January 2025 Kaufman County Transportation Report

Page 1


FM 548

CSJ: 1091-02-025; 2588-01-025

Limits: from IH 20 to FM 1641

Project Description:

reconstruct FM 740 and FM 548 to 4lane divided urban roadways; bridge widening at Mustang Creek crossing

Estimated Construction Cost: $88,634,701

Funding: *

Commissioner: Skeet Phillips, Precinct 2

Engineer & Key Contact: Jacobs, Abe Bekele

TxDOT Project Manager: Jordan Mrayyan

Schematic Approval: June 2025

Environmental Approval: December 2025

ROW Acquisition Complete: *

Utility Relocations Complete: *

100% Plans:

Ready to Let Date:

Start Date:

Current Activity:

• Design: Updated schematic and cross sections were submitted to TxDOT for review on December 16, 2024. Atkins to submit revised schematic and cross sections to TxDOT and ITS for review in early February 2025.

• Bi-weekly coordination meetings with TxDOT are ongoing.

• ROW: Revised proposed ROW file was submitted to TxDOT for coordination on December 16, 2024.

• Environmental: Jacobs continued effort toward preparation of environmental reports and responding to TxDOT comments to same. Thirteen environmental reports have been approved to date. Notice Affording an Opportunity for a Public Hearing was approved by TxDOT. Anticipate publication of NAOPH in February 2025, after resolution of SUE investigation of water line.

• Utility Coordination: SUE exhibits and updated utility coordination were submitted for review on December 15, 2024. Water line SUE data and updated SUE sheets expected at the end of January 2025.

FM 548 North: Phase I

CSJ: 2588-01-022

Limits:

Estimated Construction Cost:

Funding:

Project Description:

From north of US Highway 80 to Windmill Farms Blvd.

$132,752,619

Schematic Re-Approval: December 28, 2018

Environmental Clearance: July 3, 2019

Widen existing 2-lane, undivided facility to a 4- to 6-lane, divided facility 100% Plans: December 2024

Commissioner: Skeet Phillips, Precinct 2 Ready to Let Date: March 2025

Engineer & Key Contact: Westwood, Mark Zoellner, Mark Schluter Let Date: March 2025

TxDOT Project Manager: Gutema Gebrial

Current Activity:

• PS&E: Westwood submitted the 100% plans to TxDOT. TxDOT to submit plans to Design Division for letting.

• Utilities:

o AT&T: Relocations underway.

o Atmos: Relocations underway.

Construction Start: *

o Farmers Electric Co-Op: Relocations underway. Anticipate clearance at the end of February 2025.

o City of Forney: Clear

o High Point WSC: Relocations underway.

o NTMWD: Clear

o Oncor: Relocations underway. Anticipate completion in February 2025.

o Peoples Telephone Co-Op: Relocations underway.

• Construction: Project will let for construction in March 2025.

CSJ:

FM 548 North: Phase II

2588-01-017 (Kaufman County)

2588-02-008 (Rockwall County)

Limits: From Windmill Farms Blvd. to SH 205

Estimated Construction Cost:

Funding:

$94,669,035

$77,233,537: Kaufman County segment

$17,435,498: Rockwall County segment

$19,919,759 : CAT 2

$8,448,796: Kaufman County segment

$11,470,963: Rockwall County segment

Project Description: Widen existing 2-lane, undivided facility to a 4 to 6-lane, divided facility

Commissioner: Skeet Phillips, Precinct 2

Schematic Re-Approval: December 28, 2018

Environmental Clearance: July 3, 2019

ROW Acquisition Completed: August 2022

Utility Relocations Complete: July 2025

100% Plans: February 2025

Ready to Let Date: July 2025

Engineer & Key Contact: Burns & McDonnell, Tony Schmitt Let Date: *

TxDOT Project Manager: Gutema Gebrial

Construction Start: *

Current Activity:

• PS&E: Burns & McDonnell continues working toward completion of 100% plans and updating plans to 2024 TxDOT Specifications.

• Utilities: The status of utilities in conflict is below:

o Atmos: Relocation plans approved

o City of Dallas: Finalizing utility agreement. Pending construction start date.

o FEC: Various segments of relocation plans approved; various segments pending.

o High Point SUD: Relocation plans approved. Relocations underway.

o Spectrum: Plans approved. Pending FEC relocations.

o Sprint: Analyzing plan for relocation.

o Suddenlink (Optimum): Plans approved. Pending FEC relocations.

