Summary Report November 14, 2016
Contents Project Introduction .............................................................................................. Lake Boren Park Preferred Plan .......................................................................... Program Keynotes .................................................................................................... Design Program ........................................................................................................ Key Features .......................................................................................................... Park Views .................................................................................................................. Phasing & Cost Estimate ....................................................................................... Public Outreach Process ...................................................................................... Public Outreach Summary .................................................................................. Index of Appendices ................................................................................................
1 2 4 5 6 8 18 30 33 42
Acknowledgments The Lake Boren Park Master Plan city and consultant team would like to thank the following contributors for their varying and generous contributions in time, borrowed space, thoughtfulness, and funding: King County Flood Control District: Flood Reduction Grant King County Conservation Futures Grant The volunteer members of the City of Newcastle Community Activities Commission Newcastle City Council Newcastle Elementary Seattle Revival Center Hazelwood Elementary The Citizens of the City of Newcastle
Project Introduction Lake Boren Park is the largest city-owned park in Newcastle, Washington. The park is centrally located and serves as the primary destination for organized events and opportunities for play and relaxation. This master plan responds to the community's changing needs and growth, as well as the park's expansion. The park is currently about 22 acres. The land purchased along Boren Creek in 2016 as well as connections along the east side increase the park to around 31 acres. The design reflected in this master plan report is the result of extensive community outreach by the design team, the city team, and the Community Activities Commission. This is truly a project and design which has been shaped by the community and responds to the community's needs, hopes, dreams and wishes. The design elements included have been suggested by the community. To the greatest extent possible, the design team has carried forth the elements with the greatest support as determined by the public input collected as part of this process. The public input process is described in this report, and complete results are included with the appendix.
1
11
19
27
12 Cross Park Promenade (accessible <= 5% slope)
20 Picnic Area
28 Off-leash Area (preferred location)
13 North Sweep Boardwalk and Picnic Pavilion
21 Trees
29 Off-leash Area (alternative location)
Waterline Trail 39
39
28 17
View
12
Cor ri
dor
12 01
11
View 3 View id Corr
02
SE 84
02
View 4
21
r Co
09
04
or
rid
19 16
02
37
w Vie
ay th W
17
03
dor
08
06
02 10
Cor ri
12
21
16
03
03
Vie w
07
or
03
40
03 02
16
Vie
20 18
36
27
22
25 38
A
23 29
30
F
View 2 30
24
30
C 38
G
eek Boren Cr
26
30
B
Coal C
Lake Boren Park Preferred Plan
PROPOSED PLAN 2
ew 1
F Lake Boren
36 Accessible Lake Boren connection 40 Community Room (potential future location shown dashed)
and should be used for general reference only.
G Boren Creek
E
S ve A h
9t
12
05
11
12 30 13
D
E
Lake Boren 15
14 15
34 32
38
F 35
33 View 5
32 36 36
31
n ore B e k
E
ade
an spl
La
38
rkway Creek Pa
3
Program Keynotes (see preferred plan) Infrastructure
Lake Boren Connection
Park Core Amenities
Park-wide
01 Cross Park Lighting 02 Bioretention/Stormwater Facilities 03 Parking (expanded from 54 to 129 stalls) 04 Drop-off 05 North Parking (3 stalls) & Boat Rental Staging Opportunity
06 Newcastle Plaza (seat-walls, 30’-wide paving) 07 Amphitheater (terraced with rock outcrops) 08 Stage at the Grove (covered) 09 Additional Restrooms 10 Plaza Trellis 11 Entry Signs 12 Cross Park Promenade (accessible) 13 North Sweep Boardwalk and Picnic Pavilion 14 Beach Boardwalk 15 Beach & Boat Launch 16 Community Garden (incl. reloc. Fuchsia Garden) Shelter Improvements 17 18 Additional Tennis Court 19 Tool Storage 20 Picnic Area Trees 21
Boren Creek Collection 22 23 24 25 26 27 28 29 30
4
Boardwalk to Learning Center Shelter (learning center) Boren Creek Path (5’ crushed rock) Boren Creek Stairs Boren Creek Bridge Path around Parking Off-leash Area (preferred location) Off-leash Area (alternative location) Native/Mitigation Planting
31 32 33 34 35 36
37 38 39
Lake Boren Promenade (5’ asphalt) Lake Boren Promenade Boardwalk Promenade Deck Lake Boren Stairs Lake Boren Dock Accessible Lake Boren Connection
Site Furnishings (benches, tables, bike racks, waste/recycling receptacles) Park Identification Stair Connection
Not Included 40
Community Room (potential future location shown dashed)
Wetlands A B C D E F G
Wetland A Wetland B Boundary Wetland C Boundary Wetland D Boundary Wetland E Boundary Lake Boren Boren Creek
Wetland note: The lake, stream and wetlands and their associated buffers have been identified but not delineated in a Wetland/Stream Reconnaissance Report prepared by The Watershed Company dated April 13, 2016. For the purposes of preparing the master plan, the lake, stream and wetland boundaries and associated buffers shown herein have been located approximately and should be used for general reference only.
