructure

B1010 Floor Construction

B1020 Roof Construction

B20 Exterior Exclosure

B2010 Exterior Walls

B2020 Ext. Windows

B2030 Ext. Doors

B30 Roofing

B3010 Roof Covering

B3020 Roof Openings

D Services

D10 Conveying

D1010 Elevators & Lifts

D20 Plumbing

D2010 Plumbing Fixtures

D2020 Domestic Water Distribution

E Equipment & Furnishings

E10 Equipment

E1030 Vehicular Equipment

E1090 Other Equipment

E20 Furnishings

E2010 Fixed Furnishings

D2030 Sanitary Waste Z General

D2040 Rain Water Drainage

D30 HVAC

D3010 Energy Supply

D3020 Heat Generating Systems

D3030 Cooling Generating Systems

D3040 Distribution Systems

D3050 Terminal & Package Units

D3060 Controls and Instrumentation

D3070 Systems Testing & Balancing

D40 Fire Protection

D4010 Sprinklers

D4020 Standpipes

D50 Electrical

D5010 Electrical Service & Distribution

D5020 Lighting & Branch Wiring

D5030 Communication & Security

D5090 Other Electrical Systems

4.2. Quantity Take-Off (QTO)

Z20 Contingencies

Z2010 Design Contingency

Z2020 Escalation Contingency

Z2030 Construction Contingency

The Quantity Take-Off process is crucial in construction cost estimation, involving the measurement of labor, materials, and resources from project drawings. This data is then used to prepare a detailed cost estimate, providing a comprehensive overview of total project expenses.

4.3.

Pricing

Pricing in construction cost estimation is a critical process that involves calculating all costs associated with a project, including materials, labor, equipment, and other expenses. By breaking the project into components such as excavation, foundation, framing, roofing, electrical, plumbing, and finishing work we can estimate costs more accurately. Utilizing RSMeans provides a comprehensive list of unit prices that account for overhead and profit. Factors like project location, design complexity, and material quality significantly influence these estimates. This approach ensures a comprehensive budget, covering both direct and indirect costs, and helps manage expenses effectively, facilitating timely completion of the project within budget constraints.

Excavation (Cut)

Quantity: 9507.8 Cu.ft

Unit Price: 6.88

Total cost of Cut: 9507.8 × 6.88 = 65,409.65

Concrete (Slab)

Quantity: 534.2 Cu.ft

Unit Price: 137.34

Total cost of Cut: 534.2 × 137.34 = 73,371.15

Woodwork (Sill Plate)

Quantity: 363.3 BF

Masonry (Bricks)

Quantity: 12892 No. Unit Price: 363.3 Unit Price: 3.31

Total cost of Cut: 363.3 × 363.3 = 5,543.91 Total cost of Cut: 12892 × 3.31 = 42,640.30

5.

Quantity Take-Off (QTO) Calculation

Metals

There are steel columns and steel lintels in this project. For the location and the information, please refer to Appendix.

Woods:

The wood section divided into Walls, Floors, and roofs. For more detailed calculations please refer to Appendix.

Sample Calculation for Basement Walls:

Wooden walls above the retaining walls and wooden interior walls are calculated.

Bottom Plates:

We used 1.55E Timber Strand® LSL 1 ½” × 5½" (2” ×6”)

Figure 1: Timber Strand, Microlam, and Parallel Beams, Headers, and Columns - Pacific Northwest Specifier's Guide

Total length: 100.94’

Total BFM:

100.94 BF

Top Plates:

We used 1.55E Timber Strand® LSL 1 ½” × 5½" (2” ×6”)

Total length with doubling parts: 138.57’

Total BFM:

138.57 BF

Wall Stud:

Use 1.55E Timber Strand® LSL 1 ½” × 5½" (2” ×6”)

There are different heights for wall studs.

Total Length of all: (11’x55) +(74x9.515’) +(11x5.71’) +(5.71’x27) +(6.2’x34) +(7.45’x25)

+(6.2’x17) = 2028.54’

Total BFM:

2028.54 BF

Blocking:

Use 1.55E Timber Strand® LSL 1 ½” × 5½" (2” ×6”)

Total Length of all: 88.108

Total BFM: 88.108 BF

Hold Downs:

HDB/HD is used for controlling lateral load in shear walls.

