Save the Rain Quarterly Report Q3 2015

Page 1

Save the Rain

Third Quarterly Report 2015

July - September 2015 Joanne M. Mahoney County Executive

www.savetherain.us


ONONDAGA COUNTY DEPARTMENT OF WATER ENVIRONMENT PROTECTION VISION To be a respected leader in wastewater treatment, storm water management, and the protection of our environment using state-of-the-art, innovative technologies and sound scientific principles as our guide.

MISSION To protect and improve the water environment of Onondaga County in a cost-effective manner ensuring the health and sustainability of our community and economy.

CORE VALUES

Excellence Teamwork Honesty Innovation Cost-Effectiveness Safety


Table of Contents Report from Commissioner Gray Projects Update  

Progress of Projects Under Construction Fact Sheets

Green Projects Update  

Projects Summary Fact Sheets

Green Improvement Fund Update  

Green Improvement Fund Program Summary Fact Sheets

Metro WWTP Phosphorus Projects/TMDL/Ambient Monitoring Program Update    

Metro Phosphorus Optimization Project Metro Phosphorus Work Plan Project Onondaga Lake Water Quality Model Ambient Monitoring Program Water Quality Sampling Tributary Sampling Tributary Bacteria Compliance Assessment Onondaga Lake Sampling Biological Monitoring Program Sampling Summary

Legislative/Regulatory/Media Update   

Action Items for County Legislature Action Items for the Environmental Protection Committee Media Articles

Financial Update 

Contracts New Contracts Amendments to Existing Contracts Change Orders

Funding State Bond Act Funds Federal EPA Funds


Federal Army Corps of Engineers Funds EFC Loans 

Onondaga County Lake Improvement Project Fourth Stipulation of the ACJ Clinton/Lower MIS CSO Improvement Harbor Brook Drainage Basin CSO Abatement Midland CSO Abatement Sewer Separation of CSO Areas: 022/038/040/045/046A/046B/047/048/050/051/053/054 Save the Rain Education and Outreach Grant Appendix     

Project Payments Lake Improvement Project Status Report Federal and State Grants/Loans Approved and Received Chronology of Project Construction Starts Contractors for Construction Projects  Metro Treatment Plant  CSOs WEP Acronyms




GRAY PROJECTS UPDATE



Cit

FACT SHEET Harbor Brook CSO 063 Conveyances Project

Project: Project Owner: Project Location: Sewershed: No. of CSOs Abated: Contract Amount: Bid Date: Completion Date: Prime Contractor:

CSO 063 Conveyances Onondaga County Harbor Brook, Erie Blvd. W. Harbor Brook 1 $6,065,362 (updated) April 28, 2014 September 11, 2015 (Beneficial Occupancy) Marcellus Construction, Inc.

Project Description: The Harbor Brook CSO 063 Conveyances Project is the final conveyance pipeline associated with the Lower Harbor Brook CSO Storage Facility. This connection allows additional wastewater to be stored at the facility for eventual treatment at the Metropolitan Wastewater Treatment Plant. Construction update: Marcellus Construction, Inc. completed construction on the new pipeline on August 6th, 2015. At that time the Lower Harbor Brook Storage Facility began accepting CSO flow from the 063 basin via the new 60-inch Emerson Truck Sewer extension and the 48- and 60-inch CSO conveyance sewers. By August 20th, 2015 the new CSO 063 outfall was fully operational with the installation of the stainless steel stop logs to the proper weir height. The contractor completed the final restoration of all surfaces and the installation of the new slide gates in the grit chamber in Erie Boulevard West on September 11, 2015 and the Certificate of Beneficial Occupancy was issued. Final closeout of the project will continue into the next quarter. The final project included the installation of the following major components: • • • • • •

575 linear feet (LF) of 60-inch diameter sewer from Emerson Ave to Erie Boulevard West New CSO 063 regulator manhole and grit chamber in Erie Boulevard West 1600 LF of 48 and 60-inch diameter CSO conveyance pipeline New CSO 063 diversion manhole and outfall to Harbor Brook 715 LF of 48-inch diameter CSO conveyance sewer The cleaning of 73 catch basins, 46 rehabilitations, 7 replacements and installation of 73 oil and debris catch basin hoods

(Left to Right) New CSO 063 diversion and trash rack structures, restored Erie Boulevard West, restored Emerson Avenue, and new CSO 063 outfall to Harbor Brook. Version 10/8/15



GREEN PROJECTS UPDATE



Green Projects Update This construction season, progress has continued on several Save the Rain projects that are underway. Construction of Phases 2 and 3, the final phases of the Connective Corridor project, were completed during this quarter along East Genesee and East Fayette Streets through Downtown Syracuse. The project was a comprehensive reconstruction of these streets in partnership with Syracuse University and the City of Syracuse and a continuation of earlier phases of the project constructed in 2011 and 2013. The green infrastructure elements installed as part of the project include porous pavers in parking lanes and snow storage areas and enhanced tree pits. In total, the green infrastructure installed in Phases 2 and 3 captures approximately 10.6 million gallons annually. Overall, the green infrastructure practices in the combined three phases of the Connective Corridor captures over 26 million gallons annually. Construction began on the Southwest Community Center project this quarter. The project includes a reconstruction of the Community Center’s parking lot with porous pavement and an underground infiltration trench. Construction is anticipated to be completed at the community center by November 2015. The design for the Green Separation in CSO 052 project has progressed during the third quarter. A new stormwater management system will be constructed on the former Garzone’s Restaurant property to manage ponding on-site, as well as additional stormwater from Cornell and South avenues. A separate storm sewer will be constructed on Mitchell Avenue between South Avenue and Armstrong Place that will capture road runoff from Mitchell Avenue. The proposed project will provide the dual benefit of managing stormwater runoff into the combined sewer system and reducing localized flooding episodes in the neighborhood. A design review public meeting was held on the evening of September 22, where residents provided feedback on the current design and were informed of the anticipated schedule for construction of the project in 2016. The design of the State Street Green Corridor project began during the third quarter. The project is funded in part by a Water Quality Improvement Project grant from the New York State Department of Environmental Conservation (NYSDEC) and includes several green infrastructure practices to be installed along State Street in three different segments; Taylor St. to Adams St., Fayette St. to Water St., and James St. to Salina St. Design will continue through fall and winter with construction planned to begin during Spring 2016. The Green Planning Committee (GPC) continues to make progress in strategic green infrastructure planning. Through the work of the GPC, several road reconstruction project opportunities in the CSO060 and 077 sewersheds have been developed with preliminary design starting during the quarter. Additionally, the GPC is working with the County and City in planning a green street in the Butternut Circle corridor. Planning efforts for future projects will continue with a focus in CSOs 029 and 067.


Project: Project Owner: Project Location:

FACT SHEET Connective Corridor: Phase 2/3

Sewershed: CSO: GI Technology: Capture Area: Runoff Reduction: Year Contracted: Bid Cost: Prime Contractor:

Connective Corridor – Phases 2 and 3 City of Syracuse East Genesee St. from Forman Ave. to State St. and West Fayette St. from Townsend St. to West St. Clinton/Lower MIS 026, 027, 029, 030 Green Street 623,000 sq. ft. 10,975,000 gal/yr 2013 $973,255.00 (green infrastructure cost) Barrett Paving Materials, Inc.

Project Description: The final phases of the Connective Corridor (Phases 2 and 3) were constructed throughout 2014 and 2015. The project exemplified the continued partnership of Onondaga County with the City of Syracuse and Syracuse University. The green infrastructure installed on the project includes porous pavers in parking lanes and snow storage areas, tree pits, and underground infiltration trenches. Also included in the project is the manufactured treatment device providing water quality treatment for the West Fayette Street Sewer Separation project that was completed in 2013. The green infrastructure installed on Phases 2 and 3 of the Connective Corridor captures runoff from streets, adjacent hardscapes and upstream areas; a total of 623,000 square feet of drainage area. This equates to an estimated 10,975,000 gallons of stormwater capture annually, making this project one of the largest projects in the Save the Rain Program to date. These final two phases will complete the Connective Corridor. Phase 1 and Forman Park included similar green infrastructure and were completed in 2011 and 2013, respectively. In addition to providing significant runoff reduction for the Save the Rain Program, the Corridor also creates a valuable link between the Downtown and University communities. In total, the three phases of the Connective Corridor capture an estimated 26 million gallons of stormwater annually.

Porous Pavers and Plantings within East Genesee Street Median

Porous Paver Parking Lane and Snow Storage Area on East Genesee Street at Forman Park Version 10/5/2015


Project:

FACT SHEET Harbor Brook CSO 018 Constructed Wetlands Pilot Treatment System

Project Owner: Project Location: Sewershed: CSO: GI Technology: Capture Area: Runoff Reduction: Year Contracted: Year Completed: Constructed Cost: Prime Contractors:

Harbor Brook CSO 018 Constructed Wetlands Pilot Treatment System Onondaga County Velasko Road & Grand Avenue Harbor Brook 018 Constructed Wetland 1,966,000 sq. ft. 14,880,000 gal/yr 2012 2015 $4,519,790.65 Compensatory Storage – AJ Montclair General Construction – JJ Lane Electrical – Patricia Electric

Project Description: The Harbor Brook CSO 018 Constructed Wetlands Pilot Treatment System serves dual purposes of treating overflows from CSO 018, currently discharged into Harbor Brook, while also acting as a demonstration project to test the effectiveness of three types of constructed wetland treatment systems (floating wetland island, vertical down flow, and surface water treatment wetlands). In 2011, the Compensatory Storage portion of the work was completed. Construction of the pilot wetlands treatment system began in 2012, and the system was put online in April of 2015. Based on the knowledge gained from this pilot project, these wetland systems may be integrated as part of a larger constructed wetland treatment system along Harbor Brook with additional water quality, natural habitat, recreational, educational, and other community benefits. The project is located within the approximately 34 contiguous acres of Onondaga County owned land known as the Velasko Road Detention Basin. This constructed wetland pilot project treats approximately 14.9 million gallons of combined sewage each year and substantially improves the quality of the stormwater discharge into Harbor Brook.

Version 10/5/2015

Aerial View of Harbor Brook Wetlands (September 2013) and Ground Photos of Each Cell (2015)


Project:

FACT SHEET Green Roof at the Magnarelli Community Center

Project Owner: Project Location: Sewershed: CSO: GI Technology: Capture Area: Runoff Reduction: Year Contracted: Construction Cost: Contractor:

Green Roof at the Magnarelli Community Center City of Syracuse Parks 2300 Grant Blvd Clinton 020 Green Roof 10,400 sq. ft. 183,000 gal/yr 2014 $304,000 Josall Syracuse, Inc.

Project Description: The Green Roof at the Magnarelli Community Center highlights the continued partnership of the Save the Rain program with the City of Syracuse Parks Department. This project is the first green roof constructed on City Parks’ property, and the tenth overall Green Park project in the Save the Rain program to date. As part of the partnership on this project, the City Parks Department funded the cost of re-roofing the Community Center, while the Save the Rain program funded the cost of the green roof system.

Two separate green roofs were installed at the Community Center. One was installed on the roof above the gymnasium and the other on a lower roof. The vegetated portion of the green roof consists of a low-growing sedum mat that features many vibrant colors throughout the year. The green roof system at the Magnarelli Community Center captures approximately 183,000 gallons of stormwater annually.

Typical Green Roof Sedum Plants

Photographs of the Completed Green Roof at the Magnarelli Community Center Revised 10/5/2015


Project: Project Owner: Project Location:

Green Separation CSO 052 City of Syracuse 2426 South Avenue and Mitchell Ave. between South Ave. and Armstrong Pl. Sewershed: Midland CSO: 052 GI Technology: Detention/Slow Release and Storm FACT SHEET Sewer Separation Green Separation CSO 052 Capture Area: 241,706 sq. ft. Runoff Reduction: 1,241,900 gal/yr (estimated) Mitchell Avenue Year Contracted: TBD Bid Cost: TBD Project Description: Contractor: TBD This project will be accomplished through the collaborative efforts of Onondaga County and the City of Syracuse. Historically, the area around the proposed detention basin has been prone to severe flooding throughout the year. This is due, in part, to years of illegal dumping that impacted the natural groundwater flow patterns. The County and the City have partnered to help limit this problem through the installation of a slow-release stormwater detention basin. Additionally, the County is undertaking a storm sewer separation project on Mitchell Avenue to separate stormwater from the existing combined sewer system. The primary goal of the project is to reduce the volume of stormwater that flows into the combined sewer system along South, Cornell, and Mitchell avenues, all within CSO 052. The secondary goal is to reduce the level of flooding experienced in this area. The new detention/slow release facility will be constructed on property owned by the City of Syracuse and will capture runoff from South and Cornell avenues as well as from the City’s property. The facility will have the capacity to store 1,051,000 gallons of stormwater during rain events. The stormwater will be slowly released to the Armstrong Place sewer system. It is expected that the detention/slow release facility will improve the stormwater management and drainage in this area and lessen the effects of flooding onto residential properties that adjoin the City property. Additionally, runoff from Mitchell Avenue will be collected in a new storm sewer and redirected to the west to the existing Corcoran High School stormwater detention basin which discharges into Furnace Brook. Over 240,000 square feet of drainage area will be improved and managed, resulting in a total runoff reduction of over 1 million gallons annually.