Design Program Make the most of what you have! This master plan update is about making the most of the park as it exists today. The community embraces the park and all it has to offer, so much so that some participants during the input process didnâ&#x20AC;&#x2122;t want to see any changes. This master plan update is not about changing the park but about improving what is already there, incorporating new park land and looking toward the future. The existing highlights of the park include passive and active recreation, open space, connections to the water, gathering spaces, play opportunities, looped walkways, and trees. The master plan proposes to maintain these features and provide additional recreation opportunities. The performance stage will be upgraded along with a new location that allows more people the opportunity to be in front of the stage. Views and access to the water are improved, as well as new walkways and paths that take advantage of the newly acquired space along Boren Creek. The park is better connected to the Esplanade and east shore of the lake. Additional parking is proposed to accommodate the growing community and outdoor activity.
5
Key Features Art in the Park The inclusion of art within the park should be considered as a way to express the unique qualities of the park and community. Opportunities for art are throughout the park. Art opportunities can be found in the paving, structures, boardwalk, park identification, and discovery pieces along the pathways.
Connections The master plan is all about making connections to new and existing park features, trails, and neighborhoods. Connections to the lake are improved in multiple ways. Access from the north park entrance to the existing dock is improved by an ADA-accessible path. New parking at the north entrance provides the opportunity to unload hand-carried watercraft with easy access to the water. A new beach improves water access, along with an area to sit and gather. A proposed boardwalk connects the existing dock and beach. This boardwalk extends around the south end of the lake to the eastside dock. This new and long-desired connection crosses over water for a unique experience that includes seating and viewing areas. When it reaches land on the east side of the lake, it becomes the Lake Boren Promenade connecting to the northern reach of the park. It also provides a connection to SE 79th Street. The cross-park promenade connects the south and north ends of the park. The renewed pedestrian entrance at the south, off SE 84th Way, provides a direct connection to the core of the park and the Newcastle Plaza. From the center of the park it extends north, making use of existing paths that provide access to the new amphitheater. The cross-park promenade is proposed to be lighted for safe access year-round. The adjacent waterline property will continue to benefit the park and community. While not owned by the city, it is a well-used connection to the park and an ideal temporary parking area during events. Accessible and paved paths provide safe, designated pedestrian routes from the waterline property to the park.
Newcastle Plaza The Newcastle Plaza provides a location for gathering and vendors during all types of civic events. This centrally located gathering space is also the location of the restroom addition. The building and plaza are a way for Newcastle's history to be shared through displays, imagery, materials and unique detailing. Another feature of the plaza is the community garden. This is the new location for the fuchsia garden with additional room for other outdoor displays both permanent and temporary. There is additional plaza space in this area for gathering, event set-up, and arrival from the expanded parking lot. The parking lot is expanded to accommodate 129 vehicles. This adds 75 to the existing 54-car lot. The parking is expanded over a stormwater vault placed within the existing stormwater detention pond.
Amphitheater In this plan, the stage is moved from its existing location to the north lawn. The stage is located near the base of the sloping lawn for better visibility and increased gathering space. The new amphitheater can easily accommodate about 1,500 people, which is approximately 500 more than the current location. The new stage location moves the performance activity downhill and slightly further from adjacent homes. It will be configured for events but will serve as a shelter for other activities during a greater part of the year. 6
The amphitheater is a sloping lawn with terraces wide enough to spread out blankets or accommodate portable lawn furniture. Accessibility is improved through access to the middle of the gathering space. A unique feature of the amphitheater, which is a feature of the Newcastle area, is the rock outcrops. These will be an integral part and create seating and recreational opportunities. Lighting is proposed for the amphitheater to ensure safe exit.
Boren Creek The Boren Creek area includes the recently acquired property. The existing houses are to be removed and the space adapted to new park uses. The northern-most home site becomes a gathering space within the existing forest. The feature of this area is the existing large and mature trees, which create a unique space for a new shelter and opportunities to view the lake and adjacent wetland. New paths through the Boren Creek area allow park visitors a unique experience of walking along the creek and through the forested wetland. The new paths connect to existing paths to create a network that crosses the creek at existing and proposed bridge locations. The location of the southern house is an option for the off-leash area. This area is about an acre and situated between an existing rock retaining wall and Boren Creek. The location is off the beaten path and becomes a destination for those seeking a place for their dog to play.
Letâ&#x20AC;&#x2122;s Play The active recreation opportunities remain. Basketball, sand volleyball, and tennis are at the center of the park. Tennis gets a boost through the addition of one court for a total of three. The childrenâ&#x20AC;&#x2122;s play area remains as it currently exists with a wide variety of play events for all ages. It is well used and liked, and no improvements were requested as part of this update. The opportunity for play is increased through relocating the stage to the north. Concert and event attendees will gather in the new amphitheater, and the lawn east of the play area will be regraded to make it more usable. Each activity will benefit by having a separate area. During large events, such as the 4th of July celebration, the lawn area will be available to accommodate the greater number of attendees.
