RO Mission Critical brochure 2018

Page 1

TEXAS’ PREMIER BUILDER: MISSION CRITICAL



ABOUT ROGERS-O’BRIEN CONSTRUCTION

Since 1969, Rogers-O’Brien has firmly established itself as a leading general contractor in Texas by providing a wide range of preconstruction and construction management services. Our unique approach consistently delivers high quality buildings in a variety of market sectors, exceeding the most demanding expectations. Ethics and integrity serve as the cornerstones for everything we do, and the adherence to these values has earned us a solid reputation. The commitment to our customers is evident in the dedication of our people, our open communication policies, pioneering technology, operational diligence and continued process improvement. Rogers-O’Brien is family-owned, with the third generation leading the company’s operations. The family attitude extends throughout our strong management team, many of whom rose up through the ranks to management. To our offices in Austin, Dallas and Houston, we have also actively recruited a forwardthinking new generation to energize us with knowledge of new tools, techniques and approaches to continually improve the way we deliver services. Others who have joined us in the past decade are seasoned construction professionals, hand-picked for their ability to grow the firm. This controlled growth approach has resulted in $1.5 billion in construction volume over the past five years.


SAFETY At Rogers-O’Brien, we always put safety first, believing it is our duty to provide the safest possible workplace for our employees, jobsite partners and clients. Our dedicated safety personnel directs our proactive approach to environmental, safety and health programs that Rogers-O’Brien has refined over the course of four decades. Our program includes customary requirements such as background checks and drug screening for all new employees; subcontractor compliance with our substance abuse policy and safety procedures; and maintaining a minimum level of OSHA 30-hour safety training for all management-level personnel. We also assign each new employee a work partner until the safety director has completed an assessment of that employee and identified his/her training needs. We have a long-established partnership with OSHA to identify and eliminate potential hazards in the industry and establish the safest environment possible for our subcontractors.We consistently maintain an Experience Modification Rate (EMR) well below industry average. Rogers-O’Brien won 2nd place in the National AGC Construction Safety Excellence Awards Competition and has won the ABC Safety Star Award for two consecutive years.


COLLABORATIVE PROJECT PLANNING The mission of Collaborate Project Planning is to proactively impact project cost and schedule through creating a higher level of document detail by conducting team constructability reviews during early document development. Rogers-O’Brien Construction implements Collaborative Project Planning (CPP) on all of its projects. This is a fresh approach to our preconstruction delivery process greatly benefits many of our projects. CPP focuses on engaging with the architect, its consultants and Owner immediately and intensely after our selection to most effectively prepare for the commencement of construction. During our constructability review, we provide more detailed information that assists the design team, RO’s preconstruction professionals, our trade partners and their personnel to more effectively and accurately prepare estimates and field documentation. By engaging in this effort early, it will significantly reduce the need for RFIs and lessen the need for architect changes to the design documents. What’s included in CPP: • Interdisciplinary coordination • Constructability reviews • Virtual Model Reviews • Model and document guidance • Building Envelope Review & Detail Development


TECHNOLOGY DRIVES QUALITY An early adopter of Building Information Modeling (BIM), Rogers-O’Brien actively uses technology to enhance team collaboration and achieve operational efficiencies, faster project delivery and lower total project costs. Our staff includes recognized industry leaders in BIM that have authored national journal articles and presented to international audiences. Our technology team keeps current on BIM software such as Autodesk Revit and Navisworks; Innovaya to generate quantities and costs directly from either architect’s electronic files or our internally built models; Timberline estimating software to develop and analyze project costs; and Primavera products for scheduling. This technology team also manages our online portal for all team members to distribute and electronically review project data and documents. Rogers-O’Brien harnesses the power of technology to improve project delivery in these key areas: •

During design, our estimators quickly develop new take-offs and re-price the effects of major design revisions like changing the building skin.

Laser scanning of existing structures helps coordinate renovation design.

Project managers analyze site logistics and construction sequences.

Virtual models are used by superintendents to show work crews exactly how completed work should look; IPads are used in the field to compare in-place construction to virtual models and quickly resolve any variances.

Subcontractors can pre-fabricate MEP systems, wall sections, or even entire rooms based on the model, reducing job site labor and clutter.

At project completion, information-rich 3D as-built drawings act as a virtual operating manual.