Example of Residential Flooding

Green Separation in CSO 052 Drainage Area Version 10/12/2015


FACT SHEET Southwest Community Center

Project: Project Owner: Project Location: Sewershed: CSO: GI Technology: Capture Area: Runoff Reduction: Year Contracted: Bid Cost: Prime Contractor:

Southwest Community Center City of Syracuse Parks Dept. 401 South Avenue Midland 030 Porous Pavement 44,000 sq. ft. 803,600 gal/yr 2015 $351,646.50 General Construction: DE Tarolli Landscaping: J&J Landscaping

Project Description: This project exemplifies the continued partnership between Onondaga County and the City of Syracuse through the Save the Rain Program. The Southwest Community Center (SWCC) parking lot was extremely deteriorated, which rendered a significant portion of the lot unusable and in need of immediate repair. The existing parking lot will be removed and a new, improved parking lot will be constructed in its place. The new parking lot includes porous asphalt and infiltration stone which facilitates the infiltration of stormwater, reducing the amount of runoff from the site into the sewer system. Also, in order to maximize the stormwater capture benefit of the project, runoff from Lincoln Avenue and Clover Street is also directed into the parking lot infiltration bed. In total, 44,000 square feet of drainage area will be managed by the green infrastructure within the parking lot.

SWCC Parking Lot Condition Before Construction

The SWCC campus will also be enhanced with new plantings along Clover Street that will also decrease the Community Center’s maintenance efforts. The new plantings include cone flowers, coral bells, and creeping phlox, among others, which will significantly reduce the square footage of green space that SWCC is required to mow. Construction is expected to be substantially complete in November 2015. Upon completion, the green infrastructure elements installed at the SWCC will capture approximately 803,000 gallons of stormwater annually.

Installation of the Infiltration Bed in the New SWCC Parking Lot Version 10/12/2015


Project: Project Owner: GI Technology: Project Location:

FACT SHEET State Street Green Corridor

Sewershed: CSO: Capture Area: Runoff Reduction: Bid Price: Year Contracted: Contractors:

State Street Green Corridor Onondaga County Bioretention, Bioswales, Porous Paver Parking Areas State Street Corridor between Burt St. and N. Salina St. Clinton/Lower MIS 021, 027, 034, 080A TBD TBD TBD Estimated 2016 TBD

Project Description: The State Street Green Corridor project is a comprehensive green street application on South State Street between Burt and East Adams streets, between East Fayette and East Water streets and along North State Street between James and North Salina streets. This project demonstrates green infrastructure applications at key points along the State Street corridor to capture stormwater and enhance the urban streetscape in this area. The project will incorporate enhanced tree plantings in the right-ofway; installation of porous pavers in parking lanes; use of infiltration trenches and planters; and traditional bioretention measures and landscape features throughout project boundaries along the State Street corridor.

Additionally, parking bump outs will be installed at key intersections to enhance the pedestrian space in those areas and provide greater definition of parking lanes. This project will be funded in part by the NYS Dept. of Environmental Conservation through their Water Quality Improvement Project (WQIP) Program. In 2015, the County received a WQIP grant of $1.8 million for the project.

Example of Porous Pavers Which Will be Installed Along State Street

Map of Project Locations (Outlined in Red) Version 10/9/2015



GREEN IMPROVEMENT FUND



Green Improvement Fund Projects Update Four Green Improvement Fund (GIF) projects have been completed thus far in the 2015 construction season: Ra-Lin’s (green roof), Zip Networks (green roof), Crest Acura (porous pavement), and St. Joseph’s Hospital Hickory Street parking lot (underground infiltration). During the third quarter of 2015, construction began for GIF projects at Tucker Missionary Baptist Church (porous pavement), St. Joseph’s Hospital Prospect Ave. parking lot (underground infiltration), 538 Erie Blvd. (underground infiltration), 712 East Fayette Street (porous pavement and underground infiltration), and Marcellus Commons (underground infiltration) Completion of these projects is expected during the fall of 2015. The County will continue to work with owners of projects currently under contract to help progress them towards construction and completion. The program will also continue to work with completed GIF projects to ensure maintenance compliance and documentation.

Green Improvement Fund Summary (as of 9/30/15) Projects Completed

79

Contract/Implementation Phase

28

Projects in Award Phase

5

Applications Under Review

3

Inactive/Ineligible

25

Total Applications Received

140


Project: Project Owner: Project Location: Sewershed: CSO: GI Technology:

FACT SHEET Green Improvement Fund Auto Row Realty (Crest Acura)

Capture Area: Runoff Reduction: Year Completed: GIF Award:

Auto Row Realty Private 741-745 West Genesee Street Clinton 066 Porous Pavement, Added Green Space 34,207 sq. ft. 639,000 gal/yr 2015 $164,000.00

Project Description: The Green Improvement Fund (GIF) project at Auto Row Realty is located at 741-745 West Genesee Street. The site will now serve as additional parking for the Crest Acura dealership facility. Much of the site consisted of impervious areas, which produced large amounts of stormwater runoff. In order to manage the property runoff from the large impervious surfaces, Crest Acura partnered with the Save the Rain Program to implement green infrastructure elements on site. The project features a 16,014 square feet parking area that was converted from standard asphalt porous asphalt. The porous asphalt will now manage runoff from 15,800 square feet of impervious drainage area in addition to the porous surface area. The plumbing system within the building was modified to direct the roof runoff to the stone storage beneath the porous asphalt. In addition to the porous asphalt installation, the project removed approximately 2,380 square feet of pavement, converting it into a grass lawn.

Infiltration Stone beneath Porous Asphalt

Approximately 18,395 square feet of green infrastructure was installed to capture an estimated 639,000 gallons of stormwater annually. Porous Asphalt Installation

Version 10/01/2015


Project: Project Owner: Project Location: Sewershed: CSO: GI Technology:

FACT SHEET Green Improvement Fund St. Joseph’s Hospital Hickory St

Capture Area: Runoff Reduction: Year Completed: GIF Award:

St. Joseph’s Hospital – Hickory Street Private 410 Hickory Street Clinton 020 Underground Infiltration, Tree Plantings 19,000 sq. ft. 334,600 gal/yr 2015 $33,100.00

Project Description: The Hickory Street parking lot project is one of two Green Improvement Fund (GIF) projects at St. Joseph’s Hospital and is located at 410 Hickory Street. St. Joseph’s Hospital has been providing services to patients throughout the City of Syracuse since 1869. The project included a demolition of a vacant building to provide space for more parking. As an effort to manage the stormwater runoff in this large impervious area, St. Joseph’s partnered with the Save the Rain Program to implement green infrastructure elements on site. The stormwater runoff is captured through a series of underground storage chambers and infiltration stone. Stormwater entering the system is directed into the storage chambers beneath the parking area where it is stored until it infiltrates back into the ground. The project also incorporated tree plantings throughout the perimeter of the parking area to provide water quantity and quality benefits as well as aesthetics.

Installation of Underground Infiltration System

Approximately 1,235 square feet of green infrastructure was installed to capture an estimated 334,600 gallons of stormwater annually.

Version 10/01/2015

Photo of the New Parking Lot Installed Above the Underground Infiltration System



METRO WWTP PHOSPHORUS PROJECTS /TMDL/AMBIENT MONITORING PROGRAM UPDATE



ACJ Quarterly Status Report – 3rd Quarter 2015 Metro WWTP Projects Metro WWTP Phosphorus Optimization Project This project is currently in the design phase by GHD Consulting Engineers. The expected construction completion is in 2018.

Ambient Monitoring Program (AMP) Tributary Monitoring Program Tributary Sampling Summary (July - September 2015) July 2015:  Tributary Bacteria sampling events: July 13, 23, and 29  Tributary Biweekly sampling events: July 7 and July 21  Conducted Tributary Post-Construction Compliance Monitoring (PCCM) Event (Harbor Brook): July 30  Completed Tributary Macroinvertebrate field sampling on July 22 and 27 August 2015:  Tributary Bacteria sampling events: August 10, 20, 24, and 31  Tributary Biweekly sampling events: August 4 and 18  Conducted Tributary PCCM Event (Onondaga Creek): August 11  Completed first juvenile seine event on August 8 and 10 September 2015:  Tributary Bacteria sampling events: September 10, 17, and 23  Tributary Biweekly sampling event: September 15  Tributary Quarterly sampling event: September 1  Tributary High Flow sampling event: September 30  Conducted Tributary PCCM Events (Harbor Brook): September 9 and 29  Completed second juvenile seine event on September 14 and 16  Completed annual fall electrofishing event: September 20 -23


Tributary Bacteria Compliance (May - July 2015) Table 1 below summarizes the results of the bacteria compliance assessment for samples collected at the routine AMP sampling sites during the May through July 2015 tributary sampling events.

Table 1: AMP Tributary Bacteria Monthly Compliance Assessment1 (May - July 2015) Sampling Site Harbor Brook Velasko Road Hiawatha Boulevard Onondaga Creek Dorwin Avenue Kirkpatrick Street Ley Creek at Park Street Ninemile Creek at Lakeland (Route 48) Bloody Brook at Onondaga Lake Parkway Tributary 5a at State Fair Boulevard

May 2015

June 2015

July 2015

√ X

X X

X X

√ X X √ X √

X X X X X √

√ X X √ √ √

1

Compliance assessed with the applicable NYS Ambient Water Quality Standard (AWQS) for Fecal Coliform bacteria in the surface water as set forth in 6NYCRR Part 703.4 as follows: “The monthly mean geometric mean, from a minimum of five examinations, shall not exceed 200.”

Tributary Annual Loading Estimates (2014) Percent contributions to 2014 total load to Onondaga Lake for two key water quality constituents (a) total phosphorus (TP) and (b) fecal coliform (FC) bacteria tracked as part of the AMP are presented in a graphical format. The largest total phosphorus (TP) and total dissolved phosphorus (TDP) loads to Onondaga Lake were delivered by the two largest tributaries, Onondaga Creek (46%) and Ninemile Creek (27%). The TDP fraction is a better representation of bioavailable forms than is total phosphorus, as a large portion of particulate phosphorus is typically unavailable to support algal growth. In an effort to reduce phosphorus levels in stormwater runoff, New York State restricted the use of phosphorus fertilizer on lawns and non-agricultural turf beginning January 1, 2012. The primary sources of fecal coliform (FC) bacteria loads in 2014 were Onondaga Creek (35%) and Ninemile Creek (29%).


2014 Percent Contribution to Total TP Load (%) T5a 1%

Bypass 4% Metro 13%

East Flume Manhole 015 0% Harbor 1%

Onondaga 46%

Ley 8% Ninemile 27%

2014 Percent Contribution to Total FC Load (%) T5a 0%

Metro 5% Bypass 15%

Onondaga 35%

East Flume Manhole 015 0% Harbor 3% Ley 13%

Ninemile 29%

Onondaga Lake Monitoring Program Onondaga Lake Sampling Summary (July - September 2015) July 2015:  Lake Weekly sampling events: July 8, 9, 16, 20  Lake Biweekly sampling events: July 14 and 28  Completed second larval seine event on July 6.


August 2015:  Lake Weekly sampling events: August 3, 13, 17 and 27  Lake Biweekly sampling event: August 12 and 25  Completed first juvenile seine event on August 8 and 10. September 2015:  Lake Weekly sampling events: September 3, 14 and 28  Lake Biweekly sampling event: September 22  Lake Quarterly sampling event: September 9  Completed second juvenile seine event on September 14 and 16.  Completed annual fall electrofishing event on September 20 -23

Onondaga Lake Water Quality Phosphorus New York State has promulgated a narrative standard for phosphorus in water: “None in amounts that will result in growths of algae, weeds and slimes that will impair the waters for their best usages” (NYSCRR §703.2). For ponded waters the narrative standard is interpreted using a guidance value of 20μg/L calculated as the average total phosphorus concentration in the lake’s upper waters between June 1 and September 30. The phosphorus total maximum daily load (TMDL) target is a numeric endpoint that ensures protection of the designated best uses of a water body. The AMP tracks the summer average total phosphorus (TP) concentration in the lake’s upper waters. The ultimate measure of the success of the Onondaga Lake Phosphorus TMDL is the extent to which the in-lake total phosphorus criteria and beneficial uses are achieved.