Off-Leash Area The off-leash area has been a highly debated subject. Input received during this planning process was split between people in favor and people against. Two options for the location are proposed. The preferred location is in the southwest corner of the park in an unused area with a stand of trees, including Big Leaf Maples and Alders, and undergrowth of blackberries. The area is bowl-like with slopes to the west and north. The sloped areas create separation from the neighbors across the waterline property to the west and the park to the north. The proximity to the parking lot and park paths makes this area an option worth considering. The alternative location is in the newly acquired area away from most park activity. This location is separated from the higher-use areas of the park by elevation change and a rock retaining wall, and most park users will not be aware of its existence. It is a clearing in the woods due to the house that occupied the space for many years. The off-leash area includes the following features/amenities: equipment for agility training and a bioretention/stormwater facility to mitigate any pollution generated from the area. The off-leash area is slightly less than a half acre in size and is not envisioned as a long-range fetch amenity.
7
Park Views
View 1
Beach and boardwalk
Proposed lake access at a beach with areas to sit and relax. Lakeside vegetation is maintained to open up views of the lake and existing dock.
8
Existing condition
View 1
9
View 2
Shelter and learning center
A shelter near the south end of the lake provides a place for views of the lake and wetlands. The fireplace from the existing house could become part of the shelter.
10
Existing condition
View 2
11
View 3
Amphitheater terraced with seat-walls and rock outcrops
The amphitheater has terraces for seating. Rock outcrops create unique perches and express the geology that defines Newcastle. The Grove Shelter and stage is set next to an existing stand of trees.
12
Existing condition
View 3
13
View 4
Promenade and Plaza
Newcastle Plaza is at the center of the park and is a primary gathering place for the community. It is a place for activity and for vendors to set up during special events. Newcastle Plaza, which takes its name from the city, offers opportunities for storytelling and wayfinding elements, making the possible and unknown visible.
14
Existing condition
View 4
15
View 5
Lake Boren Promenade
The Lake Boren Promenade winds along the east shore of the lake. It allows pedestrians to get close to the water and provides a connection to the dock, promenade deck, and the Lake Boren stairs at the north end of the park. Lake overlooks and trails along the lake/wetlands provide opportunities for a linear sequence of environmental graphics and interpretive elements revealing the local ecology.
16
Existing condition
View 5
17
Phasing & Cost Estimate Phase A: Amphitheater & Newcastle Plaza This phase includes relocating and improving the stage, including a permanent stage structure that can be used as a picnic shelter during non-event times. This phase also includes the cross-park promenade, Newcastle Plaza, north and south park entries, and improved access to the pipeline right-of-way.
Quantity Unit Unit Cost Total Site preparation 5 A 30,000.00 150,000 Amphitheater - terraced, lighting 50,000 SF 6.00 300,000 Stage at the Grove - conc. pad, structure, power Allow 140,000.00 140,000 Newcastle Plaza - conc. paving and seat walls 7,000 SF 22.00 154,000 Cross-park promenade (10' asphalt) 5,100 LF 85.00 433,500 Cross-park promenade lighting - 28 fixtures 28 EA 6,250.00 175,000 North parking - 3 stalls, drive aisle, turn around 3 EA 21,500.00 64,500 North and south park entries and signs 2 EA 10,000.00 20,000 Off leash area (optional location) 50,000 SF 5.00 250,000 Shelter - improvements to existing 2 EA 15,000.00 30,000 Site furnishings Allow 20,000.00 20,000 Planting and irrigation 5 A 130,000.00 650,000 Interpretation 1 Allow 10,000 10,000 Subtotal $2,397,000 Taxes (9.5%) Design Fees (12%) Total 18
* Phases represent proposed groupings and are not in order of priority or proposed sequence.
$227,715 $287,640 $2,912,355
Phase B: Beach This phase includes creating a beach area at the lake, gathering spaces, a shelter, improved access from the north entry to the lake, and a connecting boardwalk around the south end of the lake.
Quantity Unit Unit Cost Total Site preparation 1.20 A 30,000.00 36,000 Boardwalk - north sweep 1,500 SF 70.00 105,000 Boardwalk at the beach 2,200 SF 70.00 154,000 Beach 6,000 SF 12.00 72,000 Lake Boren Promenade Boardwalk (south) 3,000 SF 90.00 270,000 Site furnishings Allow 15,000.00 15,000 Planting and irrigation 1.20 A 130,000.00 156,000 Boat launch path (5' crushed rock) 110 LF 30.00 3,300 Subtotal $811,300 Taxes (9.5%) Design Fees (12%) Total
* Phases represent proposed groupings and are not in order of priority or proposed sequence.
$77,074 $97,356 $985,730
19
Phase C: Boren Creek This phase includes improvements to the recently acquired parcels. A forest shelter is included along with an off-leash area, connecting paths adjacent to the creek, and improved access from the existing park paths.
