Onondaga County’s Green Infrastructure Program Joanne M. Mahoney, County Executive
Onondaga Lake Amended Consent Judgment (ACJ) Compliance Program
Westcott Street Green Corridor June 2013 Eastside TNT Meeting Zach Monge – CH2M HILL June 11, 2013
5/29/13
Westcott Street Green Corridor
2
5/29/13
Westcott Street Curb Alignment
3
5/29/13
Westcott Street Curb Alignment
4
5/29/13
Westcott and Dell
5
5/29/13
Westcott and Harvard
6
5/29/13
Westcott and Beech
7
5/29/13
Construction Schedule – Davis Wallbridge • 4 Phases of Work ▫ Phase 1: West Side of Street from Dell to Beech June 17/24, 2013 – August 30, 2013
▫ Westcott Street Cultural Fair September 15, 2013
▫ Phase 2: Knoll and East Side of Street between Concord and Victoria September 16, 2013 – November 15, 2013
▫ Phase 3: East Side of Street from Victoria to Dell April 15, 2014 – May 31, 2014
▫ Phase 4 (CITY): Road Reconstruction (Mill/Pave) June 1, 2014 – TBD (at the City’s Discretion)
8
5/29/13
9 Phase 1: 6/17/138/30/13
Phase 3: 4/15/145/31/14
Phase 4 (Not Shown): 6/1/14 - TBD Phase 2: 9/16/1311/15/13
5/29/13
Construction Schedule
10
• At no time will Westcott Street be entirely shut down ▫ Two-way traffic (alternating) through the corridor ▫ Temporary traffic lights will be at Dell and Beech ▫ Access to Westcott Street from Harvard, Victoria, Dell and Beech to be closed throughout construction
• Entire “Phase” of work will not be constructed all at once ▫ All of Phase 1 will not be closed at the same time; to be broken up into segments (i.e. unrolling a carpet)
• Sidewalk panel closest to buildings will be open at all times • Wayfinding and business signage will be posted (24”x18”) • Weekly construction communication emails to be sent ▫ Listserv to be organized
5/29/13
11
Thank You! Questions? Please Visit us at www.SaveTheRain.us