Chlorophyll-a The summer average chlorophyll-a (Chl-a) concentration in the upper waters of the lake was 8.5 µg/L in 2014, somewhat lower than the 2013 average of 9.1 µg/L. The average and peak concentrations of this measure of algal biomass have declined substantially since the phosphorus treatment upgrade at Metro in 2005. According to the criteria adopted by the AMP (15 µg/L and 30 µg/L for minor and major blooms, respectively), and based on weekly laboratory measurements, one minor algal bloom was identified in 2015 (to-date) in Onondaga Lake during the summer recreational period (defined as JuneSeptember). The infrequent occurrence of algal blooms in Onondaga Lake stands in contrast to the widespread occurrence of blue-green harmful algal blooms in lakes across New York State (see http://www.dec.ny.gov/chemical/77118.html for more information). Most algae are harmless and are an important part of the food web. Certain types can become abundant and form blooms under the right conditions. Some algae can produce toxins that can be harmful to people and animals (referred to collectively as harmful algal blooms (HABs)).

Onondaga Lake Biology Changes in the fish communities of Onondaga Lake In Onondaga Lake, adult species richness (i.e., number of species) collected during adult sampling events has gradually increased since 2000 largely as a result of in improved wastewater treatment technology. A total of 26 adult species were captured during the adult survey in 2014, the highest reported value since 2000 with the exception of 2013 at which time 26 species also were captured. Minor fluctuations in species richness over the past six years is primarily due to the incidental catches of uncommon species such as Black Bullhead, White Bass, Quillback, and the introduction of invasive species such as Round Goby. Onondaga Lake is part of the Seneca River system, which provides a corridor for fish movement between the lake and the waterways connected to the Seneca River as evident based on tag


returns since 2000. Since the monitoring program started in 2000, 53 species have been identified in the lake by Onondaga County.

White Bass captured from Onondaga Lake.

Overall trends in catch rates have varied by species since 2000 (Figure 1). Several species including Smallmouth Bass, White Perch, and Channel Catfish have had reduced catch rates over the past several years, while other species such as White Sucker and Walleye had less variation in catch rates. However, catch rates of several species including Largemouth Bass, Brown Bullhead, and Yellow Perch have generally increased since 2000 with consistently higher Catch per unit effort (CPUE) since 2007 (Figure 1). These patterns likely reflect the changing habitats in the lake including increased macrophyte coverage, increased mussel abundance, and changes in the fish community associated with Alewife. Species such as Gizzard Shad, are susceptible to winter induced mortality and commonly show variations in yearly catch rates at the periphery of their geographic range, most notably during long, harsh winters. It is likely that the reasons for changes in abundance are more complex and species-specific and reflect changes in overall lake productivity as well as increased littoral zone habitat diversity.


Figure 1 - Trends in catch per unit effort (CPUE) of select fish species captured during adult surveys, 2000–2014.

Onondaga Lake Progress Report - 2014 Update A copy of the Onondaga Lake Progress report, dated August 2015, is included in this quarterly report to summarize the substantial improvements in the lake’s water quality, its biological community and the new recreational opportunities that emerged in and around Onondaga Lake in response to water quality improvements.



LEGISLATIVE /REGULATORY / MEDIA UPDATE



Legislative/Regulatory Update Action Items for the County Legislature (July – September) 

Calling a Public Hearing for the Purpose of Implementing a Program of Infrastructure Improvements to Mitigate Inflow & Infiltration in Locations Outside of the Amended Consent Judgment Area at an Estimated Cost of $1,980,000.

Approving Various Infrastructure Improvement Projects to Benefit the Onondaga County Sanitary District ($1,980,000).

Bond Resolution – Authorizing the Issuance of $1,980,000 Serial Bonds of the County of Onondaga to Pay the Cost of Various Infrastructure Improvement Projects to Benefit the Onondaga County Sanitary District.

Authorizing the Extension of an Agreement with the City of Syracuse to Share in the Costs of Funding an Arborist Employed by the City of Syracuse.

Action Items for the Environmental Protection Committee (September - October) 

Calling a Public Hearing in Connection with Proposed Improvements to the Oneida Lake Pump Stations to Benefit the Onondaga County Sanitary District.


Eighty Syracuse-area middle school students have spent the past week gathering water and soil samples, catching insects, observing fish, and studying mud boils in Tully to learn more about the Onondaga Lake watershed. It’s the tenth year of Honeywell's Summer Science Week, which is organized by the Museum of Science and Technology. Solvay 8th grader Sidney Chafee wants to go into marine biology or a related field. She enjoyed learning about the restoration of the lake’s wetlands after decades of pollution. "Now we're planting things so we grow more wildlife. More birds and fish are coming. There's a lot more of an ecosystem. Mother nature is taking over, and it's just going to be a lot more pleasant to come, people will want to swim here, and it'll smell a lot better, because I live right down the road...it's terrible." Chafee isn’t deterred by the extra work it might take to pursue a career in marine science. Shakeem Ellick is about to enter Corcoran High School’s International Baccalaureate program, and science has always been on his career radar.


"Science has always been one of my favorite subjects. And this helps. I always figured I should be a lawyer, doctor, or scientist. Since I'm doing this, I want to be a scientist even more. I try and do anything extra to help me." Science week organizer and MoST Exhibits Project Manager Peter Plumley couldn’t agree more. He says the intense week of fields study, interactive experiments and data collection gives the students an experience and advantage that so few will ever have. "When they get done with this and go in the 9th grade, they know they can do science. They sit in the classroom and hear the teacher talk about stuff, and say, geez, I've done that. I bet this teacher hasn't done it! She's just reading it! That gives them a real sense of accomplishment and ownership."

Plumley says he’s tracked down some of the 8th graders from 2006 who graduated from college last year. He was gratified to learn a large number of them attended good schools and studied the stem subjects. One of those students appears to be on a similar path. Rebecca Rolnick will be a SUNY ESF freshman this fall majoring in conservation biology. She volunteered this week as a counselor for the 8th graders. But she has the unique perspective of participating in science week a few years ago as a middle schooler herself…


"When I went to the camp, they were talking about how they were just going to start the dredging of the lake. And now that's finished. Now they're working on more of the restoration. A lot of the plants and animals have started to come back, and the community has been really involved in it over the past few years. That's really great to see." Rolnick says she already had the science bug at a young age, and science week just confirmed her interest. The program culminates Wednesday with a discussion of the data they collected, a talk from a former NASA astronaut, and an awards ceremony.


Bassmaster official: Onondaga Lake's bass fishing is superb

I've said it a couple of times since taking the outdoors writers job, and I think it deserves to be said again. Onondaga Lake is an awesome place to fish -- particularly for bass.

http://www.syracuse.com/outdoors/index.ssf/2015/08/bassmaster_tournament_director_onondaga_lakes_bass_fishing_is_superb.html


I know there's a lot of critics out there who might disagree. Those who continue to see the lake as a polluted cesspool, with many fish in there having three eyes or something. They should talk to Chris Bowes. Bowes, 47 a Westhill High grad and tournament director for this past weekend's Bass Pro Shops Bassmaster Northern Open on Oneida Lake, fished Onondaga last Monday evening before the competition began. Bowes now lives in Central Florida. As a teen growing up in the Syracuse area, Bowes said he was a member of a local canoe and kayak team, fell in the lake many times and "on occasion just jumped in the water on a hot day and swam." "I still only have two eyes, my kids are fine," he said. "I keep track of the local news here. I continue to read on syracuse.com all the negativity about the lake. It's just such a resource. Should we be drinking the water on a daily basis? Well, no. But that doesn't mean it can't be used for recreational purposes by the community." Bowes said he went out on the lake in a boat with local angler Mike Wall, a member of the Salt City Bassmasters. "We put in about 3 p.m. and the wind was blowing pretty good," he said. "We scooted over to the west shore. In fact, I could have thrown a stone and hit the new amphitheater over there. We fished right there until about 8:30. "We managed to put 59 fish in the boat, including a few over four pounds," he said. "They were all largemouths and the bite was just steady as you can be." What was he using? "I can't tell you that. I'm a fisherman," he said. But after additional questioning, he admitted, "OK, I was using a soft stickbait over there and we rigged it wacky style. I guess that will tell you a http://www.syracuse.com/outdoors/index.ssf/2015/08/bassmaster_tournament_director_onondaga_lakes_bass_fishing_is_superb.html


lot." Bowes said all the fish they landed looked "incredibly healthy." "I'm fortunate enough with my job with Bassmasters to travel all around the country and see fish from California to Florida, the upper mid-West, the Northeast ... including this past week on Oneida Lake," he said. When he compares the overall length/weight ratio of those fish, Bowes said he would put Onondaga's bass against any of them. "Those fish in Onondaga are stout," he said. Why are the fish so healthy? "The habitat. As you know, you essentially have a bowl with a ring of weeds around it, which is a great habitat for big fish. It's got a lot of white bass, gizzard shad (and other things) that they feed on. You don't have a lot of pressure, very few, tournaments." In addition, very few people keep what they catch. What's usually caught on Onondaga Lake is returned to Onondaga Lake. That Monday evening Bowes said he only saw two other boats on the lake. "On one of them was Elite Series pro Brent Chapman and he was filming a TV show out there. I believe it's called "Pro vs. Joe," and it involves him fishing against a local angler," he said.

http://www.syracuse.com/outdoors/index.ssf/2015/08/bassmaster_tournament_director_onondaga_lakes_bass_fishing_is_superb.html


NY approves $20M in loans to improve Syracuse sewage treatment plant

SYRACUSE, N.Y. -- A state agency has approved $20.5 million in loans to Onondaga County to pay for improvements to the Metropolitan Syracuse Wastewater Treatment Plant. Half of the loans will be no-interest loans, according to the New York state Environmental Facilities Corp., the lender. The other half will be at market rate. The Metropolitan Syracuse Wastewater Treatment Plant treats a daily average of 84 million gallons of wastewater generated by 270,000 people and industrial and commercial customers in Syracuse and its suburbs. Treated wastewater is discharged from the plant into Onondaga Lake. The funding will be used to help the county-owned plant meet new permit requirements by installing a seasonal disinfection system. The system will reduce fecal bacteria and chlorine levels in discharged water, according to information provided by the Environmental Facilities Corp. The funding will pay for construction of a new bypass chlorine contact tank, chemical storage and feed building, dewatering pump station, tertiary bypass control gates, and other upgrades. Construction will begin in September and be completed by March 2017. Contact Mike McAndrew anytime | email | Twitter | 315-470-3016

http://www.syracuse.com/news/index.ssf/2015/08/ny_approves_20m_in_loans_to_improve_syracuse_sewage_treatment_plant.html


Future projects help NY counties prepare for extreme weather By Ali Stewart Published: August 13, 2015, 1:46 pm

RENSSELAER, N.Y. (NEWS10) – Governor Cuomo has announced that NYS is getting more than $114 million in zero and low-interest loans to help municipalities strengthen their water infrastructures. Cuomo says these loans will support improvements at 16 wastewater facilities and four drinking water systems. Six of these projects will also make facilities and systems more resilient in the face of extreme weather.

http://news10.com/2015/08/13/future-projects-help-ny-counties-prepare-for-extreme-weather/


The Environmental Facilities Corporation has approved $31.9 million ($1.2 million grants, $30.7 million loans) for six storm-related projects: 

Town of Wallkill (Orange County) – Approximately $3 million, including a $716,238 grant and a $2.17 million interest-free loan, to install a remote control, monitoring and alarm system for the drinking water supply;

The Town of Orangetown (Rockland County) – $2 million, including a $500,000 grant, to repair and reinforce the wastewater collection system serving Nyack, South Nyack and Upper Nyack;

Town of Tonawanda (Erie County) – $14.2 million (half interest-free) for the fourth phase of the Parker-Fries Interceptor, a far-reaching project to abate numerous sanitary sewer overflows;

Village of Phoenix (Oswego County) – Approximately $6.4 million in interest-free financing to repair and replace sanitary sewers and installation of storm drains throughout the village, along with improvements to the wastewater treatment plant and pump station;

Hoosick Falls (Rensselaer County) – Approximately $3.8 million to prevent stormwater and groundwater infiltration by replacing or reinforcing pipes in the sewer collection system, along with a new pump station to protect water quality in the Hoosic River. This project was designed with the help of a $24,500 planning grant from Governor Cuomo’s Regional Economic Development Initiative;

Town of Orleans (Jefferson County) – $2.5 million to reduce groundwater infiltration and stormwater inflow into the Thousand Island Park wastewater collection system. Century-old claytile pipes will be replaced with new sewer mains and laterals, as well as 55 new manholes.

