2018 ANNUAL STREET MAINTENANCE



2017 ASM RECAP

• • • •


CURB & SIDEWALKS

Remove and Replace Existing Concrete Sidewalk

SY

Remove & Replace Barrier Free Ramp

EA SY SY

Block Sod Along Disturbed Roadways/Sidewalks Remove and Replace Curb & Gutter 6"x6" curb w/ 12" gutter

2,200 4 980 1,000


CRACK SEALING

Crack Seal Concrete - Grey Sealant (includes routing & backing cracks prior to sealing)

LF

38,740


PROPOSED 2018 ANNUAL STREET MAINTENANCE       

March 27th – Council Budget Work Shop March 30th & April 6th, April 13th – Advertise April 20th – Deadline April 23th – Close Bids May 1st – Council Approval May 11th – Pre-con May 14th – Notice to Proceed


 CONCRETE PANEL REPLACEMENT  CURBS & SIDEWALKS  CONCRETE LIFTING  CRACK SEAL  CHIP SEAL  ASPHALT REPAIR & OVERLAY


















ASPHALT REPAIR & OVERLAY



ASPHALT REPAIR & OVERLAY

 LEVEL UP – UNEVEN AREAS  CRACK SEAL MAJOR CRACKS  APPLY TACK COAT  ADJUST ASPHALT AT DRIVEWAYS AS NEEDED  APPLY 2” OVERLAY  BACKFILL EDGES