Quantity Unit Unit Cost Total Site preparation 2 A 30,000.00 60,000 Boardwalk to Learning Center 2,100 SF 70.00 147,000 Shelter - Learning Center Allow 100,000.00 100,000 Boren Creek path (5' crushed rock) 1,600 LF 30.00 48,000 Boren Creek stairs 150 LF 160.00 24,000 Boren Creek bridge 480 SF 100.00 48,000 Path around parking (5' crushed rock) 600 LF 30.00 18,000 Off-leash area (optional location) 50,000 SF 5.00 250,000 Invasive species removal Allow 25,000 Native/mitigation planting 90,000 SF 5.00 450,000 Rockery railing (4' ht chain link) 250 LF 35.00 8,750 Site furnishings Allow 10,000.00 10,000 Subtotal $1,188,750 Taxes (9.5%) Design Fees (12%) Total 20
* Phases represent proposed groupings and are not in order of priority or proposed sequence.
$112,931 $142,650 $1,444,331
Phase D: Lake Boren Connection This phase includes additional access to the east side of the lake. The Lake Boren promenade provides an alternate walking experience from the Esplanade and connects the boardwalk (Phase B), the dock, the promenade deck, and Lake Boren stairs. This phase also completes the cross-park trail that connects to neighborhoods to the east.
Quantity Unit Unit Cost Total Site preparation 4 A 30,000.00 120,000 Lake Boren Promenade - (5' asphalt) 800 LF 40.00 32,000 Lake Boren Promenade boardwalk (north) 950 SF 90.00 85,500 Promenade deck - rebuilt 300 SF 90.00 27,000 Lake Boren stairs - rebuilt 200 LF 160.00 32,000 Invasive species removal Allow 15,000 Native/mitigation planting 50,000 SF 5.00 250,000 Site furnishings Allow 15,000.00 15,000 Native planting, no irrigation 25,000 SF 2.00 50,000 Interpretation 1 Allow 10,000 10,000 Subtotal $636,500 Taxes (9.5%) Design Fees (12%) Total
* Phases represent proposed groupings and are not in order of priority or proposed sequence.
$60,468 $76,380 $773,348
21
Phase E: Parking Expansion This phase includes improving and expanding the existing parking lot. An underground stormwater storage and treatment vault is located under the east half of the parking lot.
Quantity Unit Unit Cost Total Site preparation Allow 200,000 Stormwater storage, conveyance, treatment Allow 850,000 Parking expansion to 129 stalls 75 Stall 3,000.00 225,000 Lighting 8 EA 8,000.00 64,000 Site furnishings Allow 15,000 Planting and irrigation 20,000 SF 6.00 120,000 Subtotal $1,474,000 Taxes (9.5%) Design Fees (12%) Total
22
* Phases represent proposed groupings and are not in order of priority or proposed sequence.
$140,030 $176,880 $1,790,910
Phase F: Entry Plaza This phase includes restroom expansion, park plaza, community garden, and an additional tennis court.
Quantity Unit Unit Cost Total Site preparation 2 A 40,000.00 80,000 Restroom expansion Allow 750,000 Park plaza 8,000 SF 22.00 176,000 Plaza trellis 750 SF 120.00 90,000 Community garden 1,500 SF 20.00 30,000 Additional tennis court Allow 225,000 Site furnishings Allow 25,000 Planting and irrigation 12,500 SF 8.00 100,000 Subtotal $1,476,000 Taxes (9.5%) Design Fees (12%) Total
$140,220 $177,120 $1,793,340
* Phases represent proposed groupings, are not in order of priority or proposed sequence.
23
Grand Total
Subtotal Phase A Subtotal Phase B Subtotal Phase C Subtotal Phase D Subtotal Phase E Subtotal Phase F
$2,397,000 $811,300 $1,188,750 $636,500 $1,474,000 $1,476,000
Subtotal $7,983,550 Tax (9.5%) $758,437 Design Fee (12%) $958,026 Total $9,700,013
Inclusions Contingency (20%) General Conditions (10%) Contractor Overhead (8%) Contractor Profit (8%)
24
Exclusions Demolition and restoration of acquired parcels Fishing dock repair Utility upgrades, if necessary Park maintenance Permits
* Phases represent proposed groupings and are not in order of priority or proposed sequence.
25
Amphitheater - Existing & Proposed The existing amphitheater and stage area is collocated with the playground forming one contiguous, highly programmed space. The master plan design pulls the amphitheater and stage away from the playground providing more space for these two programmatic uses, but also allows for a zone of overlapping use in between where park users can have eyes on both the playground and the stage from a single vantage point. Think of it as a venn diagram!
Area of proposed overlapping use/ views: Playground + Amphitheater
1,000 SF
42,000 SF
Existing Amphitheater: 43,000 SF / 40 SF per person = 1,075
26
A
9,100 SF
48,000 SF
A
Proposed Amphitheater: 48,000 SF / 40 SF per person = 1,550
27
AMPHITHEATER SECTION A-A
28
29
Public Outreach Process The master plan process included a robust public outreach process involving multiple types of outreach. The process centered around public meetings but also utilized a mailer, online surveys, an input kiosk in the park, and fliers. Below is a diagram showing the components of the process and where they occurred from Site Analysis to Concept Design to Master Plan Development.