Acting DEC Commissioner Marc Gerstman said, “Communities in parts of New York State are still feeling the effects of the devastation caused by Superstorm Sandy and other weather related events. This action by EFC is another critical step forward in achieving Governor Cuomo’s promise to better prepare NY for these events by building smarter more resilient infrastructure.” EFC also approved local-government assistance funding for: 

$35.4 million in zero-interest and low-interest loans for five wastewater projects in Westchester County.

http://news10.com/2015/08/13/future-projects-help-ny-counties-prepare-for-extreme-weather/


$20.5 million (half interest-free) to improve the Metropolitan Syracuse Wastewater Treatment Plant. Previous wastewater upgrades by Onondaga County have improved water quality in Onondaga Lake;

$1.26 million of interest-free financing for a waterfront revitalization project in the Village of Penn Yan (Yates County). New sewers, pump stations and other improvements to the wastewater collection system along Hicks, Waddell and Monell streets will prepare the waterfront for commercial and residential development of the former Penn Yan Boat Factory;

$2 million grant and a $684,665 interest-free loan for the Town of Newcomb (Essex County) to improve the quality of its drinking water by installing new groundwater sources and upgrading the distribution system in the Winebrook Hills Water District; and,

$6.5 million zero-interest loan to the Village of Trumansburg (Tompkins County) to help correct discharge violations at the wastewater treatment plant on Lake Road. Designed with the help of a $19,840 state planning grant, the project will also save money by lowering the plant’s energy costs.

Additionally, four 30-year, interest-free loans, totaling $15.8 million, were approved today for infrastructure improvements completed in the Village of Saranac Lake (Franklin County); the City of Amsterdam (Montgomery County), the Village of Oxford (Chenango County) and the Town of Malone (Franklin County).

http://news10.com/2015/08/13/future-projects-help-ny-counties-prepare-for-extreme-weather/


http://www.syracusenewtimes.com/calendar/event/save-the-rain-clean-water-fair/


http://www.syracusenewtimes.com/calendar/event/save-the-rain-clean-water-fair/


SAVE THE RAIN CLEAN WATER FAIR

TAKE FACILITY AND GREEN INFRASTRUCTURE SITE TOURS

RAIN BARREL WORKSHOPS

EDUCATIONAL EXHIBITS

ENTERTAINMENT AND ACTIVITIES FOR KIDS

FREE FOOD

learn, explore, discover!

SEPT. 12, 2015 9AM - 2PM

ONONDAGA COUNTY TO LEARN MORE, VISIT: HTTP://SAVETHERAIN.US/2015-FAIR/

Joanne M. Mahoney County Executive


Onondaga Lake algae mats a sign of the season, not pollution: researchers

Syracuse, N.Y. -- Those stringy, stinky mats of algae drifting in Onondaga Lake are the signs of the season, not pollution. What's floating now is a type of algae that grows on plants that root in the bottom of the lake, said Dave Matthews, a scientist with the Upstate Freshwater Institute. Those rooted plants start to die as days get shorter and there is less sunlight.

http://www.syracuse.com/news/index.ssf/2015/09/onondaga_lake_algae_mats_a_sign_of_the_season_not_pollution_researcher.html


"As they die back, that filamentous stuff is free to float around and wash up on shore," he said. "'Tis the season." This kind of algae shouldn't be confused with harmful algal blooms, which are comprised of potentially toxic blue-green algae, Matthews said. "When people talk about algae blooms or harmful algae blooms, that'a s different kind of algae," he said. One researcher said the algae in Onondaga Lake now is actually a sign that the lake, once one of the nation's most polluted, is recovering. "It's a weird sign of recovery," Kim Schulz, a professor of at SUNY College of Environmental Science and Forestry, told Syracuse.com in May. The lake used to have massive blooms of microscopic algae because it was so polluted, but improvements to the county's wastewater treatment system, and the presence of zebra mussels, have made the lake much clearer, she said. That promotes the growth of filamentous algae, she said. Contact Glenn Coin: Email | Twitter | Google + | (315) 470-3251

http://www.syracuse.com/news/index.ssf/2015/09/onondaga_lake_algae_mats_a_sign_of_the_season_not_pollution_researcher.html


Salina — In 2012, the legislature approved an agreement with towns, villages, and Cayuga County to plow approximately 316 miles of Onondaga County’s roads. For many years, Onondaga County has had an agreement with the state of New York to plow state roads in exchange for a base rate per mile. In an effort to streamline this service at the local level, the county reached out to the local municipalities to request they perform a similar service on county highways. After some negotiation, 19 towns, two villages and Cayuga County have agreed to a five year agreement to provide snow plowing services. The five-year contract has a base rate of $6,335 per mile with a 3 percent increase annually. By 2017, the base rate will be $7,130 per mile. Included in this contract is a “severity factor.” Each year, New York state determines a percentage based on the severity of the winter and amount of snow plowing that was performed by each municipality. The first three years of this agreement have proven to be cost-effective for the county and the towns. This year, the town of Geddes will receive a total payment of $16,195 for plowing almost two miles of county roads, and the town of Salina will receive a total payment of $69,105 for the 7.5 miles of county roadways they plowed this past winter. This contract ensures roadways are plowed quickly by utilizing town plow trucks that are already in the area. I sincerely hope we can continue this arrangement beyond 2017. The “Save the Rain” program has been very successful in reaching our court-mandated stormwater capture goals. Three years ago, we expanded Save the Rain by creating a Suburban Green Infrastructure Program. At that time we allocated $2 million and received requests for more than $4 million in proposals from towns and villages. In 2013 the county used revenues from the Honeywell dredging to complete the remainder of projects. All things considered, it is clear this funding stream has been beneficial to municipalities faced with drainage and sewer problems.

http://www.eaglenewsonline.com/news/2015/sep/08/legislature-municipalities-work-together-save-mone/


Acting DEC commish gets earful about what's right with Onondaga Lake

http://www.syracuse.com/outdoors/index.ssf/2015/09/acting_dec_commish_gets_earful_about_whats_right_with_onondaga_lake.html


Marc Gerstman, acting commissioner of the state Department of Environmental Conservation, got a two-hour, mostly rain-filled tour of Onondaga Lake today. The tour, part of Gov. Andrew Cuomo's, day-long "Capital for a Day" series of events across the greater Syracuse area, was aboard the Emita II, a 65-foot boat owned by Mid-Lakes Navigation. The boat took off from Mid-Lake's launch on the Seneca River at Dutchman's Landing shortly after 11 a.m. with more three dozen, state, county, town officials aboard, in addition to representatives from such groups as the Montezuma Audubon Center, the Onondaga County Federation of Sportsmen's Clubs, SUNY ESF, the Nine Mile Creek Conservation Council and the local chapter of the Izaak Walton League. Much of the tour and the discussion concerning recent developments on the lake took place in the boat's lower, inside deck. One official after another gave brief statements to Gerstman about the positive developments on the lake concerning such things as its water clarity, the thriving fishery, the amphitheater, the Honeywell visitor's center and the remedies taken to turn the habitat on the south shoreline from a toxins-filled stretch to a healthy situation for plants and wildlife. Chris Lajewski, director of the Montezuma Audubon Center, noted Onondaga Lake has the largest concentration of bald eagles of any urban area in the country. Ken Lynch, the DEC's regional director, brought out an artist rendition of a new, state-run boat launch on Onondaga. It will be at the site where Honeywell currently has its field office, trailers and visitor's center. Work on it will commence after Honeywell finishes its capping work on the lake's bottom. Plans call for a two-bay boat launch for trailered boats and a separate launch site for car-top craft (canoes, kayaks) at the location. There will be 60 parking spaces and a handicapped fishing ramp stretching into the lake, DEC officials have said. "It's should be up and running by 2017," Lynch said.

http://www.syracuse.com/outdoors/index.ssf/2015/09/acting_dec_commish_gets_earful_about_whats_right_with_onondaga_lake.html


Gerstman told the group it's come to the point where attention to Onondaga Lake is now "less about cleanup and more about we can do for the future of Onondaga Lake" – specifically drawing visitors and users of its numerous resources. The rain stopped for about last 30 minutes of the tour. Everyone went up on the boat's upper deck to continue talking and to take in the lake's scenery. County lawmaker Mike Plochocki, chairman of the county Legislature's environmental Protection Committee, said "while we still have a long way to go with the lake, the fact is we've made huge strides. Today, on this boat ride and with our talk with the DEC commissioner, those strides came out."

http://www.syracuse.com/outdoors/index.ssf/2015/09/acting_dec_commish_gets_earful_about_whats_right_with_onondaga_lake.html


FINANCIAL UPDATE



Financial Update Contracts New Contracts      

Stormwater Management Program Contract with Onondaga Soil & Water to assist with stormwater management and permit compliance. Contract Amount: $77,500. Executed: 7/29/15. EBSS Investigation for Water Quality Enhancement Facility Plan Contract with O’Brien & Gere for development of a facility plan to evaluate options to enhance water quality at the Erie Boulevard Storage System. Contract Amount: $135,380. Executed: 9/3/15.

Amendments to Existing Contracts      

ACJ Project Management Contract with CDM/C&S Engineers amended for ongoing project management and administration. Amendment Amount: $445,600. Executed: 9/3/15. Environmental Outreach & Education Contract with Onondaga Environmental Institute amended to include participation in the Mudboil Working Group as part of the Onondaga Lake Partnership. Amendment Amount: $171,239.43. Executed: 7/7/15.

Change Orders  

   

Harbor Brook CSO 018 Wetlands Pilot Contract with Joseph J. Lane Construction amended to include negotiated costs of various modifications relating to contaminated soils and groundwater management and other miscellaneous modifications. Amendment Amount: $200,000. Executed: 7/9/15. Lower Harbor Brook Conveyances Contract with Joseph J. Lane Construction amended to include negotiated costs of outstanding claims. Amendment Amount: $450,000. Executed: 7/9/15.

1


Funding Grants State Bond Act Funds  Reimbursements requested: None  Reimbursements received: None Federal EPA Funds  Reimbursements requested: None  Reimbursements received: None Federal Army Corps of Engineers Funds  Reimbursements requested: None  Reimbursements received: None 

GIGP Grants Requested: None Received: None

EFC Reimbursements Received: LT Clinton for $198,336.73 on 7/27/15 LT HB for $4,277,523.40 on 7/27/15 LT HB for $1,334,368.20 on 9/18/15 LT Clinton for $119,859.88 on 9/18/15 EFC Reimbursements Requested: LT HB for $1,574,891.33 on 7/8/15 LT Clinton for $197,433.40 on 7/8/15 LT HB for $1,334,368.20 on 8/21/15 LT Clinton for $119,859.88 on 8/21/15 GIGP Grant Requested: E. Washington St. for $4,021.45 GIGP Grant Received: E. Washington St. for $4,021.45 on 7/30/15 E. Washington St. (retainage) for $36,672.75 on 9/3/15 Total reimbursement monies received to date through EFC loans for the funded ACJ projects: $247,603,598 (short term) and $110,451,054 (long term).


Onondaga County Lake Improvement Project 4th Stipulation of the ACJ Clinton/Lower MIS CSO Improvements Summary of Current and County Authorizations

Total Project Costs Expended To Total Proposed Budget 9/30/15

Project /Task/Line Item

Authorization Remaining

Clinton Street CSO Facility Planning (Original) Engineering Services (EEA)

$

751,266 $

751,266

$

(0)

Original Facility Plan Subtotal $

751,266 $

751,266

$

(0)

Clinton Street CSO Conveyances Project Contract No. 1 - Phase 1 Conveyances (Delaney)

$

14,478,053 $

14,478,053

$

(0)

Contract No. 2 - Phase 2A Conveyances (Delaney)

$

4,074,455 $

4,074,455

$

(0)

Engineering/Construction Services (CDM/C&S) $ Conveyances Subtotal $

2,738,000 $ 21,290,508 $

2,738,000 21,290,508

$ $

0 (0)

Clinton Storage Project

(1)

Construction Estimate

$

77,742,858 $

77,508,755

$

234,103

Engineering Services (EEA and others)

$

12,122,013 $

11,836,620

$

285,393

Construction Management and Administration (CDM/C&S)

$

4,833,411 $

4,463,332

$

370,079

Construction Testing (CME)

$

327,847 $

277,716

$

50,131

94,086,422

$ $

939,707

$

3,100,000

CSO Storage Subtotal $

95,026,129 $

Facility Plan for CSOs 027 & 029 Construction Estimate

$

3,100,000

Engineering Services (Ch2MHill)

$

91,211

$

91,186

$

25

Engineering Services (TBD) Floatables Arcadis

$

782,032 $

12,816

$

769,216

County Administration and Other Costs

$

-

Facility Plan Subtotal $

$

-

3,973,243 $

104,001

$

3,869,242

38,508,611 $ 15,900,000 $ 54,408,611 $

28,412,036 11,214,434 39,626,470

$ $ $

10,096,575 4,685,566 14,782,141

Clinton/Lower MIS Green Implementation Program Construction Contracts incl. GIF Public/Private Ch2MHill Program Management & Engineering

$ $ Green Subtotal $

Program Management Project Management (CDM/C&S) Project Management for Facility Plan (CDM/C&S) (2) $ Program Management Subtotal $ Miscellaneous County Costs Land Acquisition IMA Legal Consulting (John Clare & Mezey) Debt Other Contingency