Total Number: Walls Sheathing:

6 HDB/HD

Use 9’x4’,7/16”

Figure 2: Simpson Strong-Tie Company Inc.
Figure 3: OSB Wall Sheathing

(25.75x7.45) +(17.5x6.2) +(40.21x6.2) +(6.2x15.125) +(5.71x28.125) +(12.83x5.71)

+(9.515x30.618) +(19.86x11) +(16.8x9.515) +(20.83x11) = 1776.04 SF

1 sheath of OSB 9x4 = 15.75 BF

Total:

50 sheaths

787.5 BF

Sample Calculation for Floors:

Basement Framing Plan (Main Floor Joists):

BF/ft

Number:

5.92’/1’ + 1 = 7 Pieces

Length: 16.25’ Each

bf/ft

Figure 4: Basement Framing Plan
1: 9 ½” TJI S47 @ 12”
of TJI S47: 427/384
Figure 5: Specifier's Guide for TJI s31, s33 and s47 Joists for East Canada

Sample Calculation for Roofs:

Roof Rafters:

Common Rafters: (3:12) / 2” × 8” SPF@ 16”

NominalThickness:8”=>Actualthickness= 7.25”NominalWidth:2”=>Actualwidth= 1.5”

Rise:

 Rise=3.095’

Figure 10.Roof
Figure 35. Roof Framing Plan

Roofs

Roof Rafters:

Common Rafters: (3:12) / 2” × 8” SPF@ 16”

NominalThickness:8”=>Actualthickness=7.25”

NominalWidth:2”=>Actualwidth=1.5” Rise:

3.095’

AdditionalLength=0.151’

TotalLength: 12.77’+0.151’

Total Length = 12.92’

NumberofRafters:

Total No. = 52

FBM=

Common Rafters: (12:22) / 2” × 6” SPF@ 16”

NominalThickness:6”=>Actualthickness=5.5”

NominalWidth:2”=>Actualwidth=1.5” Rise:

=3.98’

Figure 37. Roof Plan for Common Rafters

AdditionalLength=0.25’

TotalLength: 4.54’+0.25’

Total Length = 4.79’

Number of Rafters: 1:

����������ℎ 12 = 5.5"/12 22

Total No. = 119

TotalFBM=

1.((8.09′ ×1)/16”)+1=8

2.((2.63′ ×12)/16”)+1=3

3.((8.75′ ×12)/16"+1=8

4.((5′×12)/16")+1=5

5.((0.71′ ×12)/16")+1=2

6.((39.92′ ×12)/16")+1=31

7.((39.92′ ×12)/16")+1=31

8.((39.92′ ×12)/16")+1=31

119×4.79′×2"×6" = ������.�������� 12"

HipRafters:(3:12)/3-2”×10”SPF

NominalThickness:10”=>Actualthickness=9.25”

NominalWidth:2”=>Actualwidth=1.5”

Figure 38. Hip rafters

Rise:(Same as common rafters)

Rise=3.095’

RunLength:

17.51’ HipRafterLength:

AdditionalLength:

AdditionalLength=0.136’

TotalLength:

17.79’+0.136’

Total Length = 17.93’

NumberofHipRafters:

No.=4

Hip Rafters: (12:22) / 3 - 2” × 8” SPF

NominalThickness:8”=>Actualthickness=7.25”

NominalWidth:2”=>Actualwidth=1.5”

Rise:(Sameascommonrafters)

Rise=3.98’

RunLength:

Length=3.07’

HipRafterLength:

AdditionalLength:

AdditionalLength=0.783’

TotalLength:

5.03+0.783’

Total Length = 5.813’

Number of Hip Rafters: No.= 4

TotalFBM=

4×3×5.813′×2"×8" = ����.�������� 12"

JackRafters:(3:12)/2”×8”SPF@NominalThickness:8”=>Actualthickness=7.25”

NominalWidth:2”=>Actualwidth=1.5”

Number of Jack Rafters: Number of Sides = 8 ;8×9=72 Jack Rafters with different lengths.

