Stakeholder Register AIT Waste Water Treatment System
AIT Waste Water Treatment Facility: Stakeholder Register
Document History Version
Description
Date
Author
Checked
Number
1
Original
31/01/13
i
NMcH, SP
LM
AIT Waste Water Treatment Facility: Stakeholder Register
Table of Contents Document History............................................................................................................................... i 1.0
Stakeholder Register ............................................................................................................. 1
Sponsor Acceptance ........................................................................................................................... 2
ii
AIT Waste Water Treatment Facility: Stakeholder Register
1.0
Stakeholder Register
Date:
31/03/13
Project Name:
Waste Water Treatment Plant
Project Phase:
Initiation Stage
Name of Stakeholder
Role in Project AIT as the client will inform the consultant what they require. The consultant
AIT
will communicate with AIT as the project develops.
Student Union
Inform students of works being carried out on site.
Athlone Town
The Town Council will inform Westmeath C.C that AIT will be discharging the
Council Westmeath County Council Department of Education Department of Finiance EPA
treated effluent into the mains. Westmeath C.C will have to give permission to AIT to discharge the treated effluent into the mains. The Department of Education will have to provide a grant for the Waste Water Treatment Plant. The Department of Finance will have to provide money towards the Waste Water Treatment Plant. Treatment of the Waste Water leaving the plant. The suppliers role in the project will be to provide a quality product and that
Suppliers Local Residents TNLS Consultancy
it will be available to provide assistance if needed on the project. Obtain permission from the local residents so the WWTP can proceed. TNLS will provide info to AIT about what is happening on site. Get in contact with the other stakeholders and maintain communication with them for the duration of the project.
1
AIT Waste Water Treatment Facility: Stakeholder Register
Sponsor Acceptance
Approved by the Project Sponsor:
____________________________________________ Project Sponsor: AIT
2
Date: _____________________