-

$

-

$ $ $ $ $ $ $ Miscellaneous Subtotal $

3,726,350 4,861,000 126,115 301,334 234,885 310,738 489,863 10,050,285

$ $ $ $ $ $

3,726,350 3,959,746 350,857 226,334 803,593 739,681

$

$

185,500,042

$

Authorized Budget 185,500,042

Notes: (1) Includes engineering costs from original Clinton RTF Project (2) CDM/C&S Project Management costs are included in the total facility plan costs

$ $ $

-

9,806,560

$ $ $ $ $ $ $ $

901,254 (224,742) 75,000 (568,708) (428,943) 489,863 243,725

165,665,228

$

19,834,814


Onondaga County Lake Improvement Project 4th Stipulation of the ACJ Harbor Brook Drainage Basin CSO Abatement Summary of Current and Proposed Costs, and County Authorizations Total Project Costs Total Proposed Budget

Project /Task/Line Item

Expended to 9/30/15

Authorization Remaining

Harbor Brook CSO Abatement Project Original Engineering Expenses

$

5,500,000

$

5,500,000

$

HBIS Replacement and CSO Abatement Project Construction Contract No. 1 (1) (JJ Lane) Other Miscellaneous Work Engineering/Construction Sevices (CDM/C&S) County Administration and Other Costs

$ $ $ $

18,289,918 2,482,920 2,012,615 114,547

$ $ $ $

23,391,425 2,549,687 951,445

$ $ $ $

(5,101,507) 2,482,920 (537,072) (836,898)

HBIS Replacement and CSO Abatement Project Total $

22,900,000

$

26,892,557

$

(3,992,557)

$ $ $ $ $

34,502,000 4,200,000 3,390,000 2,280,000 44,372,000

$ $ $ $ $

28,522,537 3,960,868 1,497,536 5,360,579 39,341,519

$ $ $ $ $

5,979,463 239,132 1,892,464 (3,080,579) 5,030,481

$ $ $ $ FCF Program Total $

12,000,000 1,878,731 800,000 400,000 15,078,731

$ $

144,843 15,300

$

160,143

$ $ $ $ $

12,000,000 1,733,888 784,700 400,000 14,918,588

Other Harbor Brook Green Construction Contracts incl. GIF Public/Private & Rain Barrels $ Ch2MHill Engineering & Program Management $ Harbor Brook Green Project Total $

9,300,000 3,650,000 12,950,000

$ $ $

16,294,560 5,409,271 21,703,831

$ $ $

(6,994,560) (1,759,271) (8,753,831)

Program Management Project Management (CDM/C&S) $ Project Management for FCF Plan Implem (CDM/C&S) $ Program Management Total $

499,269 499,269

$

2,756,869

$

(2,257,600)

$

2,756,869

$

(2,257,600)

Lower Harbor Brook Storage & Conveyance Construction Estimate (with contingency) Engineering Services (EEA) Engineering Services (CDM/C&S) Project Escalation to Midpoint of Construction Lower Harbor Brook Storage & Conv Total Harbor Brook CSOs FCF Program Construction Estimate Engineering Services (Arcadis) County Administration and Other Costs Project Escalation to Midpoint of Construction

-

Harbor Brook Mitigation

$

3,500,000

$

3,265,000

$

235,000

Total Costs for Harbor Brook CSO Area under 4th Stip

$

104,800,000

$

99,619,920

$

5,180,080


Onondaga County Lake Improvement Project 4th Stipulation of the ACJ Midland CSO Abatement Summary of Current and Proposed Costs, and County Authorizations

Total Project Costs Total Proposed Budget

Project /Task/Line Item Midland Ave. RTF & Conveyances Midland Phase 1 Conveyances - Construction Midland Phase 2 RTF & Conveyances - Construction Midland Demolition Contracts - Construction Other Construction Phase 1 and 2 Engineering (Parsons & EEA) CME Construction Testing RTF Modifications (Construction, Eng, CM, Admin) Facility Plan Total

Expended to 9/30/15

$ $ $ $ $ $ $ $

1,836,434 53,372,689 748,483 137,000 14,717,163 227,341 3,000,000 74,039,110

$ $ $ $ $ $

1,836,434 53,372,689 748,483 136,342 12,503,353 218,486

$

68,815,787

$ $ $

12,296,549 64,800 750,000

$ $ $

12,098,662 729,224

$

13,111,349

$

12,827,887

FCF Facility Plan Construction Estimate Engineering Services (Arcadis and others) Construction Management and Administration Project Escalation to Midpoint of Construction Clinton Storage Project Total

$ $ $ $ $

5,000,000 623,954 210,000 5,833,954

$ $

Facility Plan for Midland CSOs Construction Estimate Engineering Services (Ch2MHill) Engineering Services, County Admin, ect (TBD) Facility Plan Total

$ $ $ $

14,900,000 121,401 3,720,000 18,741,401

CSO 044 Conveyances Project Contract No. 6. - JJ Lane Construction Contingency 5% Engineering Services (EEA) Construction Management Sevices (CDM/C&S) see below Conveyances Project Total

Midland Green Implementation Program Construction Contracts incl. GIF Public/Private $ Ch2MHill Program Management & Engineering $ Clinton Green Program Total $ Program Management Project Management (CDM/C&S) includes CSO 044 $ Project Management for Facility Plan (CDM/C&S) (1) Program Management Total $

Miscellaneous County Costs Land Acquisition IMA Legal Consulting (John Clare & Mezey) Debt Contingency Other

$ $ $ $ $ $ $ $ $

(0) (0) 0 658 2,213,810 8,855 3,000,000 5,223,323 5,223,323

$ $ $ $ $ $

197,887 64,800 20,776 283,462 283,462

46,039

$ $ $

5,000,000 577,915 210,000

$

46,039

$ $

5,787,915 5,787,915

$ $ $ $

121,368 121,368

$ $ $ $ $

14,900,000 33 3,720,000 18,620,033 18,620,033

2,457,111 $ 2,651,093 $ 5,108,204 $ $

5,042,889 1,266,543 6,309,432 6,309,432

7,500,000 $ 3,917,636 $ 11,417,636 $

6,621,274 6,621,274

$

(90,672)

6,530,602

$ $ $

$ $

(90,672) (90,672)

$

1,809,802

$

1,809,802

$

$ $ $ $ $ Miscellaneous Costs Total $

182,323 194,317 635,031 2,591,117 526,211 5,938,801

$ $ $ $ $

$181,975 194,317 689,294 529,271 3,404,659

$ $ $ $ $ $

348 0 (54,263) 2,591,117 (3,060) 2,534,142

135,612,853

$

$

38,667,634

Total Cost for Midland project under 4th stipulation

Authorized Master Budget $128,300,000

$

6,530,602

Authorization Remaining

96,945,219

-


Onondaga County Lake Improvement Project 4th Stipulation of the ACJ Sewer Separation of CSO Areas 022/038/040/045/046A/046B/047/048/050/051/053/054 Summary of Current and Proposed Costs, and County Authorizations

Total Project Costs Total Proposed Budget

Project /Task/Line Item Sewer Separation Construction Contracts CSO 024 (Falter) CSO 053/054 (Falter) CSO 038//40/046A/046B (Falter) CSO 047/048 (Falter) CSO 050 (Lane) CSO 051 (Lane) CSO 022/045 (estimated Project Costs)

Expended to 9/30/15

Authorization Remaining

Construction Total

$698,864 $2,000,817 $3,598,931 $1,654,022 $4,362,188 $5,037,280 $6,750,000 $24,102,102

$698,864 $2,000,817 $3,524,487 $1,654,022 $4,362,188 $5,037,280 $5,611,423 $22,889,082

$0 $0 $74,444 $0 $0 $0 $1,138,577 $1,213,020

Service Contracts (Engineering /Consulting /Program Management) ACE CDM/C&S CME Department of the Army Spectra Engineering/Management Total

$484,286 $1,446,468 $109,492 $153,504 $437,996 $2,631,746

$484,286 $2,008,174 $49,704 $153,504 $437,996 $3,133,663

$0 -$561,706 $59,788 $0 $0 -$501,917

Miscellaneous Costs Total

$135,084 $101,425 $116,269 $14,235 $13,540 $380,553

$135,084 $101,425 $142,816 $14,235 $4,093 $397,652

$0 $0 -$26,547 $0 $9,447 -$17,099

Total

$27,114,401

$26,420,398

$694,003

Miscellaneous County Costs City of Syracuse Consulting (John Clare & Mezey) Debt Legal Other

Authorized by Legislature $27,684,286


Onondaga County Lake Improvement Project Save The Rain Education and Outreach Grant Summary of Current and Additional Costs, and County Appropriations Sept 2015

Funding Sources

Appropriations

Program Funding 09,10,11 Appropriations 2011 Suburban Green Infrastructure 2012 Appropriation 2011 Trolley Lot Parking Mitigation Appropriation* 2012 Green grant education 2013 Green Grant education 2014 Green Grant education 2015 Green Grant education Total Appropriation

$ $ $ $ $ $ $ $

875,000 200,000 400,000 125,000 200,000 400,000 400,000 100,000

$

2,700,000

Funding Uses

Contract Amount

Retz Advertising + Design 2010/2011 Marketing Services 2012 Marketing Services Marketing Services Subtotal

411,789 224,303

$ $

411,789 224,303

$

636,092

$

636,092 $

Contract Amount

Expended to Date

$ $ $ $

346,677 241,815 237,758 350,126

$ $ $ $

$

1,176,376

$

$ $ $ $ $

2,930 8,510 1,590 12,483 21,152

Baltimore Education & Outreach $

46,665

Education & Outreach Subtotal

Difference + (-)

$ $

Environmental Finance Center Education and Outreach 2011 Education and Outreach 2012 Education and Outreach 2013 Education and Outreach 2014 Education and Outreach

Expended to Date

(0)

Difference + (-)

346,677 241,815 237,758 350,125 1,176,376 $

0

$

$ 6,585 $ $ $ 2,050 $

2,930 1,925 1,590 12,483 19,102

$

8,635 $

38,030

Baltimore Woods Supplies Transport Travel Env Educator Hours Administrative Hours

Contract Amount

Miscelaneous Ed/Outreach Expenses 2010/2011 Miscellaneous Exp. 2012 Miscellaneous Exp. 2013 Miscellaneous Exp 2014 Miscellaneous Exp 2015 Miscellaneous Exp

$ $ $ $ $

105,764 79,852 34,158 46,657 307,600

Travel Purchase card/Petty cash Page Seed Co Just the right stuff Catering at the Zoo Joel Shaw Syr blue print

OEI - RB Workshops Pinckney Hugo Grp Environmental Design and Research 2010/2011 media 2012 Media

Miscellaneous Subtotal

STR Education and Outreach Totals

Expended to Date $ $ $ $

105,764 79,852 34,158 46,657

$ $ $ $ $ $ $

494 300 2,334 3,351 1,748 384 420

Difference + (-)

$ $ $ $ $ $

16,585.00 200,000.00 20,000.00 28,750.00 1,500 -

$

8,601

$ $ $ $

20,000 28,750 1,500 -

$

$

840,866

$

334,313

$

Contract Amount $

Remaining Balance

$

2,700,000

Expended to Date $

2,155,416

506,553

Difference + (-) $

544,584

$

544,584

*Trolley lot parking mitigation money is from the Clinton CSO Storage Facility Budget and is funding education and outreach specific to that project.