MISSION CRITICAL PORTFOLIO


CONFIDENTIAL CLIENT FORTUNE 50 CLIENT, SAT 09 & 10 SAN ANTONIO, TX

Owner: Confidential Architect: Corgan Associates Critical Power: 36.8 MW Size: 395,000 SF Schedule: 18 months

Both buildings 09 & 10 are complete data centers with four (4) 4.6 MW colo rooms (8 total). Each building will have a total IT capacity of 18.4 MW, totaling 36.8 MW. Each colo is powered by three (3) 1.46 MW electrical and UPS line ups (cells) located in adjacent electrical rooms. Each building will have two (2) MDF rooms, and one Facility Ops/ Administration. • • • • • • •

Each building’s total IT capacity is 18.4 MW including IDF capacity. 19.2 MW if AHUs are operated within clean filter conditions Full build-out total IT capacity of 36.8 MW including IDF of 38.4 MW if AHUs are operated within clean filter conditions Each Colo is powered by three 2 MW generators and six (6) 800 Kw UPS Four 200kW IDF with common 2 MW generator (SAT 09) One maintenance reserve electrical line-up and distribution for each building for a maximum 13:1 (Cell:MR) redundancy ratio. 4+1 distribution system with 2.5 MW generators for chiller power. Fed from same MV as Colos.


COMPASS DATA CENTER ALLEN, TX

Owner: Compass Datacenters Architect: DLB Associates MEP Engineer:

\89\89517\111 Drawings\DFWII ‐ OVERVIEW.dwg, 9/8/17 at 2:52 PM By MMANGAN ‐ Last Printed: 9/8/17 at 6:02 PM By Mangan, Michael

DLB Associates Critical Power: 1.2 MW Size: 24,000 SF Schedule: 6 months

The Compass Data Center in Allen, TX contains 24,000 SF of white space and 5,500 SF of office space. Additionally there is 3000A Service Building. Notable features include: • • • • • • • • •

1.2MW N+1 Designed Facility (2) 1.825kW generators Skid mounted Power Center setup 3000A Building Service 1.2kva of IT Load 400kW of cooling Building 1 of 3 on this site Will be Uptime certified


CYRUS ONE

Building I, Phase 1 & 2 SAN ANTONIO, TX

Owner: CyrusOne Architect: Corgan Associates

Phase I includes 86,297 SF build-out of Data Hall including 40,000 SF of white space. 2.25 MW Day 1 with infrastructure included allowing immediate expansion to 4.5 MW. The 29,733 SF interior finish-out includes office, main lobby and corridors of existing shell building.

MEP Engineer: RDMC

Phase II encompasses the complete MEP fit-out of the existing facility.

Owner’s Rep: Critical Project Services

phase included 6.75MW for a total of 9MW facility. This second phase

Critical Power: Phase 1: 2.25 MW Phase 2: 6.75 MW Size: 200,000 SF Schedule: Phase 1: 14 weeks Phase 2: 16 weeks

During Phase 1, Rogers-O’Brien installed 2.25MW and in this second schedule is 16 weeks from start through Level 5 Commissioning.


CYRUS ONE Building II

SAN ANTONIO, TX

Owner: CyrusOne

Building II started as site retaining walls only for two new building additions adjacent to the current site and then evolved into the entire Building 2 facility including data center fit up complete in 7months. A project of this magnitude has never been done in this time frame.

Architect: Corgan Associates MEP Engineer: KW Mission Critical Engineering Owner’s Rep: Critical Project Services Critical Power: 18 MW Size: 188,617 SF Schedule: 7 months

This tilt-wall and precast structure houses a single tenant (Fortune 100 client) with 18 MW of critical load, totaling 188,617 SF. With a 7month schedule, this ground-up project was completed on time from start to a fully commissioned data center with 4 months of around-the-clock construction. To reduce noise to an adjacent residential neighborhood and two separate utility yards, 30’ tall sound barrier walls were installed on the entire west side of the project site. These walls consisted of poured-inplace concrete, tilt panels and precast at various areas of the building to remain within the sound ordinance levels. This 2 - story building includes: • 16 - 2.25 MW generators • 48 - 750KW UPSs • 96 - 600A STS/PDUs • 16 - 425 ton roof mounted chillers • 48 - 6,000 cfm CRAH units


CYRUS ONE Building III

SAN ANTONIO, TX

Owner: CyrusOne

This tilt-wall and precast structure is designed to accommodate a single tenant or a co-location environment. This facility consists of

Architect: Corgan Associates MEP Engineer: KW Mission Critical Engineering Owner’s Rep: Critical Project Services Critical Power: 9 MW Size: 101,159 SF Schedule: 5 months

9 MW of critical load in a building totaling 101,159 SF (7 acres). With a 5 month schedule, this ground-up project from start to a fully commissioned data center will include around-the-clock construction. To reduce noise to an adjacent residential neighborhood and two separate utility yards, 30’ tall sound barrier walls were installed on the entire west side of the project site. These walls consist of poured-inplace concrete, tilt panels and precast at various areas of the building to remain within the sound ordinance levels.


