reconstruct FM 740 and FM 548 to 4lane divided urban roadways; bridge widening at Mustang Creek crossing
Estimated Construction Cost: $88,634,701
Funding: *
Commissioner: Skeet Phillips, Precinct 2
Engineer & Key Contact: Jacobs, Abe Bekele
TxDOT Project Manager: Jordan Mrayyan
Schematic Approval: June 2025
Environmental Approval: December 2025
ROW Acquisition Complete: *
Utility Relocations Complete: *
100% Plans:
Ready to Let Date:
Start Date:
Current Activity:
• Design: Updated schematic and cross sections were submitted to TxDOT for review on December 16, 2024. Atkins to submit revised schematic and cross sections to TxDOT and ITS for review in early February 2025.
• Bi-weekly coordination meetings with TxDOT are ongoing.
• ROW: Revised proposed ROW file was submitted to TxDOT for coordination on December 16, 2024.
• Environmental: Jacobs continued effort toward preparation of environmental reports and responding to TxDOT comments to same. Thirteen environmental reports have been approved to date. Notice Affording an Opportunity for a Public Hearing was approved by TxDOT. Anticipate publication of NAOPH in February 2025, after resolution of SUE investigation of water line.
• Utility Coordination: SUE exhibits and updated utility coordination were submitted for review on December 15, 2024. Water line SUE data and updated SUE sheets expected at the end of January 2025.
FM 548 North: Phase I
CSJ: 2588-01-022
Limits:
Estimated Construction Cost:
Funding:
Project Description:
From north of US Highway 80 to Windmill Farms Blvd.
$132,752,619
Schematic Re-Approval: December 28, 2018
Environmental Clearance: July 3, 2019
Widen existing 2-lane, undivided facility to a 4- to 6-lane, divided facility 100% Plans: December 2024
Commissioner: Skeet Phillips, Precinct 2 Ready to Let Date: March 2025
Engineer & Key Contact: Westwood, Mark Zoellner, Mark Schluter Let Date: March 2025
TxDOT Project Manager: Gutema Gebrial
Current Activity:
• PS&E: Westwood submitted the 100% plans to TxDOT. TxDOT to submit plans to Design Division for letting.
• Utilities:
o AT&T: Relocations underway.
o Atmos: Relocations underway.
Construction Start: *
o Farmers Electric Co-Op: Relocations underway. Anticipate clearance at the end of February 2025.
o City of Forney: Clear
o High Point WSC: Relocations underway.
o NTMWD: Clear
o Oncor: Relocations underway. Anticipate completion in February 2025.
o Peoples Telephone Co-Op: Relocations underway.
• Construction: Project will let for construction in March 2025.
CSJ:
FM 548 North: Phase II
2588-01-017 (Kaufman County)
2588-02-008 (Rockwall County)
Limits: From Windmill Farms Blvd. to SH 205
Estimated Construction Cost:
Funding:
$94,669,035
$77,233,537: Kaufman County segment
$17,435,498: Rockwall County segment
$19,919,759 : CAT 2
$8,448,796: Kaufman County segment
$11,470,963: Rockwall County segment
Project Description: Widen existing 2-lane, undivided facility to a 4 to 6-lane, divided facility
Commissioner: Skeet Phillips, Precinct 2
Schematic Re-Approval: December 28, 2018
Environmental Clearance: July 3, 2019
ROW Acquisition Completed: August 2022
Utility Relocations Complete: July 2025
100% Plans: February 2025
Ready to Let Date: July 2025
Engineer & Key Contact: Burns & McDonnell, Tony Schmitt Let Date: *
TxDOT Project Manager: Gutema Gebrial
Construction Start: *
Current Activity:
• PS&E: Burns & McDonnell continues working toward completion of 100% plans and updating plans to 2024 TxDOT Specifications.
• Utilities: The status of utilities in conflict is below:
o Atmos: Relocation plans approved
o City of Dallas: Finalizing utility agreement. Pending construction start date.
o FEC: Various segments of relocation plans approved; various segments pending.
o High Point SUD: Relocation plans approved. Relocations underway.
o Spectrum: Plans approved. Pending FEC relocations.
o Sprint: Analyzing plan for relocation.
o Suddenlink (Optimum): Plans approved. Pending FEC relocations.