APPENDIX



September 2015 FINANCIAL TRACKING SUMMARY: FEDERAL & STATE GRANTS/LOANS APPROVED & RECEIVED

PROJECT NAME METRO - CURRENT AERATION SYSTEM UPGRADE AMMONIA REMOVAL DEMO BIOSOLIDS-MECHANICAL THICKENERS(c ) DIGESTER MOD/CHEMICAL STORAGE DIGITAL SYSTEM IMPROVEMENTS MISCELLANEOUS IMPROVEMENTS ODOR CONTROL AMMONIA REMOVAL FULL SCALE/ STAGE II PHOSPHORUS REMOVAL PHOSPHORUS REMOVAL PILOT CSO - CURRENT CLINTON ST CONVEYANCE & RTF ERIE BLVD SEW SEP STORAGE FRANKLIN ST FCF HARBOR BROOK FCF HARBOR BROOK CSO ABATEMENT (a) HIAWATHA INTERCEPTOR/RTF KIRKPATRICK ST PUMP STATION MALTBIE ST FCF MIDLAND AVE CONVEYANCE MIDLAND AVE PHASE II & RTF MIDLAND AVE PHASE III MIDLAND AVE MITIGATION COSTS (b) NEWELL ST FCF ONONDAGA CREEK FCF SEWER SEPARATION(a) SIPHON REHABILITATION TEALL BROOK FCF WEST ST SEWER SEPARATION OTHER AMBIENT WATER MONITORING OXYGENATION DEMO SEQR REGULATORY TOTAL DOLLARS

PROJECT BUDGET

NYS GRANT APPROVED

NYS GRANT RECEIVED

FED EPA GRANT APPROVED

FED EPA GRANT RECEIVED

SHORT-TERM SHORT-TERM LONG-TERM LONG-TERM ACE EFC LOAN EFC LOAN EFC LOAN EFC LOAN GRANT APPROVED RECEIVED APPROVED RECEIVED APPROVED

$8,500,000 $2,000,000

$5,834,381 $1,145,109

$5,834,381 $1,145,109

$7,365,000 Full-Scale

$6,868,954 $202,078

$5,600,000 $2,900,000 $1,400,000 $7,700,000

$4,319,819 $1,563,317

$4,319,819 $1,563,317

$4,938,419 $1,849,000

$4,938,419 $1,849,000

$190,000,000 $5,000,000

$47,331,203

$47,331,203

$31,245,000 $3,000,000 $3,200,000 $250,000 $5,444,000 $8,000,000 $5,642,000 $250,000 $3,000,000 $45,000,000 $27,000,000

$54,870,000 $1,700,000 $3,828,053 $384,200 $3,880,000

$54,870,000 $1,700,000 $3,828,053 $384,200 $3,880,000

$7,502,302 $211,097 $26,055,238

$7,502,302 $211,097 $26,055,238

$1,310,000 $3,000,000 $7,704,000 $1,230,000 $175,000 $1,000,000

$367,737 $442,154

$367,737 $442,154

$870,768 $1,045,162 $2,299,460

$870,768 $1,045,162 $2,299,460

$54,705,015

$14,003,569

$34,900,616

$54,705,015

$15,378,304

$1,049,185

$14,613

$14,676,422 $775,509 $285,682

$14,711,148 $154,126 $3,833

$7,413,199

$7,389,197

ACE GRANT RECEIVED

$108,000,000 Full Scale

$105,860,930 $1,936,991

$17,200,000

$989,323

$70,288,890 $2,301,876 $4,726,762

$41,834,264 $2,094,314 $4,589,759

$53,689,500

$46,700,136

$12,000,000 $212,000

$10,940,632 $188,106

$78,568,119 $923,162 $1,179,012 $343,500 $62,477,416 $2,710,169 $4,246,376

$33,558,650 $216,543 $296,823 $348,596 $22,638,299 $37,749 $828,115

$15,000,000 $10,000,000

$15,000,000

$37,339,317

$19,063,069

$1,024,433 $1,094,139 $2,481,443

$11,332,407 $140,623 $188,809 $395,540

$10,276,648 $1,958 $5,743 $6,621

$14,050,177 $14,050,177

$1,435,500 $1,236,594 $3,059,716

$247,603,598 $241,244,447 $110,541,054

$17,456,177 $17,456,177

$3,406,000

$3,406,000

$33,525,880

$8,000,000 $2,400,000 $50,000 *$380,000,000

$163,650,000 $163,650,000 $103,609,200 $103,609,200

*Original budget figures were based on 1997 dollars NYS includes awards beyond original pledge (i.e. civic strip) (a) NOTE: PROJECT IS US ARMY CORPS OF ENGINEERS PROJECT (b) NOTE: PROJECT RECEIVED $40,500 COST SHARE GRANT FROM (NYSERDA) (c )NOTE: PROJECT RECEIVED $87,500 COST SHARE GRANT FROM (NYSERDA)

$296,103,257


Lake Improvement Project Status Report For The Period Ending 09/30/2015

ACJ START DATE

Project Title

ACJ FINISH DATE

COUNTY FINISH DATE

ORIGINAL BUDGET(2)

AUTHORIZED BUDGET

ENGINEER

METRO - Current 1 AERATION SYSTEM UPGRADE 2 AMMON. REMOVAL DEMONSTRATION

11/1/1998

7/1/2002

01/03/00 $

8,500,000 $

3/1/2000

12/31/99 $

2,000,000 $

3 BIOSOLIDS - MECHANICAL THICKENERS

$

6,925,115 EEA 1,350,000 EEA 14,815,674

4 DIGESTER MOD/CHEMICAL STORAGE

7/1/2002

10/31/00 $

5,600,000 $

5,092,545 C&S

5 DIGITAL SYSTEMS IMPROVEMENTS

7/1/2002

06/31/01 $

2,900,000 $

3,520,317 Systems Integrated

6 MISCEL. IMPROVEMENTS

7/1/2002

01/31/99 $

1,400,000 $

1,400,000

7,700,000 $

8,393,855 OBG

7 ODOR CONTROL

7/1/2002

12/20/00 $

AMMONIA REMOVAL FULL SCALE/

10/1/2001

11/1/2003

11/01/03 $

125,000,000

STAGE II PHOSPHORUS REMOVAL

10/1/2003

4/1/2005

$

65,000,000

4/1/2006

4/1/2007

12/31/00 $

CLINTON ST. CONVEYANCE/

5/1/2003

5/1/2007

10/28/06 $

15,987,190

CLINTON ST. RTF

5/1/2007

1/1/2012

12/28/10 $

15,258,090

7/1/2002

04/13/02 $

3,000,000 $

2,684,523 Barton & Loguidice

5/1/2000

05/01/00 $

3,200,000 $

5,216,618 EEA

13 HARBOR BROOK FCF

7/1/2002

07/01/02 $

250,000 $

14 HARBOR BROOK CSO ABATEMENT

7/1/2002

$

5,443,980 $

104,800,000 Moffa & Assoc.

15 HIAWATHA INTERCEPTOR/RTF

7/1/2002

12/31/00 $

8,000,000 $

6,047,183 EEA/Parsons

8

9 PHOSPHORUS REMOVAL - PILOT

$

129,386,187 EEA

5,000,000 $

4,111,714 EEA

CSO - Current 10

11 ERIE BLVD STORAGE SYSTEM 12 FRANKLIN ST. FCF

4/26/1999

16 KIRKPATRICK ST. PUMP STATION 17 MALTBIE STREET FCF 18 MIDLAND AVE RTF & CSO ABATEMENT

$

185,500,042 EEA

889,109 EEA

7/1/2002

10/29/02 $

5,641,860 $

12,558,335 EEA

8/31/1998

7/1/2002

04/26/99 $

250,000 $

362,028 EEA

5/1/1999

5/1/2004

12/06/00 $

75,000,000 $

135,612,853 EEA

19 MIDLAND AVE MITIGATION COSTS

$

3,000,000

20 NEWELL STREET RTF

7/1/2002

07/01/01 $

1,310,000 $

21 ONONDAGA CREEK FCF

7/1/2002

07/01/02 $

3,000,000 $

22 SEWER SEPARATION

1/1/2012

01/01/12 $

7,703,880 $

27,684,286 OBG

23 SIPHON REHABILITATION

7/1/2002

06/11/99 $

1,230,000 $

1,026,391 C&S

24 TEALL BROOK FCF

7/1/2002

12/01/01 $

175,000 $

01/14/00 $

1,000,000 $

25 WEST ST SEWER SEPARATION

5/1/1999

473,132 Moffa & Assoc. 648,342 Parsons

1,235,346 EEA 2,720,572 CHA

26 ERIE BLVD CSO ABATEMENT

New Project

OTHER 27 AMBIENT WATER MONITORING 28 OXYGENATION DEMO PROJECT 29 SEQRA REGULATORY COMPLIANCE

5/1/1999

7/1/2002

$

4/1/2003

02/25/04 $

2,400,000 $

$

50,000 $

* $

380,000,000 $

(1)

TOTAL DOLLARS (2) *Original budget figures were based on 1997 dollars (1) SEQR costs are reflected in the individual projects under total payments to date (2) Original budget figures were based on 1997 dollars

8,000,000 10,087 50,000 Parsons

665,514,254


Lake Improvement Project Status Report For The Period Ending 09/30/2015

CONSTRUCTION CONTRACT AMOUNTS

SOFT COST CONTRACTS

1 $

352,747 $

6,473,110

TOTAL PAYMENTS TO DATE

$

TOTAL ESTIMATED COST

FORECASTED COSTS

6,925,115

$

6,925,115 $

OVER/UNDER BUDGET

% COMPLETED EXPENDITURES

(1,574,885)

100.00%

(652,813)

100.00%

2 $

1,346,856

$

1,347,187

$

1,347,187 $

3 $

1,266,345 $

13,131,105

$

14,815,674

$

14,815,674 $

4 $

748,386 $

4,357,480

$

5,092,545

$

5,092,545 $

(507,455)

100.00%

5 $

451,713 $

2,974,514

$

3,520,317

$

3,520,317 $

620,317

100.00%

$

1,400,000

$

1,400,000 $

6

14,815,674

-

100.00%

7 $

999,299 $

6,956,868

$

8,393,855

$

8,393,855 $

8 $

21,289,868 $

106,962,810

$

128,688,040

$

128,688,040 $

(61,311,960)

100.00%

$

4,111,714

$

4,111,714 $

(888,286)

100.00%

19,834,814 $

185,500,042 $

$

2,684,523 $

2,018,689 $

6,967,205 $

9 $

4,055,734

10 $

34,223,190 $

124,534,417

$

165,665,228 $

11 $

901,556 $

1,734,929

$

2,684,523

12 $

973,543 $

3,920,238

$

4,948,516 $

693,855

100.00%

154,254,762 (315,477)

100.00%

89.31% 100.00%

3,767,205

71.03%

13 $

436,363 $

373,370

$

889,109

$

889,109 $

639,109

100.00%

14 $

22,529,313 $

78,331,192

$

99,619,919 $

5,180,081 $

104,800,000 $

99,356,020

95.06%

15 $

540,945

$

5,535,152

$

6,047,183 $

3,406,000 $

9,453,183 $

1,453,183

63.97%

16 $

2,520,394 $

9,882,154

$

12,558,335

$

12,558,335 $

6,916,475

100.00%

17 $

109,483 $

152,418

$

362,028

$

362,028 $

112,028

100.00%

18 $

27,637,412 $

70,265,630

$

96,945,220 $

38,667,633 $

$

3,000,000 $

19

-

135,612,853 $

60,612,853

71.49%

$

3,000,000 $

3,000,000

100.00%

20 $

472,572

$

473,132

$

473,132 $

(836,868)

100.00%

21 $

503,551

$

648,342

$

648,342 $

(2,351,658)

100.00%

26,420,398 $

5,411 $

26,425,808 $

18,721,928

99.98%

22 $

2,613,431 $

22,879,464

$

23

$

1,021,823

$

1,026,391

$

1,026,391 $

24 $

320,039 $

903,566

$

1,235,346

$

1,235,346 $

1,060,346

100.00%

25 $

403,332 $

2,311,126

$

2,720,572

$

2,720,572 $

1,720,572

100.00%

$

-

(2,389,913)

100.00%

26

27 28 $

10,087

$

19,351,389 $

$

10,087

-

$

(203,609)

-

$

10,087 $

69,112,628 $

668,661,404 $

29

$

124,706,156 $

462,701,366

$

618,900,164 $

100.00%

296,711,404


September 2015

Project Title

TOTAL PAYMENTS TO DATE 09-30-15

TOTAL PAYMENTS TO DATE 06-30-15

Change

METRO - Current 1 AERATION SYSTEM UPGRADE

$

6,925,115

$

6,925,115

$

-

2 AMMON. REMOVAL DEMONSTRATION

$

1,347,187

$

1,347,187

$

-

3 BIOSOLIDS - MECHANICAL THICKENERS

$

14,815,674

$

14,815,674

$

-

4 DIGESTER MOD/CHEMICAL STORAGE

$

5,092,545

$

5,092,545

$

-

5 DIGITAL SYSTEMS IMPROVEMENTS

$

3,520,317

$

3,520,317

$

-

6 MISCEL. IMPROVEMENTS

$

1,400,000

$

1,400,000

$

-

7 ODOR CONTROL

$

8,393,855

$

8,393,855

$

-

8 AMMONIA REMOVAL FULL SCALE/

$

128,688,040

$

128,688,040

$

-

STAGE II PHOSPHORUS REMOVAL 9 PHOSPHORUS REMOVAL - PILOT

$ $

4,111,714

$ $

4,111,714

CSO - Current 10 CLINTON ST. CONVEYANCE/ CLINTON ST. RTF

$ $

165,665,228

$

161,853,116

-

$

-

$

-

$

3,812,113

$

-

11 ERIE BLVD STORAGE SYSTEM

$

2,684,523

$

2,684,523

$

-

12 FRANKLIN ST. FCF

$

4,948,516

$

4,948,516

$

-

13 HARBOR BROOK FCF

$

889,109

$

889,109

$

-

14 HARBOR BROOK CSO ABATEMENT

$

99,619,919

$

97,400,787

$

15 HIAWATHA INTERCEPTOR/RTF

$

6,047,183

$

6,047,183

$

-

16 KIRKPATRICK ST. PUMP STATION

$

12,558,335

$

12,558,335

$

-

17 MALTBIE STREET FCF

$

362,028

$

362,028

$

-

18 MIDLAND AVE RTF & CSO ABATEMENT

$

96,945,220

$

96,609,802

$

19 MIDLAND AVE MITIGATION COSTS

$

3,000,000

$

3,000,000

$

-

20 NEWELL STREET RTF

$

473,132

$

473,132

$

-

21 ONONDAGA CREEK FCF

$

648,342

$

648,342

$

-

22 SEWER SEPARATION

$

26,420,398

$

26,409,763

$

10,635

23 SIPHON REHABILITATION

$

1,026,391

$

1,026,391

$

-

24 TEALL BROOK FCF

$

1,235,346

$

1,235,346

$

-

25 WEST ST SEWER SEPARATION

$

2,720,572

$

2,720,572

$

-

26 ERIE BLVD CSO ABATEMENT

$

$

-

$

-

-

$

-

OTHER

2,219,132

335,418

27 AMBIENT WATER MONITORING

$

19,351,389

$

19,351,389

$

-

28 OXYGENATION DEMO PROJECT

$

10,087

$

10,087

$

-

29 SEQRA REGULATORY COMPLIANCE

$

-

$

-

$

-

$

-

TOTAL DOLLARS

$

618,900,164

$

612,522,867

$

6,377,297


Chronology of Project Construction Starts Status

Location

Complete Complete

Metro Metro

Digital Systems Upgrade Ammonia Removal Demonstration Aeration System Upgrade Hiawatha RTF - ACOE Newell St. RTF Demo/Improvements Maltbie St. FCF Siphon Rehab