CSJ: 0095-04-069

US 80/SH 205/FM 148

Schematic Approval: January 26, 2018

Limits: US 80 and SH 205/FM 148 intersection Environmental Clearance: August 23, 2018

Construction Cost: $15,839,362

Funding: $9,349,949 : CAT 6

Project Description:

Intersection improvements to increase the capacity and improve safety at the intersection and the adjacent railroad crossing on FM 148 south of US 80, including full traffic signalization

Commissioner: Kelly Lane, Precinct 3

ROW Acquisition Complete: October 2019

Utility Relocations Complete: October 2022

100% Plans: December 10, 2021

Engineer & Key Contact: Othon, Jeff Love Construction

TxDOT Project Manager: Lane Selman

Current Activity:

• Construction: The project was awarded to Sterling Delaware Holding Company, Inc. with a low bid of $15,839,362.17, at 23.12% over engineer’s estimate. There are 504 working days and 24 months of barricades. See attached TxDOT construction report.

TxDOT Monthly Project Report for Kaufman County

Date of report: January 8, 2025

Report prepared by: Cody Jolley, P.E.

Control: 0095-04-069, ETC. Limits: Intersection SH205/FM148/US80

Project: CM2022(384)

Highway: US 80

Contractor: Sterling Delaware Holding Company, Inc.

TxDOT Area Engineer: Lane Selman, P.E.

TxDOT Assist. Area Engineer: Nic Wadlington, P.E.

TxDOT Project Manager: Chris Bruner

Contractor’s Superintendent: Kent Bergthold

Date Work Began: October 3, 2022

Anticipated Completion Date: March 28, 2025

Phone: (972) 962-3617

Phone: (972) 962-3617

Phone: (972) 962-3617

Phone: (972) 963-0262

Current activities: Asphalt pavement Flexbase. Concrete curb and gutter. Concrete paving.

Narrative description of last month’s activities: Driveways. Asphalt removal. Concrete removal. Mulch and block sod. Asphalt pavement.

Narrative description of activities planned for next month: Asphalt pavement. Flexbase. Concrete curb and gutter. Concrete paving.

Traffic issues: None

Plans for changes in traffic patterns: None

Item(s) of work currently controlling project completion: None

Other items of significance: None

FM 148 Bypass

CSJ: 0751-05-001; 0197-03-078

Limits: From US 175 to south of FM 3039

Construction Cost:

$60,049,999

Funding: $38,777,994

CAT 2: $33,777,994

CAT 3: $5,000,000

Project Description:

Construct new 2-lane undivided facility; add connection to proposed US 175 frontage road project

Current Activity:

• Utilities: With the exception of utilities that will complete relocations at the FM 148 Bypass/US 175 intersection, if necessary, during the US 175 South Frontage Road construction, utilities are clear of construction.

• Construction: The project was awarded to Granite Construction Company with a low bid of $60,049,998.99 at 3.74% above the engineer’s estimate. There are 35 months of barricades and 735 working days. See attached TxDOT construction report.

Schematic Approval: June 30, 2017

Environmental Clearance: April 26, 2019

ROW Acquisition Completed: November 2020

Utility Relocations Completed: February 2023

100% Plans: April 28, 2023

Construction Completion: November 2025

Commissioner: Tommy Moore, Precinct 4
Ready to Let Date: March 2023
Engineer & Key Contact: Halff Associates, David Burkett Let Date: June 27, 2023
TxDOT Project Manager: Lane Selman

TxDOT Monthly Project Report for Kaufman County

Date of report: January 8, 2025

Report prepared by: Cody Jolley, P.E.

Control: 0197-03-078 Limits: 2.3 miles west of FM 148 Bypass to East of FM 148 Bypass Project: F 2023(704)

Highway: FM 148

Contractor: Granite Construction Company

TxDOT Area Engineer: Lane Selman, P.E.

TxDOT Assist. Area Engineer: Nic Wadlington, P.E.

