Case Study
Case Study 3 57 - 63 Church Road Wimbledon
Client Marchmont Project Architect Helme & Partners Project Period 12 weeks Project Value £785,000
We secured the contract for a design and build project for the interior and exterior refurbishment of an office development in the heart of Wimbledon Village.
The project involved the complete strip out of internal walls and finishes over three floors, including the re-fit of new finishes to remodel these offices into bright, fresh and open spaces.
We were also involved in the M&E design for the project, including new heating, lighting and AC installation.