Figure 39. Jack Rafters 16

Length=11.4’

AdditionalLength:

AdditionalLength=0.151’ TotalLength: 11.4’+0.151’

Length 1: 11.551’

2: Run:

11.05-1.33=9.72’

AdditionalLength=0.151’ TotalLength: 10.02’+0.151’ Total Length 2: 10.171’

3: Run:

9.72-1.33=8.39’

4: Run:

8.39-1.33=7.06’

Length=7.28’

AdditionalLength:

AdditionalLength=0.151’

TotalLength:

7.28’+0.151’

Total Length 4: 7.431’

5: Run:

7.06-1.33=5.73’

Length=5.906’

AdditionalLength:

AdditionalLength=0.151’

TotalLength:

5.906’+0.151’

Total Length 5: 6.057’

6: Run:

5.73-1.33=4.4’

7: Run:

4.4-1.33=3.07’

Length=3.165’

AdditionalLength:

AdditionalLength=0.151’

TotalLength:

3.165’+0.151’

Total Length 7: 3.316’

8: Run:

3.07-1.33=1.74’

Length=1.794’

AdditionalLength:

AdditionalLength=0.151’

TotalLength:

1.794’+0.151’

Total Length 8: 1.945’

9: Run:

1.74-1.33=0.41’

0.43’+0.151’

Total Length 9: 0.581’

Total Length= 54.544’ for one side

TotalFBM=

Jack Rafters: (12:22) / 3 - 2” × 6” SPF @ 16”

NominalThickness:6”=>Actualthickness=5.5”

NominalWidth:2”=>Actualwidth=1.5”

NumberofJackRafters:

Number of Sides = 8

8×1=8 Jack Rafters same size

Figure 41. Jack Rafter
Figure 42.Jack Rafter

Run:10”

Rise:

(rise/10) =(12/22)

Rise= 5.455”

Length: √5.4552 +102= 11.391”; Length= 11.391”

Additional Length:( ����������ℎ/5.5”) =12/22

Additional Length = 3”

Total Length:

11.391” +3” =14.391” =1.2’

Total Length: 1.2’

Total Length= 1.2’ for one side

Total FBM= (8 × 1.2′ × 2" × 6")/12"=�� ������

Roof Joists: 2” ×6” SPF

Roof Sheathing:202.19 BF

From the roof plan,

Total Roof Area: 1971.46 SF

Each Sheath:(4’×8’×3/4”) = 32 SF

Number of Sheaths: 1971.46/32=62 Sheaths;976.5 BF; OSB (9’×4’×7/16”

Girder and Lintels:

Basement Floor:

of Girders

Figure 6: Basement Framing Plan Girders

Posts:

Second Floor and Roof Framing Plan:

For posts between second floor framing plan and roof framing plan 4 P3 and 2 P5 columns are usedsince the drawings are not accurate and it has mistaken. It couldn’t be any columns in perimeter of house in this level regard to section 1 and 2 Posts: 90.42’

Figure 7: Catalog: Wood Construction Connectors 2019-2020 (C-C-2019)

Framing Cap/Base: BC8 Cap/Base Cap:

BC8 Base: 28 BC8

Total of Base/Cap:

Figure 8: Figure 15 Catalog: Wood Construction Connectors Canadian Limit States Design 2018-2019 (C-C-CAN2018)

Sill Plate:

Use 1.55E Timber Strand® LSL 1¾" × 9½" (2” ×10”) over concrete surfaces.