Complete Complete Complete Complete Complete Complete Complete

Metro Metro Metro Regional Market W.Newell/Vale St. Maltbie/Plum St. Various

Digester Modifications/Chemical Storage Franklin St. FCF West Street Sewer Separation

Complete Complete Complete

Ammonia Trackdown

Complete

Metro I-690/Franklin W. Genesee, Plum, Tracy, N. West St. Metro

Midland Ave. Conveyance Phase I Phosphorus Removal – Phase I Pilot

Complete Complete

Tallman/Oxford St. Metro

Erie Blvd. Storage System Upgrade Full Scale Ammonia Removal/ Stage II Phosphorus Removal Kirkpatrick St. Pump Station & Force Main Onondaga Creek FCF Teall Brook FCF Water Street Sewer Separation (CSO 024)

Complete

Franklin to Teall

Complete Complete Complete Complete Complete

Metro Kirkpatrick St. Inner Harbor Teall Ave. Water Street

Harbor Brook FCF Brighton Ave Sewer Separation (CSO 053/054)

Complete Complete

W.Hiaw./I-690 Brighton/Bishop Ave

Pre-ACJ Signing (1/20/98) General Improvements Odor Control and Residuals Handling

1998

1999

2000

2001

2002


Project

Status

Location

Tallman/Onondaga Sewer Separation (CSO 038, 040, 046A &046B) Midland Phase II RTF/Conveyances

Complete

Tallman/Onondaga

Complete

Blaine/Oxford St.

Phosphorus Removal – Phase II Pilot Biosolids Handling Improvements

Complete Complete

Metro Metro

Sewer Separation – CSO 047 & 048

Complete

South Ave/ Bissell St.

Sewer Separation – CSO 050 Clinton Phase I Conveyances

Complete Complete

Parkway/Rockland

Clinton Phase IIA Conveyances

Complete

Sewer Separation – CSO 051

Complete

Colvin St.

Harbor Brook Interceptor Sewer

Complete

Velasko/Fayette

Midland CSO 044 Clinton Storage Facility Lower Harbor Brook (Conveyance & Storage) Save the Rain Green Projects CSO 022 Sewer Separation Project CSO 045 Sewer Separation Project

Complete Complete Complete Authorized/Underway Authorized/Underway Authorized/Underway

W. Castle/South Ave Armory Square Hiawatha/State Fair Blvd. Various West Genesee/Franklin South Avenue

Save the Rain Green Projects

Completed

Various

Save the Rain Green Projects

Completed

Various

Save the Rain Green Projects Harbor Brook CSO 063 Conveyances Project

Completed Underway

Various Hiawatha/State Fair Blvd.

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014


CONTRACTORS FOR CONSTRUCTION PROJECTS Metro Treatment Plant AERATION SYSTEM UPGRADE Bongiovanni Construction (General) Ridley Electric (Electrical)

$ 5,626,956.41 $ 846,154.00

DIGITAL SYSTEM UPGRADE Systems Integrated

$ 2,974,514.27

ODOR CONTROL CONTRACT #1 Falconet, Inc. (General) Scriba Electric (Electrical) Burns Bros. (Heating/Ventilation) Burns Bros. (Plumbing)

$ 4,872,660.53 $ 315,580.30 $ 82,459.00 $ 50,168.00

ODOR CONTROL CONTRACT #2 Murnane Construction

$ 1,636,000.00

PHASE III IMPORVEMENTS CONTRACT 1 - DIGESTER & LAGOON IMPROVEMENTS Maxim Construction

$

645,730.74

PHASE III IMPROVEMENTS CONTACT 2 - CHEMICAL STORAGE & FEED FACILITIES C.O. Falter Construction Corp. (General) Barry & Barry Electrical Co. (Electrical) Burns Bros. (HVAC) Edward Joy Company (Plumbing)

$ 2,527,300.08 $ 193,665.22 $ 224,232.51 $ 38,669.35

PHASE III IMPROVEMENTS CONTRACT 3 - DIGESTER & LAGOON CLEANING Waste Stream Environmental Inc.

$

727,881.80

$ $ $ $

28,388.00 112,224.00 32,295.00 18,440.00

FULL SCALE AMMONIA/PHOSPOHORUS REMOVAL - FIELD OFFICE James & Son Constrcution Resun Leasing, Inc. Ridley Electric Co. Burns Brothers

FULL SCALE AMMONIA/PHOSPHORUS REMOVAL U.S. Filter - Kruger Products, Inc. U.S. Filter - Kruger Products, Inc.

$ 8,261,182.00 $ 3,918,080.00


CONTRACTORS FOR CONSTRUCTION PROJECTS Metro Treatment Plant FULL SCALE AMMONIA/PHOSPHORUS REMVOAL SITE PREPARATION - CONTRACT 2 C.O. Falter Construction Corp. (General) Ridley Electric (Electrical) C.O. Falter Construction Corp. (Pile Testing) Moretrench Environmental

$ 22,243,604.98 $ 255,627.00 $ 431,008.00 $ 4,602,086.57

PILE INSTALLATION - CONTRACT 3 M.A. Bongiovanni Construction

$ 9,045,731.95

GENERAL - CONTRACT 4 The Pike Company (General) Ridley Electric Co. (Electrical) Edward Joy Company (HVAC) Burns Brothers (Plumbing/Fire Protection)

$ $ $ $

46,860,263.46 6,927,238.00 3,009,057.61 1,217,583.74

BIOSOLIDS HANDLING IMPROVEMENTS C. O. Falter Construction Corp. (General) Ridley Electric (Electrical) Airside Technology (HVAC) Burns Bros. (Plumbing) Independent Fiedl Svs (Cogen)

$ 10,929,016.19 $ 1,476,223.00 $ 532,187.00 $ 173,679.09 $ 18,019.75

CSO's CLINTON CONVEYANCES PHASE I & 2A The Delaney Group, Inc. The Delaney Group, Inc. SIDA MOU (City of Syracuse) MOU City of Syracuse (Connective Corridor)

$ 14,478,053.39 $ 4,074,455.32 $ 2,634,999.43 $ 168,000.00 $3,825,000.00

CLINTON CSO ABATEMENT Ruston Paving (Farmers' market Lot) Davis Wallbridge (Pearl St/Lot 3) Davis Wallbridge (Townsend St.) J&B (Pirro Conv. Center) C.O. Falter (War Memorial) Ridley (War Memorial) Economy Paving (On Center) J&B (Erie Canal Museum) Jett Industries (Clinton Storage) Joy Process Mechanical (Cistern War Memorial) C&S Technical (Cistern War Memorial) Green Culture (Rain Barrels) Syracuse Utilities (Duct Bank) Water Cooling Corp. (Storage Tank)

$ 188,046.14 $ 635,873.93 $ 476,625.39 $ 1,083,727.39 $ 692,298.87 $ 447,957.66 $ 1,094,119.49 $ 73,480.00 $ 76,522,539.87 $ 82,615.00 $ 233,652.56 $ 44,335.50 $ 59,982.56 $ 2,875.00


CONTRACTORS FOR CONSTRUCTION PROJECTS CSO's (cont) MOU City of Syracuse (Road Reconstruction) MOU City of Syracuse (Dr. Weeks) MOU City of Syracuse (Bank Alley) MOU City of Syracuse (Upstate) Walbridge (Streetscape/Water St) Ruston Paving (Sunnycrest Parking Lot) MA Bongiovanni Inc. Acts II Construction (Skiddy Park) D.E. Tarolli (Otisco Street) Orchard Earth & Pipe (Syr School dist Park Lot) Slate Hill Construction (E. Water St) Davis Wallbriddge (Onon Cty Pub Library) Tumbers, Schichtels Nursery (Trees), Martisco, Dixie, Pro Scapes Acts II (Seymour Academy) Paul R. Vitale (City Lot 4) John R. Dudley (Leavenworth Park) VIP (Onon Public Library) Ballard Construction (Westcott Comm Ctr) Cornerstone Paving (Oswego St) John Dudley Construction (W. Onondaga St.) Barrett Paving (W. Fayette St.) Davis Wallbriddge (Westcott St.) ProScapes (Sunnycrest Arena) Acts II (E. Washington St) John R. Dudley (690 Downspout) Josall (Maganelli Comm Ctr) Spectra (Butternut Circle) Jeffrey DeRoberts (GIF) King & King Architects (GIF) Jefferson Clinton Commons (GIF) ESF Foundation, Abby Lane Housing (GIF) Hotel Skyler (GIF) Near West Side Initiatives, Inc. (GIF) Near West Side Initiatives, Inc. (GIF) Tash Taskale (GIF) St. Lucy's Church (GIF) Putnam Properties (GIF) Centro (GIF) 500 W. Onondaga St. Inc. (GIF) CNY Jazz Arts Foundation (GIF) Jim & Juli Boeheim Foundation (GIF) Home Headquarters, Inc. (GIF) Galleries of Syr, 147 E. Onondaga St. (GIF) Syracuse Housing (GIF) Kopp billing Agency (GIF) American Beech (GIF) Park Central Presbyterian Church (GIF)

$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $

638,997.06 89,000.00 108,000.00 1,500,000.00 1,432,437.86 410,372.20 3,000.00 550,916.44 1,847,459.81 430,172.42 147,952.84 320,291.95 697,899.35 373,309.00 607,852.44 719,311.20 54,160.06 52,500.00 109,046.54 1,371,475.75 588,982.07 870,263.89 87,585.22 795,523.24 597,965.65 378,400.00 65,640.00 99,311.00 100,000.00 100,000.00 78,000.00 100,000.00 22,730.69 78,000.00 100,011.00 125,000.00 75,757.00 65,390.00 52,740.00 52,188.00 163,203.51 40,500.00 100,000.00 120,290.00 25,300.00 53,050.00 61,050.00


CONTRACTORS FOR CONSTRUCTION PROJECTS CSO's (cont) CNY Philanthropy (GIF) Loon Creek (GIF) NHW Syracuse (GIF) McMahan/Ryan Child Advocacy (GIF) St. Lucy's Church (GIF) Bethany Baptist Church (GIF) St. Lucy's Church (GIF) 500 W. Onondaga St. Inc. (GIF) Onondaga Commons LLC (GIF) Onondaga Commons LLC (GIF) Onondaga Commons LLC (GIF) Onondaga Commons LLC (GIF) Gemmi Boy (GIF) Mr. Lady Bug (GIF) Grace Episcopal Church (GIF) Snapse Downtown (GIF) 360 Warren Associates (GIF) Housing Visions Unlimited (GIF) Near West Side Initiatives, Inc. (GIF) Scannell Properties (GIF) Genesee Armory (GIF) Third National Associates (GIF) Center for Peace & Social Justice (GIF) Graham Millwork (GIF) Onondaga Commons LLC (GIF) Onondaga Commons LLC (GIF) Onondaga Commons LLC (GIF) PEACE (GIF) Syracuse Business Center (GIF) Erie Bruce Corp (GIF) Visiting Nurses Association (GIF) Near West Side Initiatives, Inc. (GIF) JNJ Syracuse (GIF) UAS (GIF) Brewster Medical (GIF) Southside Community (GIF) J C Smith Inc. (GIF) Burnet Railroad (GIF) Taksum Assoc. (GIF) Zip Networks (GIF) Ra lin Inc. (GIF) Ra lin Inc. (GIF) Butternut St. LLC (GIF) Nojaim Inc. (GIF) St. Joseph's Hopital Health Center (GIF) University Hill Apts. (GIF) Auto Row (GIF)