TxDOT Project Manager: Jacob Self

Contractor’s Superintendent: Brad Tyrer

Date Work Began: October 2, 2023

Anticipated Completion Date: November 6, 2025

Phone: (972) 962-3617

Phone: (972) 962-3617

Phone: (972) 962-3617

Phone: (972) 358-3712

Current activities: Flexbase. Conduit. Constructing concrete traffic rail. Excavation/Embankment.

Lime treatment for subgrade. Constructing asphalt pavement (westbound main lanes). Temporary grass seeding (FM 148). Lime treatment for subgrade.

Narrative description of last month’s activities: Flexbase. Concrete curb and gutter. Temporary wall construction. Excavation/Embankment. Lime treatment for subgrade. Electrical services. Conduit.

Narrative description of activities planned for next month: Construct concrete traffic barrier. Electrical installation. Temporary detour construction. Prepare for traffic switch (no date currently set). Striping. Excavation/Embankment. Lime treatment for subgrade. Installing drainage.

Traffic issues: None

Plans for changes in traffic patterns: None

Item(s) of work currently controlling project completion: None

Other items of significance: None

FM 1641

CSJ: 1217-01-019; 2588-01-020

Limits: From FM 548 to FM 148

Estimated Const. Cost:

Funding:

$90,661,674 -019: $87,462,145 -020: $3,199,529

$1,000,000

-019: $500,000: CAT 7 -020: $500,000: CAT 7

Project Description: Widen to a 4-lane divided (6-lane ultimate) urban facility

Commissioner: Skeet Phillips, Precinct 2

Engineer & Key Contact: LTRA, Massoud Manesh

TxDOT Project Manager: Chaikou Bah

Schematic Re-Approval: April 26, 2021

Environmental Clearance: August 31, 2021

ROW Acquisition Completed: September 2023

Utility Relocations Complete: December 2025

100% Plans: February 2025

Ready to Let Date: December 2025

Current Activity:

• PS&E: LTRA continued conversion of bid items to 2024 TxDOT Specifications, addressing TxDOT comments to 95% plan set, and working toward completion of final plan set. Anticipate submittal of final plan set to TxDOT in early February 2025.

• Utilities: Utilities that are clear: Gulf South Pipeline.

• Status of utilities in conflict is below.

o AT&T: Relocations underway. Pending clearance date

o Atmos: Pending design approval.

o Forney: Relocations underway.

o Oncor: Relocations underway.

o NTMWD: Working on relocation plans.

o Peoples Telephone: Relocation plans approved.

o Suddenlink (Optimum): Needs TVEC pole plans for relocation.

o Talty SUD: Working to acquire easements.

o TVEC: Final design in progress; pending relocation start.

CSJ: 1092-01-021; 1092-01-026

Limits: From US 175 to FM 548

FM 741

Schematic Approval: July 20, 2022

Environmental Clearance: March 28, 2023

Project Description: Widen and reconstruct from a 2-lane rural undivided to a 4/6-lane urban divided ROW Acquisition Complete: September 2027

Estimated Constr. Cost: $211,463,549

Funding: $10,000,000 CAT 7: -026

Commissioner: Skeet Phillips, Precinct 2 and Tommy Moore, Precinct 4

Engineer & Key Contact: HNTB, Kyle Riley

TxDOT Project Manager: Solomon Robelie

Current Activity:

• PS&E: The PBLR was approved by Bridge Division on November 8, 2023.

• HNTB completed the 95% PS&E plan set and submitted to TxDOT for review on September 20, 2024. Comment resolution meeting held on December 14, 2024

• TxDOT is negotiating with HNTB regarding a supplemental work authorization to divide the project into two packages: CSJ: 1092-01-026 will begin at US 175 and terminate based on available construction funding; CSJ: 1092-01-021 will begin at the end of CSJ: -026 and continue to FM 548; exact limits to be determined

• ROW: There are 124 parcels to acquire. There are: 1 parcel in appraisal, 1 parcel in negotiations, 25 parcels in ED, and 97 parcels in possession ROW acquisition efforts continue to be on hold due to District budgetary constraints; however, TxDOT was able to close some parcels that were with the title company.