Online Survey #1
Kiosk Outreach Poster #1 12/2015
8'
71 2"
12/2015
(7) FULL 45 x 6 BOARDS (ACTUAL 1"x
2"
2"
5.5")
71 2"
6'-5"
BITUMINOUS ROLL ROOFING, SECURE WITH NAILS - NO TRIM
3'
Mailer #1
Public Meeting #1
12/2015
1/12/2016
FLUSH
°
5 4 x 6 (ACTUAL 1" x 5.5") FIR/PINE LUMBER (ROUGH SAWN PREFERRABLE), TYP.
3 x 8 (ACTUAL 2.5" x 7.5") FIR/PINE LUMBER (ROUGH SAWN PREFERRABLE), TYP.
Newcastle Cemetery
Notice Posts
45°
10"
90
Share your vision! 1. Grab a pen and paper tag. 2. Write down your favorite Lake Boren Park experiences, what you love most about the park or what you would most like to see here. 3. Pin your tag on the kiosk to share your vision.
21 2"
LAKE BOREN PARK
Lake Boren
45°
(12) FULL 45 x 6" BOARDS (ACTUAL
1"
7'
. on! here visi are your You re Sha
APPROX. 7'-33 4" CLEAR
Parkway
1" x 5.5")
Coal Creek
45°
2016
8 x 8 (ACTUAL 7.5" x 7.5") FIR/PINE LUMBER (ROUGH SAWN PREFERRABLE), TYP. 2 x 10 (ACTUAL 1.5" x 9.5") FIR/PINE LUMBER (ROUGH SAWN PREFERRABLE), TYP. 1 x 3 (ACTUAL .75" x 2.5") FIR/PINE LUMBER (ROUGH SAWN PREFERRABLE), TYP.
1'
2 x 4 (ACTUAL 1.5" x 3.5") FIR/PINE LUMBER (ROUGH SAWN PREFERRABLE), TYP.
3'
1'
FLUSH
°
92
FINISH GRADE
NOTES: 1. FASTENERS @ ROOFING TO BE NAILS 2. ALL OTHER FASTENERS SHALL BE SCREWS 2.1. LAG SCREWS PREFERRABLE WHERE VISIBLE FOR AESTHETIC - OVERSIZE IF POSSIBLE. 3. DETAIL IS DRAWN ASSUMING DIMENSIONAL LUMBER IS USED, HOWEVER, ROUGH SAWN LUMBER IS PREFERRED. IF ROUGH SAWN IS USED, ADJUST DIMENSIONS ACCORDINGLY (EXAMPLE: DIMENSIONAL 8 X 8 = 7.5" x 7.5" WHEREAS ROUGH SAWN 8 X 8 - 8" x 8") 4. POST TO BE SET IN POST HOLE; BACKFILL W/ CONCRETE OR CRUSHED ROCK.
LAKE BOREN PARK - KIOSK 2015/12/14
Kiosk Outreach Poster #2 3/2016
FINISH GRADE
SECTION
3'
ELEVATION
Online Survey #2
Public Meeting #2 3/10/2016
Site Analysis
3/2016
Concept Design Online Survey #3 5/2016
Kiosk Outreach Poster #3
Public Meeting #3 4/26/2016
5/2016
Infrastructure:
Park Core Amenities:
01 Cross Park Lighting
06 Newcastle Plaza (seat-walls, 30’ wide paving)
14 Beach Boardwalk
Lake Boren Connection
Park-wide
22 Canopy Walk Trestle
33 Lake Boren Promenade (5’ asphalt)
38 Site furnishings (benches, tables, bike racks, waste/recycling receptacles
30 Path around Parking
Wetlands A Wetland A boundary
31 Off-leash Area
16 Community Garden
24 Cattail Walk
32 Native/mitigation Planting
35 Promenade Deck
C Wetland C boundary
17 Shelter Improvements
25 Boardwalk to Learning Center
36 Lake Boren Stairs
D Wetland D boundary
26 Shelter (learning center)
37 Lake Boren Dock
07 Amphitheater (terraced with seat-walls & rock outcrops
10 Plaza Trellis
05 North Parking
18 Additional Tennis Court
34 Lake Boren Promenade Boardwalk
Wetlands Note: The lake, stream and wetlands and their associated buffers have been identified but not delineated in a Wetland/Stream Reconnaissance Report prepared by The Watershed Company and dated April 13, 2016. For the purposes of preparing the Master Plan, the lake, stream and wetland boundaries and associated buffers shown herein have been located approximately and should be used for general reference only.
B Wetland B boundary
23 Canopy Walk Span
08 Stage @ The Grove (covered) 09 Community Room(s)/Restrooms (3000 sf)
02 Bioretention/Stormwater facilities
15 Beach
The Boren Creek Collection
03 Parking (reconfigured to 54 stalls) 04 Parking & Drop-off (added 76 stalls)
E Wetland E boundary F Lake Boren
11 Entry Signs
19 Skate Spot
27 Boren Creek Path (5’ crushed rock)
12 Cross Park Promenade
20 Stone Garden
28 Boren Creek Stairs
G Boren Creek
13 North Sweep Boardwalk
21 Trees
29 Boren Creek Bridge
H Cumulative wetlands/stream/lake buffer
Waterline Trail
e SE h Av
9t
12 17
19
THE DRAFT MASTER PLAN CONCEPT IS AVAILABLE.