Total Length: 218’

Total BFM:

C1(3

Steel Lintel Main floor:

Wood Works:

Steel Lintels:Second floor:

Steel Lintel Basement:

Wall Stud 22 1.55E TimberStrand® LSL 1 ½” × 5½" (2” ×6”)

Blocking

Floor Joist

Floor:

Basement Framing Plan (Main Floor Joists):Floor Joist:

Figure 10: Specifier's Guide for TJI s31, s33 and s47 Joists for East Canada
9 ½” TJI S47 @ 12”
Figure 9: Basement Framing Plan
TJI S47: 427/384 bf/ft

1:9 ½” TJI S47 @ 12”

Number:5.92’/1’ + 1 = 7 Pieces; Length:16.25’ Each

2:1 ¾” × 9 ¼” LVL / Assume @ 12’

Number:11.17’/1’ +1 = 13 Pieces1; Length:20.25’ Each

3:9 ½” TJI S47 @ 12”

Number:23.34’/1’ +1 = 25 PiecesLength:16.25’ Each

4:9 ½” TJI S47 @ 16”

Number:29.25’×12/16” +1 = 24 Pieces; Length:10.125’ Each

5:9 ½” TJI S47 @ 16”

Number:2.3’×12/16” +1 = 3 Pieces; Length:6.21’ Each

6:9 ½” TJI S47 @ 16”

Number:4.09’×12/16” +1 = 5 Pieces; Length:16.875’ Each

7:9 ½” TJI S47 @ 16”

Number:10.375’×12/16” +1 = 9 Pieces; Length:17.875’ Each

8:9 ½” TJI S47 @ 16”

Number:13.84’×12/16” +1 = 12 Pieces; Length:16.875’ Each

9:9 ½” TJI S47 @ 16”

Number:8.625’×12/16” +1 = 8 Pieces;17.875’ Each

10:9 ½” TJI S47 @ 16”

Number:3.34’×12/16” +1 = 4 Pieces; Length:16.875’ Each

Openings:

Trimmers are not doubled since there are beams over openings. Only for the west side of the opening rim will be put.

Rim Joist:

Regard to “Specifier's Guide for TJI s31, s33 and s47 Joists for East Canada” TJI S47 is used as a rim joist.

Figure 11: Specifier's Guide for TJI s31, s33 and s47 Joists for

North and South:

Length:

2× (5.92+11.17.23.34) = 80.86’

Blockings:

Regard to “Specifier's Guide for TJI s31, s33 and s47 Joists for East Canada” TJI S47 is used as a blocking joist. for over 8’ long floor.

12: Specifier's Guide for TJI s31, s33 and s47 Joists for East Canada

1,2,3 (16.25’):

Put 4 rows of blocking panels (near wall, 2 mid-points and near beam) 16.25/8 +1 =4

Top Row:5.92+23.34+11.17 = 29.26’

Mid-Point 1,2:2(5.92+11.17+23.34) = 80.86’

Bottom Row:5.92+11.17+23.34= 40.43’

Length:29.26+40.43+40.43 = 161.72’

6,7,8,9: Same 4 rows Total length:2(162.72) = 323.44’ of blockings

Double joist for bearing walls.

*All connections are by nail.

In basement framing plan there are different elevations which constructed by knee walls, so

Figure
10.125’ TJI S47

1: Floor Joist: 2” × 6” SPF @ 16”

Number:8.71’×12/16” + 1 = 8 Pieces

Length:4.17’ Each

Rim Joist: 2” × 6” SPF

Number:2 Pieces

Length:8.71’ Each

2: Floor Joist: 2” × 8” SPF @ 16”

Number:6’×12/16” + 1 = 6 Pieces

Length:5’ Each

Rim Joist: 2” × 8” SPF

Number: 2 Pieces

Length: 6’ Each Landing:

Floor Joist: 2” × 6” SPF @ 16”

Number:9.58’×12/16” + 1 = 9 Pieces

Length:3.67’ Each

Rim Joist: 2” × 6” SPF; Number:2 Pieces

Length: 9.58’ Each 9 ½” TJI S47

Total Length:1854.305’;2061.95 BF

1 ¾” × 9 ¼” LVL

Total Length:263.25’;438.75 BF; 2” × 6” SPF

Total Length:102.97’=102.97 BF 2” × 8” SPF; Total Length=42’56 BF

Figure 13: Knee Wall
Figure 14: Stairs

Main Floor Framing Plan (Second Floor Joists):

Floor Joist:

1:9 ½” TJI S47 @ 16”