Utility Relocations Complete: September 2029

Ready to Let Date: September 2029

Let Date: *

Construction Completion: *

CSJ: *

Limits: from IH 20 to US 80

Helms Trail

Schematic Approval: March 2025

Environmental Clearance: May 2025

Project Description: widen from 2-lane rural to 4-lane divided urban ROW Acquisition Complete:

Estimated Construction Cost: $38,250,000

Utility Relocations Complete:

Commissioner: Skeet Phillips, Precinct 2 Ready to Let Date:

Engineer & Key Contact: Dannenbaum, Donald Stephanik

TxDOT Project Manager:

Current Activity:

• Design: Dannenbaum submitted the pre-100% schematic on January 3, 2025. ITS is reviewing schematic.

• Dannenbaum continued drainage efforts. Dannenbaum continues efforts toward draft drainage report.

• Monthly coordination meeting with Dannenbaum and ITS held on December 4, 2024.

• SUE: Preliminary SUE efforts are complete.

• Environmental: Antiquities permit application and curation agreement have been approved

• Environmental technical reports are in progress.

CSJ:

SH 205 South

0451-02-028 (Kaufman County)

0451-01-053 (Rockwall County)

Limits: From US 80 to north of FM 549

Project Description: Widen from 2-lane rural to 4-lane urban divided with allowance for ultimate 6 lanes

Estimated construction cost:

Funding:

$249,616,163 -028: $113,757,508 -053: $137,161,345

$261,113,888

$15,927,757: CAT 1

$44,046,699: CAT 2

$201,139,432: CAT 4

Schematic Approval: July 3, 2018 (-028) May 1, 2019 (-053)

Environmental Approval: Environmental Re-eval: April 12, 2019 December 22, 2021

ROW Acquisition Completed: July 2023

Utility

100% Plans: August 2024

Engineer: TxDOT Ready to Let Date: -028: December 2025 -053: September 2025

TxDOT Contact: Suja Mathew Let Date: *

Current Activity:

• PS&E: TxDOT completed the 100% PS&E plan set, including the updates to the 2024 TxDOT Specifications, for the CSJ -028 (Kaufman County) segment.

• TxDOT completed the 100% PS&E plan set including the updates to the 2024 TxDOT Specifications, for the CSJ -053 (Rockwall County) segment

• Utilities: Status of -028 utilities in conflict:

o AT&T: Pending splicing.

o Atmos: Relocation plans approved. Pending start of relocations.

o Dallas Water Utilities: Working with TxDOT on utility agreement.

o FEC: Pending start of relocations in several sections; relocations underway in one section.

o High Pint WSC: Working to acquire easements. Pending design completion.

o NTMWD: Clear

o Oncor: Clear

o Sprint: Clear

o Terrell: Pending start of relocations.

I-20 Frontage Roads – Terrell

Project Description: Add continuous frontage roads ROW Acquisition Completed: October 2023

Construction

Current Activity:

• PS&E: LTRA is addressing comments from the 95% plan set and is working toward completion of final plan set

• PBLR was approved by Bridge Division.

• Utilities: Utility coordination kick-off meeting to be held. Status of utilities in conflict below:

o AT&T: Reviewing TxDOT plans and conflict matrix.

o Atmos: Reviewing TxDOT plans and conflict matrix.

o Enterprise: Reviewing TxDOT plans and conflict matrix.

o Oncor: Reviewing TxDOT plans and conflict matrix.

o Oneok: Reviewing TxDOT plans and conflict matrix.

o Optimum: Reviewing TxDOT plans and conflict matrix.

o Rose Hill SUD: Consultant reviewing TxDOT plans and conflict matrix.

o City of Terrell: Reviewing TxDOT plans and conflict matrix.

o TVEC: Consultant reviewing TxDOT plans and conflict matrix.

o Zayo: Reviewing TxDOT plans and conflict matrix.

TxDOT Project Manager: Marlena Kelly

I-20 Frontage Roads – Kaufman

CSJ: 0095-14-036

Limits: From west of FM 741 to Big Brushy Creek

Project Description:

Estimated

Engineer & Key Contact:

Schematic Approval: January 31, 2019

Environmental Approval: April 10, 2020

Current Activity:

• PS&E: WSB is reviewing and responding to 60% plan set comments and working toward completion of the 95% plan set Anticipate submittal of the 95% plan set in February 2025.

• H&H report and Preliminary Bridge Layout approved at the TxDOT District. Submitted to TxDOT Austin for review on March 25, 2024. District is discussing comments to PBLR with Bridge Division.