11 12 05 01
11
02
07
03
H
12 38
SE 84t
02
13
12
21
h Way
17
E
D
08
06 02
Lake Boren
21
10 04 09
02
H 14 16
02
INPUT KIOSK
Contact: Jeff Brauns JeffB@ci.newcastle.wa.us 425-649-4143 x124
Located in the park near the bathrooms & parking
INPUT SURVEY
20
18
38
30
15
Exampl
25
e Tag “My favor elements ite 20, & are 15, 33
22
H
http://sgiz.mobi/s3/ Lake-Boren-Park
28 31
H
A
26
F
32 32
36
24
22
34
27
C
37
F
ade
35
lan
23
29
H 32
22
Lake
Boren
Esp
33
B
Coal Creek
Parkway
Plan Inset partial build out of master plan without community room(s)/restrooms, underground stormwater vault, and expanded parking INSTRUCTIONS: We need your input on this DRAFT Master Plan concept. Please write your comments with making reference to specific element names or numbers as shown on the plan. For example, a comment could be: “My favorite elements are 15, 20 & 33.” Please also visit the online survey site using the URL below or by scanning the QR code. We are using this data to understand the level of support for various elements. Your input is being used to shape the Master Plan! SURVEY URL:
http://sgiz.mobi/s3/Lake-Boren-Park
Newcastle Town Hall 6/21/2016
30
* To see complete summary of public meetings, refer to Appendix Vol.1 C.
Master Plan Development
LAKE BOREN PARK Share your vision! 1. Grab a pen and paper tag. 2. Write down your favorite Lake Boren Park experiences, what you love most about the park or what you would most like to see here. 3. Pin your tag on the kiosk to share your vision.
Newcastle Cemetery Lake Boren
ek Park
e Coal Cr way
re. ion he vis re ur u a yo Yo are Sh ! 31
32
Kiosk Tag Summary â&#x20AC;&#x153;Keep as isâ&#x20AC;? (7%)
Total Comments Neutral (18%)
Pro-improvement (75%)
Top Improvements
0
15
30
Playground improvements or features Dog park Pool / splash park / wading pool -related Beach / swim dock / clean water -related Walking related: more paths and/or lit paths Vendor trucks, concessions, or vending machines Boat-access or launch related, or request for rentals More tennis courts or lighting for tennis courts Skate park Bathroom improvements General beautification (flowers, trees) Zipline Community garden Climbing wall or tower Fix dock Frisbee golf * To see complete summary of kiosk tags, please refer to Appendix Vol. B. 33
Public Survey #1 Summary This survey asked residents questions about the existing park, such as what are their favorite elements and activities.
34
* To see full survey results, please refer to Appendix Vol. B. 35
CONCEPT ‘A’ 01 ACCESSIBLE PATH CONNECTION 02 MINING PLAY/LEARNING AREA & LEVEL PLAY LAWN 03 NEWCASTLE PLAZA & FESTIVAL TENTS (EPHEMERAL) 04 OPPORTUNITY AREA (DOG PARK, SKATE PARK) 05 STAGE & AMPHITHEATER BOWL W/ OUTCROPS 06 ACCESSIBLE PRIMARY PATH NETWORK 07 FERN, MOSS & ROCK GARDEN 08 PARK ENTRANCE W/ PARKING 09 MAINTENANCE FACILITY SCREENING 10 REBUILT DOCK 11 TRESTLE BOARDWALK & NATURAL BEACH 12 RELOCATED STRUCTURE AND FOREST MEADOW
20
13 ACCESSIBLE SECONDARY PATH NETWORK 14 OUTCROP VIEWPOINT 15 NATURAL BEACH 16 OPPORTUNITY AREA (DOG PARK, SKATE PARK) 17 LAKESIDE PROMENADE 18 REBUILT DOCK 19 REBUILT DOCK PLATFORM 20 STAIR CONNECTION TO EXISTING CONCRETE STEPS 21 IMPROVED SHELTER AMENITIES 22 NATIVE PLANT RESTORATION AREA 23 RAIN GARDEN/SWALE
16
17
19
'C P W ON LA IT C N H EP SH PU T O BL A' I WN IC NC A SU LU S RV DE EY D 2
16
18
10
17
16
08
22
11
15
07
09
01
22
12
23
05
06
22
06
22
13
21
21
02
06
03
14
, ion ! vis ack ur b yo feed are nd Sh ea a id
01 06 13
04
SHARE YOUR VISION We’re here to share concepts and listen to your feedback/Ideas. Please leave your mark. 1. Grab a pen and paper tag/post-it. 2. Write down your thoughts on the concepts, what you love most about the park or what you would most like to see here. 3. Pin your tag/post-it on any poster
PUBLIC MEETING NO.2 2016/03/10
36
0
25’ 50’
100’
Public Survey #2 Summary Rank your top three favorite elements from Concept A. Rank Item Score Total Respondents 1 (17) Lakeside promenade 38 19 2 (5) Stage & amphitheater bowl with outcrops 38 17 3 (11) Trestle boardwalk & natural beach 36 17 4 (4) Opportunity area (dog park, skate park) 26 12 5 (2) Mining play/learning area & level play lawn 24 10 6 (10) Rebuilt dock 19 11 7 (6) Accessible primary path network 18 7 8 (8) Park entrance with parking 18 10 9 (13) Accessible secondary path network 17 10 10 (7) Fern, moss & rock garden 14 6 11 (15) Natural beach 14 8 12 (18) Rebuilt dock 14 7 13 (22) Native plant restoration area 11 7 14 (3) Newcastle plaza & festival tents (ephemeral) 11 5 15 (1) Accessible path connection 11 5 16 (16) Opportunity area (dog park, skate park) 10 6 17 (21) Improved shelter amenities 9 5 18 (14) Outcrop viewpoint 7 4 19 (19) Rebuilt dock platform 6 3 20 (12) Relocated structure and forest meadow 4 3 21 (23) Rain garden/swale 4 2 22 (20) Stair connection to existing concrete steps 3 2 23 (9) Maintenance facility screening 2 1