$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $

62,700.00 137,350.00 129,400.00 178,050.00 17,700.00 301,930.00 69,000.00 34,347.00 124,200.00 198,300.00 175,787.00 77,800.00 47,537.00 46,700.00 99,000.00 35,700.00 107,864.00 194,650.00 34,500.00 204,000.00 144,400.00 533,300.00 57,700.00 90,500.00 124,100.00 33,400.00 294,300.00 52,200.00 288,400.00 151,700.00 60,349.20 94,300.00 32,600.00 57,600.00 221,000.00 59,800.00 337,250.00 357,400.00 45,200.00 276,529.00 137,000.00 206,450.00 104,430.00 234,800.00 145,900.00 36,500.00 164,000.00


CONSTRUCTION PROJECTS CSO's (cont) J C Smith Inc. (GIF) WCNY (GIF) St. Joseph's Hopital Health Center (GIF) Housing Visions Unlimited (GIF) Thomas J Cerio (GIF) R J Westcott (GIF) R J Westcott (GIF) R J Westcott (GIF)

$ $ $ $ $ $ $ $

84,411.00 98,527.00 33,100.00 70,200.00 36,750.00 125,750.00 119,687.00 13,500.00

ERIE BOULEVARD STORAGE SYSTEM M. Hubbard Construction Rdiley Electric (Electrical) Endeco/YSI (SE33923)

$ 1,556,752.00 $ 154,059.00 $ 24,117.90

FRANKLIN STREET FCF Burns Bros (Mechanical) Scriba electric (Electrical) Burns Bros. (Plumbing) Maxim

$ 179,167.67 $ 144,640.61 $ 28,400.00 $ 3,568,029.43

HARBOR BROOK CSO ABATEMENT Joseph J. Lane Construction (Interceptor Sewer Replacement) Bette Cring (Elephant Barn Greening) John Dudley Construction (Geddes St) J&B Installaions (Hazard Library/Erie Canal Museum) Economy Paving (Rosamond Gifford Zoo) J.J. Lane (Lower HB) A.J. Montclair (HB CSO Storage) C.O. Falter (HB CSO Storage) Davis Wallbridge (Onon Cty Pub Library) Cornerstone Paving (Parking Lots) Green Culture Tumbers, Schichtels Nursery (trees), Proscapes, Dixie City of Syracuse VIP Steadman Old Farm Marcellus Const. (CSO 063) OnSite J J Lane (CSO 18) Patricia Electric (Wetland Pilot) MOU City of Syracuse (Road Reconstruction) Davis Wallbridge (Wadsworth Park) Acts II (Lewis Park) Knapp Electric (Wetlands) Vitale Excavating (Bedding Sand), Butler Fence Bette Cring (Zoo Wetlands) DE Tarolli (Green Structures)

$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $

23,391,425.07 207,701.00 279,068.06 67,275.00 688,638.00 4,923,078.94 260,000.00 30,259,100.80 378,920.43 149,195.48 80,665.00 321,497.73 3,342,875.63 54,160.06 11,480.00 5,780,441.00 8,755.00 4,170,168.29 194,436.23 138,165.00 345,524.55 217,285.58 41,856.00 232,533.35 1,290,064.10 985,915.87


CONTRACTORS FOR CONSTRUCTION PROJECTS CSO's (cont) J & J Landscape Vibrant Spaces, LLC (GIF) NYSARC, Inc. (GIF) Consuela's Westside Taqueria (GIF) Consuela's Tato Britter (GIF) James Ranalli, W. Genesee (GIF) Vibrant Spaces, LLC (GIF) Brooklyn Pickle (GIF) St. Patrick's Loft (GIF) Smith Housing (GIF) Richard Destito (GIF) Burnet Park Newstand (GIF) All Times (GIF)

$ $ $ $ $ $ $ $ $ $ $ $ $

34,742.00 153,618.00 78,907.14 29,988.00 8,249.50 616,100.00 198,680.00 30,555.00 177,300.00 52,600.00 152,300.00 59,256.00 76,500.00

$

373,370.21

HARBOR BROOK FCF C.O. Falter Construction Corp. (General)

KIRKPATRICK ST. PUMP STATION & FORCE MAIN C.O. Falter Construction Corp. C.O. Falter Construction Corp. Patricia Electric King & King Mechanical

$ 4,398,009.12 $ 4,425,766.31 $ 761,184.63 $ 245,569.51

MALTBIE STREET FCF Over & Under Piping

$

152,418.00

MIDLAND AVENUE CONVEYANCES Marcellus Construction (General)

$ 1,836,434.47

MIDLAND AVENUE PHASE II CONVEYANCES & RTF Empire Dismantlement Corp. (Demolition) Murnane Building Contractors, Inc. (General) Ridley Electric Company (Electrical) Edward Joy Company (HVAC) Edward Joy Company (Plumbing)

$ 457,681.50 $ 47,929,392.75 $ 2,904,771.00 $ 2,053,808.50 $ 484,717.17

MIDLAND AVENUE PHASE III CONVEYANCES Titan Wrecking & Environmental, LLC (Demolition) J.J. Lane Acts II (Hugh's Magnet School Parking Lot) Davis Wallbridge (Onon Cty Pub Library) VIP (Onon Public Library) Green Culture (Rain Barrels)

$ 290,801.39 $ 12,098,662.37 $ 314,439.81 $ 116,033.35 $ 27,080.03 $ 44,335.50


CONTRACTORS FOR CONSTRUCTION PROJECTS CSO's (cont) Tumbers, Schichtels Nursery (Trees) Weather Guard Tecta (USPO Salina St) MOU City of Syracuse (Road Reconstruction) MA Bongiovanni (storage Tank) MOU City of Syracuse (ESF) Env. Design (Gazones Stormwater) Jubilee Homes of Syracuse (GIF) Dunbar Association, Inc. (GIF) Syracuse Model Neighborhood (GIF) People's AME Zion Church (GIF) People's Community Dev. Corp (GIF) Salina Shoe Salon (GIF) People's AME Zion Church (GIF) Matawon Development Group (GIF) Tucker Missionary Baptist Church (GIF) Swallows (GIF) Lauren Tawil (GIF)

$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $

176,791.44 242,860.00 408,332.04 66,130.00 100,000.00 66,500.00 100,000.00 99,840.00 250,000.00 61,400.00 80,825.00 48,000.00 5,000.00 24,214.00 195,000.00 117,200.00 212,400.00

SEWER SEPARATION - CSO 022/045 Joy Process Mechanical (Plumbing) Joseph J. Lane Construction

$ 853,536.68 $ 4,757,886.66

SEWER SEPARATION - CSO 024 C.O. Falter Construction Corp.

$

698,863.74

SEWER SEPARATION - CSO 053/054 C.O. Falter Construction Corp.

$ 2,000,817.40

SEWER SEPARATION - CSO 038, 040, 046A&B C.O. Falter Construction Corp.

$ 3,524,487.29

SEWER SEPARATION - CSO 047 & 048 C.O. Falter Construction Corp.

$ 1,654,022.34

SEWER SEPARATION - CSO 050 Joseph J. Lane Construction

$ 4,360,527.06

SEWER SEPARATION - CSO 051 Joseph J. Lane Construction

$ 5,029,323.00

SIPHON REHABILITATION Insituform Metropolitan

$ 1,021,822.99


CONTRACTORS FOR CONSTRUCTION PROJECTS CSO's (cont) TEALL BROOK FCF C.O. Falter Construction Corp. (General) Scria Electric (Electrical)

$ $

877,095.43 26,470.20

WEST STREET AREA SEWER SEPARATION Maxim Construction (General)

$ 2,311,125.85


WEP ACRONYMS ACJ

Amended Consent Judgment

AMP

Ambient Monitoring Program

AMSA

Association of Metropolitan Sewerage Agencies

ARRA

American Recovery and Reinvestment Act

ASLF

Atlantic States Legal Foundation

AWQS

Ambient Water Quality Standards

BAF

Biological Aerated Filter (Biostyr)

BMP

Best Management Practices

BOD

Biological Oxygen Demand

BPJ

Best Professional Judgment

Brew

WEP’s Standard Abbreviation for the Brewerton Wastewater Treatment Plant

Bville

WEP’s Standard Abbreviation for the Baldwinsville Wastewater Treatment Plant

CAA

Clean Air Act

CALM

Consolidated Assessment and Listing Methodology

CAMP

Community Air Monitoring Plan

CIP

Capital Improvement Plan

CMOM

Capacity, Management, Operation, and Maintenance

CSLAP

Citizens Statewide Lake Assessment Program

CSO

Combined Sewer Overflow

CWA

Clean Water Act

DMR

Discharge Monitoring Report

DO

Dissolved Oxygen

EBM

Ecosystem-Based Management

ECL

Environmental Conservation Law

ECM

Energy Conservation Measures

EECBG

Energy Efficiency and Conservation Block Grant

ELAP

Environmental Laboratory Approval Program

EMS

Environmental Management System

ERM

Environmental Resource Mapper

FCF

Floatable Control Facility

FOG

Fats, Oil, and Grease

GIF

Green Improvement Fund

H:\2013\MoRpt\Abbreviations\abbreviations.doc


HRFS

High Rate Flocculation Settling

I&I

Inflow & Infiltration

IW

Industrial Wastewater

km

Kilometers

km2

Square Kilometers

LA

Load Allocations

LF

Linear Feet

m

Meters

MCP

Municipal Compliance Plan

MDV

Multiple Discharge Variance

Metro

WEP’s Standard Abbreviation for the Metropolitan Syracuse Wastewater Treatment Plant

MGD

Million Gallons Per Day

mg/L

Milligrams Per Liter

MIS

Main Interceptor Sewer

ML

WEP’s Standard Abbreviation for the Meadowbrook/Limestone WWTP

MS4s

Municipal Separate Storm Sewer Systems

mt

Metric Tons

NACWA

National Association of Clean Water Agencies

NBP

National Biosolids Partnership

NELAC

National Environmental Laboratory Accreditation Conference

NPDES

National Pollutant Discharge Elimination System

NYSDEC

New York State Department of Environmental Conservation

NYSDOH

New York State Department of Health

NYSEFC

New York State Environmental Facilities Corp.

NYWEA

New York Water Environmental Association

OAK

WEP’s Standard Abbreviation for the Oak Orchard WWTP

OLP

Onondaga Lake Partnership

OLWQM

Onondaga Lake Water Quality Model

OU

Odor Unit

P2

Prevention Program

P2CO

Prevention Program County Operations

PdM

Predictive Maintenance

H:\2013\MoRpt\Abbreviations\abbreviations.doc


PIDs

Photo-ionization Detectors

PFRP

Process to Further Reduce Pathogens

PLA

Project Labor Agreement

POTW

Publicly Owned Treatment Works

PWL

Priority Waterbodies List

RTF

Regional Treatment Facility

SCA

Sediment Consolidation Area

SCADA

Supervisory Control and Data Acquisition

SEPS

Secondary Effluent Pump Station

SEQR

State Environmental Quality Review

SGIP

Suburban Green Infrastructure Program

SHB

Solids Handling Building

SMPs

Storm Water Management Practices

SOP

Standard Operating Procedure

SORP

Sewer Overflow Response Plan

SPCC

Spill Prevention, Control, and Countermeasures

SPDES

State Pollutant Discharge Elimination System

SRP

Soluble Reactive Phosphorus

SSES

Sanitary Sewer Evaluation Study

SSI

Sewage Sludge Incinerator

SSV

Site-Specific Variance

SUNY-ESF

State University of New York College of Science and Forestry

SWMM

Storm Water Management Modeling

SWMP

Storm Water Management Plan

SWPPP

Storm Water Pollution Prevention Plan

TBEL

Stechnology-Based Effluent Limits

TDP

Total Dissolved Phosphorus

TMDL

Total Maximum Daily Load

TP

Total Phosphorus

TSI

Trophic State Index

UAA

Use Attainability Analysis

UFI

Upstate Freshwater Institute

ug/l

Micrograms per Liter

USEPA

United States Environmental Protection Agency

H:\2013\MoRpt\Abbreviations\abbreviations.doc


USFWS

United States Fish and Wildlife Service

USGBC

United States Green Building Council

USGS

United States Geological Survey

UST

Underground Storage Tank

VOC

Volatile Organic Compounds

WAN

Wide Area Network

WLA

Waste Load Allocations

WEF

Water Environment Federation

WEP

Water Environment Protection

WET

Whole Effluent Toxicity

WLA

Waste Load Allocations

WQBEL

Water Quality-Based Effluent Limits

WR

WEP’s Standard Abbreviation for the Wetzel Road Wastewater Treatment Plant

WSE

Waste Stream Environmental

H:\2013\MoRpt\Abbreviations\abbreviations.doc