• ROW: There are 84 parcels to acquire. There are: 1 parcel in negotiations and 83 parcels in possession. ROW acquisition is on hold due to District budgetary constraints.

CSJ:

US 80 Widening

0095-03-080; -085

Limits: From Lawson Road to FM 460

Project Description:

Reconstruct and widen from 4 to 6 main lanes and reconstruct 2/4-lane discontinuous to 4/6-lane continuous frontage roads

Estimated Construction Cost: $128,902,801

$146,274,571

Funding:

$139,443,588: CAT 4; $1,882,263: CAT 6

$3,944,904: CAT 10; $1,003,816: CAT 11

Schematic Approval: August 24, 2018

Environmental Approval: April 13, 2020

ROW Acquisition Completed: February 2022

Utility Relocations Complete: June 2023

100% Plans: March 2022

Engineer & Key Contact: Halff Associates, Jeremy McGahan Let Date: June 29, 2022

TxDOT Project Manager: Lane Selman

Construction Completion: September 2026

Current Activity:

• Construction: The project let on June 29, 2022. The project was awarded to Webber, LLC, with a low bid of $128,902,801.08, at 7.40% above engineer’s estimate. There are 42 months of barricades and 1,086 working days. See attached TxDOT construction report.

TxDOT Monthly Project Report for Kaufman County

Date of report: January 8, 2025

Report prepared by: Cody Jolley

Control: 0095-03-080 Limits Lawson Road to FM 460

Project: F 2022(793)

Highway: US 80

Contractor: Webber, LLC

TxDOT Project Manager: Chris Bruner

Contractor’s Superintendent: Robert Cox

Contractor’s Superintendent: Javier Zubillaga

Date Work Began: April 4, 2023

Anticipated Completion Date: September 30, 2026

Phone: (972) 962-3617

Phone: (214) 406-9600

Phone: (346) 224-6877

Current activities: Embankment. Flexbase. Excavation. Bridge panels. Drill shafts. Columns. Caps. Beams. Asphalt.

Narrative description of last month’s activities: Embankment. Flexbase. Excavation Bridge panels. Drill shafts. Columns. Caps. Beams. Asphalt.

Narrative description of activities planned for next month: Embankment/Excavation. Flexbase. Drill shafts. Columns. Caps. Beams. Bridge deck Trinity River. Concrete curb and gutter. Asphalt paving.

Traffic issues: None

Plans for changes in traffic patterns: None

Item(s) of work currently controlling project completion: None

Other items of significance: None

US 80/Spur 557 (FM 460 to IH 20)

CSJ: 0095-03-106; 0095-04-076; 0495-01-081

Limits: From FM 460 to IH 20

Project Description: Widen and add lanes

Estimated Construction Cost: $1,407,562,206

Funding: *

Schematic Approval: December 2023

Environmental Approval: April 3, 2024

ROW Acquisition Complete: March 2028

Utility Relocations Complete: March 2030

100% Plans: *

Engineer & Key Contact: * Ready to Let: March 2030

Current Activity:

• Environmental: A public hearing was held on February 8, 2024, in Forney. Finding of No Significant Impact (FONSI) was issued on April 3, 2024.

• PS&E: Awaiting TxDOT determination of priorities and next steps to advance project to PS&E phase.

TxDOT Project Manager: Doreen Choo

CSJ: 0918-11-109

Outer Loop

Schematic Approval: May 2025

Limits: From SH 205 to FM 148 Environmental Approval: November 2025

Project

Engineer

Current Activity:

• Design: HDR continues coordination with project stakeholders. HDR also continues coordination with TxDOT, Halff Associates (Rockwall County Outer Loop project), NCTCOG, and ITS.

• HDR submitted the 90% schematic to TxDOT for review on October 11, 2024. Schematic comments provided by TxDOT; HDR is reviewing and addressing.

• Revised IAJR memo submitted on October 31, 2024.

• Environmental: TxDOT has approved this project for an EA in lieu of an EIS Environmental technical reports continue. Two environmental technical reports have been approved to date; twelve reports are in progress.