* To see full survey results, please refer to Appendix Vol. B. 37
CONCEPT ‘B’ 01 PARK ENTRANCE & CROSSWALK 02 ACCESSIBLE SECONDARY PATH NETWORK 03 ACCESSIBLE PRIMARY PATH NETWORK 04 ACCESSIBLE PATH CONNECTION 05 EXPANDED PARKING 06 RAIN GARDEN/SWALE 07 ACCESSIBLE RAMPED PATHWAY 08 EXPANDED SPORTS COURTS 09 UNDERGROUND STORMWATER VAULT 10 IMPROVED SHELTER AMENITIES 11 MINING PLAY/LEARNING TERRACES 12 HILLSIDE SLIDES
39
13 MINING ROCK SCRAMBLE 14 LEVEL PLAY LAWN 15 COMMUNITY CENTER 16 NEWCASTLE PLAZA & FESTIVAL TENTS (EPHEMERAL) 17 FOREST EDGE LAWN / COMMUNITY GARDEN 18 CANOPY WALK TRESTLE 19 ADVENTURE PATH 20 OUTDOOR LIVING ROOM STRUCTURE 21 FERN, MOSS & ROCK GARDEN 22 STONE STEPS 23 STAGE
36
24 AMPHITHEATER BOWL W/ OUTCROPS 25 MAINTENANCE FACILITY SCREENING
33
26 TURNAROUND PARK ENTRANCE W/ PARKING 27 FOREST ROOM 28 REBUILT DOCK 29 NATURAL SWIM BEACH 30 GATHERING AREA
38
31 NATIVE PLANT RESTORATION AREA 32 TRESTLE BOARDWALK
33
33 OPPORTUNITY AREA (DOG PARK, SKATE PARK) 34 CABLED BOAT CROSSING 37
'C P W ON LA IT C N H EP SH PU T O BL B' I WN IC NC A SU LU S RV DE EY D 2
35 NATURAL BEACH
36 LAKESIDE PROMENADE 37 REBUILT DOCK
34
33
38 REBUILT DOCK PLATFORM
39 STAIR CONNECTION TO CONCRETE STEPS
28
03
22
26
22
36
29
27
35
30
03
33
21
25
20
04
32
31
03
19
06
23
24
24
31
19
17
16
18
12
02
31
14
10
15
13
19
11
, ion ! vis ack ur b yo feed are nd Sh ea a id
06
04 03
07 05
08 09
02 31
01
SHARE YOUR VISION We’re here to share concepts and listen to your feedback/Ideas. Please leave your mark. 1. Grab a pen and paper tag/post-it. 2. Write down your thoughts on the concepts, what you love most about the park or what you would most like to see here. 3. Pin your tag/post-it on any poster
PUBLIC MEETING NO.2 2016/03/10
38
0
25’ 50’
100’
Public Survey #2 Summary Rank your top three favorite elements from Concept B. Rank Item Score Total Respondents 1 (29) Natural swim beach 33 15 2 (8) Expanded sports courts 24 9 3 (36) Lakeside promenade 23 12 4 (32) Trestle boardwalk 23 13 5 (15) Community center 20 9 6 (33) Opportunity area (dog park, skate park) 20 8 7 (11) Mining play/learning terraces 18 8 8 (19) Adventure path 16 9 9 (5) Expanded parking 6 8 10 (24) Amphitheater bowl with outcrops 16 8 11 (12) Hillside slides 14 7 12 (23) Stage 13 6 13 (4) Accessible path connection 12 5 14 (9) Underground stormwater vault 9 5 15 (3) Accessible primary path network 8 3 16 (2) Accessible secondary path network 8 5 17 (13) Mining rock scramble 7 4 18 (26) Turnaround park entrance with parking 7 5 19 (31) Native plant restoration area 7 4 20 (21) Fern, moss & rock garden 6 3 21 (10) Improved shelter amenities 6 3 22 (28) Rebuilt dock 5 3 23 (37) Rebuilt dock 4 2 24 (17) Forest edge lawn / community garden 4 2 25 (6) Rain garden/swale 4 2 26 (34) Cabled boat crossing 3 3 27 (18) Canopy walk trestle 3 1 28 (39) Stair connection to concrete steps 3 2 29 (20) Outdoor living room structure 3 2 30 (16) Newcastle plaza & festival tents (ephemeral) 2 1 31 (25) Maintenance facility screening 2 1 32 (30) Gathering area 1 1 33 (14) Level play lawn 1 1 34 (38) Rebuilt dock platform 1 1
* To see full survey results, please refer to Appendix Vol. B. 39
11
02
02
H
30
A
38
28
10
16
09
Plan Inset partial build out of master plan without community room(s)/restrooms, underground stormwater vault, and expanded parking
ay th W
02
04
02
02
C
21
18
F
31
29
32
32
21
22
27
26
24
20
38
Waterline Trail
32 Native/mitigation Planting
F
12
11
E
E
eS Av
14
05
H
22
07
08
32
23
B
22
15
y k Parkwa e Coal Cre
25
H
D
13
33
Lake Boren
H
37
35
E Wetland E boundary
eB Lak
ore
36
Wetlands Note: The lake, stream and wetlands and their associated buffers have been identified but not delineated in a Wetland/Stream Reconnaissance Report prepared by The Watershed Company and dated April 13, 2016. For the purposes of preparing the Master Plan, the lake, stream and wetland boundaries and associated buffers shown herein have been located approximately and should be used for general reference only.