TIME WARNER CABLE (NOW SPECTRUM)

LEWISVILLE AND PLANO, TX

Owner:

Lewisville:

Time Warner Cable

This Hub site expansion for Time Warner Cable, servicing their new TWC Maxx

Now Spectrum

product, includes remodel of interior spaces creating a new mechanical and standalone electrical room; replacement and upgrade of the existing 400A to an 800A

Architect: Carlton MEP Engineer: RDMC

from utility, new electrical equipment and generator; removal and replacement of acoustical ceiling grid and ductwork above ceiling in Data Center for increased cooling system capacity. Other upgrades include removal of 4� concrete slabs in mechanical and electrical spaces and replacement with an 8� thick slab to accommodate additional equipment weight; coordination of replacement and upgrade of existing DC plant and doubling the current capacity and installation of new air purge system to tie in with gas cylinder Fire Suppression System.

Plano: This location includes the addition of two new CRAC units and roof mounted condensers; replacement and upgrade of the existing 400A to an 800A from utility, new electrical equipment and generator; and doubling the current capacity of the gas cylinder Fire Suppression System. Other upgrades include the addition of acoustical panels at the generator yard for sound attenuation and installation of a new air purge system to tie-in with gas cylinder Fire Suppression System.


INSYS THERAPEUTICS ROUND ROCK, TX

Owner:

INSYS Therapeutics is a specialty pharmaceutical company that develops

INSYS Therapeutics, Inc

and commercializes innovative products for supportive care of pain patients. The INSYS Therapeutics Facility project entailed the interior demolition of

Architect:

a 60,000 SF warehouse and the interior build out of a new pharmaceutical

Page

manufacturing facility. Along with the renovation of the exterior faรงade, the project scope also includes the addition of an 8,000 SF Class 10,000 Clean Room and another 20,000 SF of process space to accommodate the manufacturing of a range of patented pharmaceutical products.


INFOSYS DATA CENTER PLANO, TX

Owner:

The conversion of an existing Class A office space into a new 5,000 SF data

BradfordManagement

center was achieved in three short months in a fully occupied building without

Company, Inc.

incident or disruption of service to occupants. The supporting infrastructure areas are protected by an Inergen fire suppression system as well as a city

Architect:

required, redundant fail safe pre-action system. The requirement for stand-

Architeriors

alone and uninterrupted operation of servers required that new dedicated

MEP Engineer: Nelson H2L2

infrastructure be added, including new electrical service, UPS, standalone Chilled Water Cooling System with air cooled chillers and an emergency generator for back-up power. A new service yard (tilt-wall enclosure) was constructed in the adjacent parking lot for securing the generator and cooling tower from outside interference or tampering.


APPLIED MATERIALS AUSTIN, TX

Owner:

The projects total over 1.5 million SF of office, clean room and manufacturing

Applied Materials

space. All of the buildings were design/build projects, and have been built on fast-track schedules.

Architect: Graeber Simmons & Cowan

Building 30 200,000 SF Office & manufacturing

Building 36 300,000 SF Office/clean room

Building 31 184,000 SF Office & manufacturing

Building 46 100,000 SF Office/clean room

Building 32 188,000 SF Office & manufacturing

Building 34 380,000 SF Office/clean room

Building 33 204,000 SF Office & manufacturing


TEXAS INSTRUMENTS DMOS PHASE II DALLAS, TX

Owner:

Texas Instruments, Inc. DMOS 5, Phase II, includes the construction of a three-

Texas Instruments

story Computer Wafer Fabrication facility. The building is designed around a 65,000 SF clean room with support area of 455,000 SF for systems servicing the clean room function. Additionally, a five-story Administration Building of 120,000 SF was required for the administrative functions of the clean room. Also included is a chemical dock and a deionized water building. This complex, totaling 650,000 SF is connected to an existing operating clean room facility - DMOS 5 Phase I and required a 12-month construction schedule. DMOS 5 Phase II is an addition to Phase I, which was also completed by RogersO’Brien.


SAMSUNG

SEMICONDUCTOR U-FAB FACILITY AUSTIN, TX

Owner:

Samsung’s U-Fab project was Samsung’s first semiconductor facility in the

Samsung Austin

United States. The $305 million project had a construction management

Semiconductor

team comprised of several general contractors. Our team members served as the General Contractor for the 120,000 squarefoot, Class 1 clean room as well as the exterior precast building wall systems. The Project Team also contributed to supervision of the project overall project including mechanical QA/QC, and structural and architectural Quality Control.


SETON MEDICAL CENTER DATA CENTER UPGRADES AUSTIN, TX

Owner:

This two-phase project, totaling 3,195 SF, included replacing the existing HVAC unit

Seton Healthcare

system that fed Seton’s main network data center with new ductwork, a new HVAC

Network

unit, CRAC unit and upgraded the finishes within the data center. Rogers-O’Brien kept the data center on line at all times during construction maintaining cooling, vibration and dust control throughout the project duration.


CONTACT Graham Merriman Vice President, Director of Client Relations 1901 Regal Row Dallas, Texas 75235 (214) 962-3000, office (214) 534-9696, cell gmerriman@r-o.com

www.r-o.com


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.