• Other: Project website is available at: https://kaufmanouterloop.com

FM 740

CSJ: 2249-01-009; 1091-01-023

Limits: from Kaufman/Rockwall County Line to Ranch Road

Project Description: reconstruct FM 460 and FM 740 to 4lane (6-lane ultimate) divided urban roadways

Schematic Approval: August 2025

Environmental Approval: June 2026

Current Activity:

• Design: Atkins is addressing TxDOT comments to 90% schematic.

• Atkins continued drainage efforts and working on hydraulic model and evaluation of mitigation for detention pond layouts

• Atkins continued updating forecasts and providing recommendations for all intersections based on traffic analysis.

• Coordination meetings with Atkins, TxDOT, and ITS are ongoing.

• Atkins continues preparing for public meeting. Second public meeting is tentatively scheduled for March 6, 2025.

• ROW: ROW footprint is being finalized.

US 175 Grade Separations – Kemp

CSJ: 0197-05-063

Limits: from Business US 175 to FM 1895

Project Description: construct interchange at BUS 175 and FM 1895

Estimated Construction Cost: $89,486,203

Funding: *

Commissioner: Tommy Moore, Precinct 4

Schematic Approval: November 2023

Environmental Approval: November 26, 2024

ROW Acquisition Complete: NA

Utility Relocations Complete: *

100% Plans: *

Ready to Let Date: *

Engineer & Key Contact: Halff, Melanie Cleavelin Let Date: *

TxDOT Project Manager: Liang Ding

Current Activity:

• Environmental: Project was environmentally cleared on November 26, 2024.

• Design: Halff Associates is preparing a supplemental agreement to advance project to PS&E phase.

Construction Start: *

CSJ:

US 175 Safety Improvements – Kaufman

0197-04-086; 0196-04-087

Limits: from 0.5 miles south of SH 34 to Fair Road

Project Description: relocate existing crossovers, construct U-turns and deceleration lanes

Estimated Construction Cost: $8,911,637

Funding:

$8,773,402

$2,788,596: CAT 8

$5,984,806: CAT 11

Schematic Approval: NA

Environmental Approval: December 2023

ROW Acquisition Complete: NA

Utility Relocations Complete: NA

Final Plans: May 2024

Commissioner: Terry Crow, Precinct 1 Ready to Let Date: August 2024

Engineer & Key Contact: Quiddity, David Unger

TxDOT Project Manager: Lane Selman

Current Activity:

• Construction: Project let for construction on August 2, 2024. The project was awarded to Granite Construction Company, with a low bid of $12,103,561.02, at 0.92% below engineer’s estimate. There are 150 working days and 10 months of barricades. Construction began on December 4, 2024. See attached TxDOT construction report.

Construction Completion: February 2026

TxDOT Monthly Project Report for Kaufman County

Date of report: January 8, 2025

Report prepared by: Cody Jolley

Control: 0197-04-086

Project: F 2B24 (336), ETC.

Limits: US 175 – west of SH 34 to south of FM 153

Highway: US 175

Contractor: Granite Construction Company

TxDOT Project Manager: Jason Hyde

Contractor’s Superintendent: Ben Simpson

Date Work Began: December 4, 2024

Anticipated Completion Date: February 2026

Phone: (972) 962-3617

Phone: (214) 254-6503

Current activities: Mobilization. Place project signs. Prepare ROW for construction.

Narrative description of last month’s activities: Mobilization. Prepare ROW for construction.

Narrative description of activities planned for next month: Construct temporary detours. Prepare for Phase 1 traffic shift (no date set currently).

Traffic issues: None

Plans for changes in traffic patterns: None

Item(s) of work currently controlling project completion: None

Other items of significance: None

SH 34-US 175 Connector Road

CSJ: NA

Roadway No. 1: south of US 34 to new Roadway No. 2

Limits:

Project Description:

Roadway No. 2: southwest of US 175 to new Roadway No. 1

Construction of new 2-lane (4-lane ultimate) divided (Roadway No. 1) and new 2-lane (4-lane ultimate) undivided (Roadway No. 2) connection roads for new Kaufman County justice center

Construction Cost: $3,270,425

Schematic Approval: NA

Environmental Approval: NA

ROW Acquisition Complete: *

Funding: 2019 County Bond Funds 100%

Commissioner: Terry Crow, Precinct 1

Engineer & Key Contact: TNP, Matt Atkins Construction

Current Activity:

• Construction: Pavecon Public Works, LP was the lowest bidder, with a bid of $3,450,477.70. The county awarded the project to Pavecon on December 19, 2023 A pre-construction meeting was held on February 9, 2024. Construction began on March 14, 2024. See attached construction report.