ad e an spl nE
34
H Cumulative wetlands/stream/lake buffer
G Boren Creek
F Lake Boren
D Wetland D boundary
C Wetland C boundary
B Wetland B boundary
A Wetland A boundary
Wetlands
37 Lake Boren Dock
12
h 9t
38 Site furnishings (benches, tables, bike racks, waste/recycling receptacles
Park-wide
36 Lake Boren Stairs
35 Promenade Deck
34 Lake Boren Promenade Boardwalk
33 Lake Boren Promenade (5’ asphalt)
Lake Boren Connection
AN PU I BL NC IC LU SU DE RV D W EY IT 3 H
PL
27 Boren Creek Path (5’ crushed rock)
26 Shelter (learning center)
25 Boardwalk to Learning Center
31 Off-leash Area
PUBLIC MEETING NO.3 2016/04/26 CONCEPT PLAN
17
12
21 Trees
13 North Sweep Boardwalk
06
20 Stone Garden
12 Cross Park Promenade
03
19 Skate Spot
11 Entry Signs
01
18 Additional Tennis Court
10 Plaza Trellis
05 North Parking
12
29 Boren Creek Bridge
17 Shelter Improvements
09 Community Room(s)/Restrooms (3000 sf)
04 Parking & Drop-off (added 76 stalls)
17
28 Boren Creek Stairs
16 Community Garden
08 Stage @ The Grove (covered)
03 Parking (reconfigured to 54 stalls)
19
23 Canopy Walk Span
15 Beach
07 Amphitheater (terraced with seat-walls & rock outcrops
02 Bioretention/Stormwater facilities 24 Cattail Walk
22 Canopy Walk Trestle
06 Newcastle Plaza (seat-walls, 30’ wide paving)
30 Path around Parking
The Boren Creek Collection 14 Beach Boardwalk
Park Core Amenities:
01 Cross Park Lighting
Infrastructure:
40
SE 84
Public Survey #3 Summary Rank your top three favorite elements from Draft Master Plan Concept. Rank Item Score 1 (7 & 8) Amphitheater & Stage 113 2 (15) Beach 86 3 (31) Off-leash Area 72 4 (4) Expanded Parking 51 5 (14) Beach Boardwalk 45 6 (22 & 23) Canopy Walk Trestle & Span 44 7 (21) Trees 41 8 (37) Lake Boren Dock 27 9 (17) Picnic Shelter Improvements 27 10 (33) Lake Boren Promenade 26 11 (5) North Parking 21 12 (13) North Sweep Boardwalk 21 13 (12) Cross Park Promenade 19 14 (18) Additional Tennis Court 18 15 (34) Lake Boren Boardwalk 17 16 (27) Boren Creek Path 14 17 (9) Community Room(s) 14 18 (26) Shelter (Learning Center) 12 19 (19) Skate Spot 11 20 (25) Boardwalk to Learning Center 10 21 (24) Cattail Walk 9 22 (16) Community Garden 8 23 (6) Newcastle Plaza 8 24 (29) Boren Creek Bridge 8 25 (36) Lake Boren Stairs 7 26 (35) Promenade Deck 7 27 (10) Plaza Trellis 5 28 (20) Stone Garden 4 29 (30) Path around Parking 2 30 (28) Boren Creek Stairs 0
* To see full survey results, please refer to Appendix Vol. B. 41
Index of Appendices Appendix Vol. 1
A: Master Planning Project Schedule
B: Public Survey Results
C: Kiosk Tag Results/Summary
Appendix Vol. 2
D: Lake Boren Park, Permitting Memorandum
E: Lake Boren Park, Wetland/Stream Reconnaissance Report
Appendix Vol. 3
F: SEPA Document(s)
Appendix Vol. 4
G: Public Meeting Notes
Appendix Vol. 5
42
H: City Council Resolution