Number:6.75’×12/16” +1 = 7 Pieces; Length:18.3’ Each

2:9 ½” TJI S47 @ 16”

Number:9.5’×12/16” +1 = 9 Pieces; Length:22.3’ Each

3:9 ½” TJI S47 @ 16”

Number:24’×12/16” +1 = 19 Pieces; Length:18.3’ Each

4:9 ½” TJI S31 @ 16”

Figure 15: Main Floor Framing Plan
Figure 16: Specifier's Guide for TJI s31, s33 and s47 Joists for East Canada

Number:27.25’×12/16” +1 = 22 Pieces; Length:9.92’ Each

6:9 ½” TJI S47 @ 16”

Number:4.09’×12/16” +1 = 5 Pieces; Length:17’ Each

7:9 ½” TJI S47 @ 16”

Number:10.42’×12/16” +1 = 9 Pieces; Length:18’ Each

8:9 ½” TJI S47 @ 16”

Number:13.84’×12/16” +1 = 12 Pieces; Length:17’ Each

9:9 ½” TJI S47 @ 16”

Number:8.59’×12/16” +1 = 8 Pieces; Length:18’ Each

10:9 ½” TJI S47 @ 16”

Number:3.3’×12/16” +1 = 4 Pieces; Length:17’ Each

11:9 ½” TJI S47 @ 16”

Number:3.8’×12/16” +1 = 4 Pieces; Length:1’ Each

Openings: TJI S47:1+2(3.8) = 8.6’

Rim Joist: TJI S47 North and South:2(40.25) = 80.5’

Block: TJI S47 1,2,3

Number of Rows:18.3/8+1 = 4 Rows

Length:4(40.25) = 161’

6,7,8,9

Number of Rows:17/8+1 = 4 Rows Length:4(40.25) = 161’

Total Length of Blocking Panels:322’

Landing and Powder Room:(Main floor)

Figure 17: Landing and Powder Room

Floor Joist: 2” × 6” SPF @ 16”

Number:6.7’×12/16” + 1 = 7 Pieces; Length:3.5’ Each; Rim Joist: 2” × 6” SPF

Number:2 Pieces

Length: 6.7’ Each; Floor Joist: 2” × 6” SPF @ 16”

Number: 3.5’×12/16” + 1 = 4 Pieces; Length:3.5’ Each; Rim Joist: 2” × 6” SPF

Number:2 Pieces

Length: 3.5’ Each.

Floor Joist: 2” × 6” SPF @ 16” (Powder Room)

Number:8.375’×12/16” + 1 = 8 Pieces

Length:3.5’ Each; Rim Joist: 2” × 6” SPF

Number:2 Pieces Length:8.375’ Each

9 ½” TJI S47; Total Length:1754.6’; 1951.08 BF

9 ½” TJI S31; Total Length:218.24’;180.73 BF 2” × 6” SPF

Total Length:103.65’=103.65 BF

Second Floor Framing Plan (Ceiling Joists):

Ceiling Joist and Rim Joist:

Figure 18: Second Floor Framing plan

a: Ceiling Joist: 2” × 8” SPF @ 16”; Number:38.63’×12/16” + 1 = 30 Pieces

Length:15.29’ Each; Rim Joist: 2” × 8” SPF

Number:1 Piece; Length:38.63’

1: Ceiling Joist: 2” × 8” SPF @ 16”

Number: 15.1’×12/16” + 1 = 13 Pieces; Length:12.88’ Each

2: Ceiling Joist: 2” × 8” SPF @ 16”

Number:17.34’×12/16” + 1 = 15 Pieces; Length:12.88’ Each

3: Ceiling Joist: 2” × 8” SPF @ 16”

Number:6.21’×12/16” + 1 = 4 Pieces; Length:6.5’ Each

b: Ceiling Joist: 2” × 8” SPF @ 16”

Number:38.63’×12/16” + 1 = 30 Pieces; Length:15.67’ Each

Rim Joist: 2” × 8” SP

Number: 6.21’×12/16” + 1 = 4 Pieces

Length: 6.5’ Each b: Ceiling Joist: 2” × 8” SPF @ 16”

