w/c 16th October 2017 Vote Southside Parklet For those of you still uncertain about what, exactly, Southside’s parklet on Bromsgrove Street is, you can head on over to YouTube and see its recent appearance on Midlands Today here: https://youtu.be/gYnjeKzUCKI Other welcome news is that the parklet has received a nomination for UK’s Best Park, as voted by YOU! 2017. We strongly urge everyone to head over to the awards website and vote Southside: www.fieldsintrust.org/bestpark/westmidlands#Southside-Parklet Voting for UK’s Best Park 2017 closes at 5pm on Friday 3rd November after which the shortlist will be announced. The one park with the highest number of votes in each of England, Wales, Scotland and Northern Ireland will be shortlisted and the overall winner will be announced at the Fields in Trust Awards at Lord’s Cricket Ground in London on Wednesday 29th November.
Civil Works The latest weekly briefing on the civil works is attached at the end of this update.
Trees and Flowers The Trees on Hippodrome/Southside Square have now been pruned and the red lanterns returned in advance of the Christmas Lighting. From Monday the Civil Works to make Southside Square happen will be commencing. You will also see that the planters have been emptied of summer flowers. Birmingham Parks and Nurseries will be restocking them for the next season by the end of the week.
RBSA Charity Auction The Royal Birmingham Society of Artists has asked us to circulate an invitation to its first Charity Auction, run by Bonhams, on November 2. It will be hosted at Deutsche Bank’s prestigious Brindleyplace offices. For more than 200 years, the RBSA has provided opportunities in Birmingham for people to engage with the arts. The Gallery is just off St Paul’s Square, and needs to raise funds urgently to continue its year-round programme of exhibitions and events. All auction proceeds will go to the RBSA: lots have been donated by artists to raise funds for the visual arts charity which is one of the oldest Royal Societies in the UK. Income from ticket sales will go to Autistica, Deutsche Bank’s Charity of the Year.
Southside Hurst St – Permanent TRO Works OVERALL PROJECT PLAN
Emergency Contact Details Contractor: Fitzgerald Contractors Ltd Steve Jones: 07970454184 – Contract Manager Michael Southern: 07977284325 - Site Manager Out of hours contact: 0121 326 0402
Birmingham City Council Site Team Colin Pearce: 0776 692 3286 - Project Manager Mark Dixon: 07881358552 - Supervisor
Starting date:
2nd October 2017
Duration:
10 weeks
Roads Affected:
Dudley St, Pershore St, Ladywell walk, Hurst St and Thorp St
Description of Scheme: These works are required to facilitate the introduction of high quality public realm improvements in the area by implementing advanced revisions to the road network to change the way traffic operates.
The scheme includes the following activities • Permanent restriction of through traffic from Ladywell Walk to Hurst Street; • Renewing traffic signal equipment at Pershore Street/Ladywell Walk junction, including reshaping of the central pedestrian island • Conversion of protected contra-flow cycle lane on Hurst Street to protected two-way cycle lane with a cycle only phase at Smallbrook Queensway Junction • Introduction of contra-flow cycle lane on Dudley Street between Edgbaston Street and Hinckley Street • Installation of a mini roundabout at Dudley Street/ Edgbaston Street • Conversion of Dudley Street to two-way traffic between Edgbaston Street and Ladywell Walk; • Conversion of Ladywell Walk to two-way traffic between Wrottesley Street and Pershore Street • Reversal of one way flow on Thorp Street • Relocation of taxi / loading / parking bays • Localised resurfacing;
Date of Report:
12th October 2017
Working hours:
07:30 am – 17:00pm
Works Performed to date: • • •
Ducting completed along Upper Dean Street (ducting still to be completed across Upper Dean Street. Duct chambers and detector loops in carriageway on Dudley Street outside market all installed. Works started on main splitter on junction of Dudley Street/Ladywell Walk/Pershore Street
Planned Works for Week Commencing 16th October 2017 • • •
Ducting on Pershore Street Ducting and pole housings to be installed on main splitter, Dudley Street/Ladywell Walk/Pershore Street. Continue work on main splitter island
Traffic Management:
09:30 – 15:30 Pershore Street lane closure.
Pedestrian Diversions:
Pershore Street, pedestrians to use closed off lane.