TxDOT Project Manager: NA

US 175 Feasibility Study

CSJ/Project ID: A00190822

Limits:

Project Description:

Estimated Construction Cost:

From west of FM 1389 (Kaufman County line) to east of SH 198 (Henderson County line)

Feasibility study to investigate capacity improvements including main lanes expansion and addition of continuous frontage roads and new interchanges

Engineer & Key Contact: BGE, Hossein Hosseiny

Schematic Approval:

Environmental Approval: *

ROW Acquisition Complete:

Current Activity:

• Design: BGE continues developing design with an urban typical section throughout the county to minimize ROW impacts.

• Meeting to present design concepts and impacts to TxDOT Dallas District was held on December 18, 2024.

• BGE is preparing and analyzing an urban section for the corridor and comparing impacts.

• BGE is updating presentation to outline design concepts and impacts. BGE will meet with TxDOT on February 10, 2025, to present findings.

Glossary of Acronyms

• AADT – Annual Average Daily Traffic

• AFA – Advanced Funding Agreement

• ARPA – Archeological Resources Protection Act

• ASED – Annual Scope & Estimate Documentation

• CE – Categorical Exclusion (environmental clearance process for projects that do not involve significant environmental impacts)

• CLOMR – (FEMA’s) Conditional Letter of Map Revision

• Conformity – Federal requirement in nonattainment areas to conduct air quality analysis on projects, programs, and policies identified in transportation plans, transportation improvement programs, federally funded projects, or projects requiring federal approval

• CSJ – (TxDOT’s) Control Section Job Number

• EA – Environmental Assessment

• ED – Eminent Domain

• EIS – Environmental Impact Statement

• EPIC – Environmental Permits, Issues, and Commitments

• FONSI – Finding of No Significant Impact

• IAJR – Interstate Access Justification Request

• ICA – Interlocal Cooperative Agreement

• IFP – Initial Financial Plan

• MAPO – Meeting with Affected Property Owners

• MPO – Metropolitan Planning Organization

• MTP – Metropolitan Transportation Plan

• NCTCOG – North Central Texas Council of Governments

• NEPA – National Environmental Policy Act

• NOPC – Notice of Proposed Construction

• NORA – Notice of Required Accommodation

• NTTA – North Texas Toll Authority

• PBLR – Preliminary Bridge Layout Review

• PS&E – Plans Specifications and Estimate

• PUA – Possession and Use Agreement

• ROW – Right-of-Way

• RTC – Regional Transportation Council

• RTL – Read to Let (date project is clear for construction but lacks funding for actual let)

• RTR – Regional Toll Revenue (funds resulting from certain toll/managed lane projects in DFW region)

• RULIS – Right-of-Way, Utilities, Leasing, and Information System

• STBG – Surface Transportation Block Grant

• STIP – Statewide Transportation Improvement Program

• SUE – Subsurface Utility Engineering

• SW3P – Storm Water Pollution Prevention Plan

• TIA – Time Impact Analysis

• TPP – Transportation Planning and Programming

• TPWD – Texas Parks & Wildlife Department

• TTC – Texas Transportation Commission

• TxDOT – Texas Department of Transportation

• UTP – Unified Transportation Program

• VE – Value Engineering

TxDOT Funding Categories

• CAT 1: Preventive Maintenance and Rehabilitation

• CAT 2: Metropolitan and Urban Area Corridor Projects / NCTCOG

• CAT 3: Non-Traditionally Funded Transportation Projects

• CAT 4: Statewide Connectivity Corridor Projects

• CAT 5: Congestion Mitigation and Air Quality Improvement / NCTCOG

• CAT 6: Structures Replacement and Rehabilitation (Bridge)

• CAT 7: Metropolitan Mobility and Rehabilitation / NCTCOG

• CAT 8: Safety Projects

• CAT 9: Transportation Alternatives

• CAT 10: Supplemental Transportation Projects

• CAT 11: District Discretionary

• CAT 12: Strategic Priority