Number: 38.63’×12/16” + 1 = 30 Pieces

Length: 15.67’ Each, Rim Joist: 2” × 8” SPF

Figure 19: Landing Second Floor

Number:

1. Piece Length:38.63’ Block: 2” × 8” SPF

a: Number: 15.29/8+1= 3 rows Length:38.63’

1: Number: 12.88/8+1= 3 rows Length: 15.1’

2: Number: 12.88/8+1= 3 rows Length: 17.34’

b: Number: 15.67/8+1= 3 rows Length: 38.63’

Double under bearing wall: 15.29+15.29+6.5+15.67= 52.75’.

Subfloor Sheathing

8 ft. long, 4 ft. height and ¾ in. thickness Weyerhaeuser Edge™ oriented strand board (OSB) floor panels is used for subfloor sheathing and the longest direction is Appendix.

Basement Finished Plan:75 sheaths

Basement Framing Plan:(Main Floor)

Number of Columns: (1,2,3) 16.25/4= 5 columns Number of Rows:

40.25/8= 6 rows Sum:5×6= 30 sheaths

Number of Columns: (4) 10.125/4= 3 columns Number of Rows:

30.125/8= 4 rows Sum:4×3= 12 sheaths

Number of Columns: (6,7,8,9,10) 16.88/4= 5 columns

Number of Rows:40.25/8= 6 rows Sum:5×6= 30 sheaths

Additional Parts: (2,3’,5,6’,7,9)

2+1+1+1+2= 7 sheaths Sum:79 Sheath

Main Floor Framing Plan: (Second Floor)

Number of Columns: (1,2,3) 18.3/4= 5 columns

Number of Rows: 40.25/8= 6 rows Sum:5×6= 30 sheaths

Number of Columns: (4) 9.92/4= 3 columns Number of Rows: 27.25/8= 4 rows

Sum:4×3= 12 sheaths

Number of Columns: (6,7,8,9,10) 17/4= 5 columns

Number of Rows: 40.25/8= 6 rows Sum:5×6= 30 sheaths

Additional Parts: (2,3’,11,6’,7,9)

2+1+1+1+2= 7

sheaths Sum:79 Sheaths Total:

233 Sheaths=5592 BF

4’×8’×3/4” OSB=Each Sheath is 24 BF

Figure 20: Floor Framing Plan

For this section, the sequence of activities was first converted from Uni Format to Master Format, which resulted in a list of activities with their corresponding Master Format code. These activities were then categorized into 5 different categories, which correspond to various phases or aspects of the project.

To calculate the project's cost, we used a one-month trial version of RSMeans. However, the trial version only provided access to the Master Format 2018 and cost data from 2011. Therefore, the cost data from 2011 had to be converted to 2023 to fathom how much it would cost were it to be built in 2023.

Hence, the complete cost estimation for constructing this project in 2023 is just over 1.26 million Canadian Dollars.

8. Conclusion

He estimated project cost in 2011 was $805,000. Adjusted for inflation using the Historical Cost Index from RS Means, the 2023 estimate rises to approximately $1.26 million. This figure is about 13.5% higher than the midterm report's conceptual and elemental cost estimates of $1.09 million and $1.11 million.

Girders and Lintels

Basement Floor:

Figure 21: Basement Framing Plan
Figure 22: Main Floor
Figure 23: Second floor

Walls:

Bottom Plate/Top Plate/Wall Stud/Blocking/Hold Downs/Knee WallBasement Plan (above the retaining wall)

There are wooden walls above the retaining walls and also there are wooden interior walls.

Bottom Plates:

Use 1.55E TimberStrand® LSL 1 ½” × 5½" (2” ×6”)

Total length: 100.94’

Total BFM:

100.94 BF

Top Plates:

We used 1.55E Timber Strand® LSL 1 ½” × 5½" (2” ×6”)

Total length with doubling parts: 138.57’

Total BFM:

138.57 BF

Wall Stud:

We used 1.55E Timber Strand® LSL 1 ½” × 5½" (2” ×6”)

We have different height for wall studs.

Total Length of all: (11’x55) +(74x9.515’) +(11x5.71’) +(5.71’x27) +(6.2’x34) +(7.45’x25) +(6.2’x17) =2028.54’

Total BFM:

2028.54 BF

Blocking:

We used 1.55E Timber Strand® LSL 1 ½” × 5½" (2” ×6”)Total Length of all: 88.108

Total BFM:

88.108 BF

Figure 24: Timber Strand LSL

Hold Downs: We used HDB/HD for controlling lateral load.

Total Number:

6 HDB/HD

Walls Sheathing:

We used 9’x4’,7/16” Thickness.

Figure 25: Hold Downs
Figure 26: OSB Wall Sheathing Weyerhaeuser

(25.75x7.45) +(17.5x6.2) +(40.21x6.2) +(6.2x15.125) +(5.71x28.125) +(12.83x5.71) +(9.515x30.618) +(19.86x11) +(16.8x9.515) +(20.83x11) = 1776.04 SF

1 sheath of OSB 9x4 = 15.75 BF Total

Main Floor PlanBottom Plates:

We used 1.55E Timber Strand® LSL 1 ½” × 5½" (2” ×6”)

50 sheaths

787.5 BF

Total length: 333.495’

Total BFM:

333.495 BFTop Plates:

We used 1.55E Timber Strand® LSL 1 ½” × 5½" (2” ×6”)

Total length with doubling parts: 495.56’

Total BFM:

495.56 BF

Wall Stud:

We used 1.55E Timber Strand® LSL 1 ½” × 5½" (2” ×6”)

We have different elevations, so we have different heights for walls and studs.

Total Length of all: (63x10) +(25x11.75) +(64x11.25) +66+117+(60x11.75) +20+(26x11.25) = 2844.25’

Total BFM:

2844.25 BF

Knee walls:

We used 1.55E Timber Strand® LSL 1 ½” × 5½" (2” ×6”)

Figure 27: Timber Strand LSL

(6x2.23) +(8x3.57) =41.94’

41.94 BF

Blocking:

We used 1.55E Timber Strand® LSL 1 ½” × 5½" (2” ×6”)

Total Length of all: 180.405Total BFM:

180.405 BF

Hold Downs:

We used HDB/HD for controlling lateral load.

Total Number:

40 HDB/HD

Walls Sheathing:

We used 9’x4’,7/16” Thickness.

Figure 28L: Simpson Strong-Tie Company Inc.
Figure 29: OSB Sheathing

(355x8.99) = 3191.45 SF

1 sheath of OSB 9x4 = 15.75 BFTotal:

73 sheaths

1149.75 BF

Second Floor Plan:Bottom Plates:

We used 1.55E TimberStrand® LSL 1 ½” × 5½" (2” ×6”)

Total length: 355’

Total BFM:

355 BF

Top Plates:

We used 1.55E TimberStrand® LSL 1 ½” × 5½" (2” ×6”)

Total length with doubling parts: 514’

Total BFM:

514 BF

Wall Stud:

We used 1.55E Timber Strand® LSL 1 ½” × 5½" (2” ×6”) Regular Stud: 382 pieces / Length: 8.99’ /Total length:3434.18’

King Stud: 20 pieces / Total length:179.8’

Jack Stud: 20 pieces/ Total length: 96.67’ Cripple Stud: 50 pieces/ Total length:100’Total Length of all: 3810.65’

Total BFM:

3810.65 BF

Blocking:

We used 1.55E Timber Strand® LSL 1 ½” × 5½" (2” ×6”)

Figure 30: Timber Strand LSL

Total Length of all: 297.336Total BFM:

297.336 BF

Hold Downs: We used HDB/HD for controlling lateral load.

Total Number: Walls Sheathing:

30 HDB/HD

We used 9’x4’,7/16”

(355x8.99) = 3191.45 SF;1 sheath of OSB 9x4 = 15.75 BF ; 89 sheaths;1401.75 BF

Figure 31: Simpson Strong-
Figure 32: OSB Sheathing

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.