CSJ: 0095-04-069
US 80/SH 205/FM 148
Schematic Approval: January 26, 2018
Limits: US 80 and SH 205/FM 148 intersection Environmental Clearance: August 23, 2018
Construction Cost: $15,839,362
Funding: $9,349,949 : CAT 6
Project Description:
Intersection improvements to increase the capacity and improve safety at the intersection and the adjacent railroad crossing on FM 148 south of US 80, including full traffic signalization
Commissioner: Kelly Lane, Precinct 3
ROW Acquisition Complete: October 2019
Utility Relocations Complete: October 2022
100% Plans: December 10, 2021
Engineer & Key Contact: Othon, Jeff Love Construction
TxDOT Project Manager: Lane Selman
Current Activity:
• Construction: The project was awarded to Sterling Delaware Holding Company, Inc. with a low bid of $15,839,362.17, at 23.12% over engineer’s estimate. There are 504 working days and 24 months of barricades. See attached TxDOT construction report.
TxDOT Monthly Project Report for Kaufman County
Date of report: January 8, 2025
Report prepared by: Cody Jolley, P.E.
Control: 0095-04-069, ETC. Limits: Intersection SH205/FM148/US80
Project: CM2022(384)
Highway: US 80
Contractor: Sterling Delaware Holding Company, Inc.
TxDOT Area Engineer: Lane Selman, P.E.
TxDOT Assist. Area Engineer: Nic Wadlington, P.E.
TxDOT Project Manager: Chris Bruner
Contractor’s Superintendent: Kent Bergthold
Date Work Began: October 3, 2022
Anticipated Completion Date: March 28, 2025
Phone: (972) 962-3617
Phone: (972) 962-3617
Phone: (972) 962-3617
Phone: (972) 963-0262
Current activities: Asphalt pavement Flexbase. Concrete curb and gutter. Concrete paving.
Narrative description of last month’s activities: Driveways. Asphalt removal. Concrete removal. Mulch and block sod. Asphalt pavement.
Narrative description of activities planned for next month: Asphalt pavement. Flexbase. Concrete curb and gutter. Concrete paving.
Traffic issues: None
Plans for changes in traffic patterns: None
Item(s) of work currently controlling project completion: None
Other items of significance: None
FM 148 Bypass
CSJ: 0751-05-001; 0197-03-078
Limits: From US 175 to south of FM 3039
Construction Cost:
$60,049,999
Funding: $38,777,994
CAT 2: $33,777,994
CAT 3: $5,000,000
Project Description:
Construct new 2-lane undivided facility; add connection to proposed US 175 frontage road project
Current Activity:
• Utilities: With the exception of utilities that will complete relocations at the FM 148 Bypass/US 175 intersection, if necessary, during the US 175 South Frontage Road construction, utilities are clear of construction.
• Construction: The project was awarded to Granite Construction Company with a low bid of $60,049,998.99 at 3.74% above the engineer’s estimate. There are 35 months of barricades and 735 working days. See attached TxDOT construction report.
Schematic Approval: June 30, 2017
Environmental Clearance: April 26, 2019
ROW Acquisition Completed: November 2020
Utility Relocations Completed: February 2023
100% Plans: April 28, 2023
Construction Completion: November 2025
Commissioner: Tommy Moore, Precinct 4
Ready to Let Date: March 2023
Engineer & Key Contact: Halff Associates, David Burkett Let Date: June 27, 2023
TxDOT Project Manager: Lane Selman
TxDOT Monthly Project Report for Kaufman County
Date of report: January 8, 2025
Report prepared by: Cody Jolley, P.E.
Control: 0197-03-078 Limits: 2.3 miles west of FM 148 Bypass to East of FM 148 Bypass Project: F 2023(704)
Highway: FM 148
Contractor: Granite Construction Company
TxDOT Area Engineer: Lane Selman, P.E.
TxDOT Assist. Area Engineer: Nic Wadlington, P.E.
TxDOT Project Manager: Jacob Self
Contractor’s Superintendent: Brad Tyrer
Date Work Began: October 2, 2023
Anticipated Completion Date: November 6, 2025
Phone: (972) 962-3617
Phone: (972) 962-3617
Phone: (972) 962-3617
Phone: (972) 358-3712
Current activities: Flexbase. Conduit. Constructing concrete traffic rail. Excavation/Embankment.
Lime treatment for subgrade. Constructing asphalt pavement (westbound main lanes). Temporary grass seeding (FM 148). Lime treatment for subgrade.
Narrative description of last month’s activities: Flexbase. Concrete curb and gutter. Temporary wall construction. Excavation/Embankment. Lime treatment for subgrade. Electrical services. Conduit.
Narrative description of activities planned for next month: Construct concrete traffic barrier. Electrical installation. Temporary detour construction. Prepare for traffic switch (no date currently set). Striping. Excavation/Embankment. Lime treatment for subgrade. Installing drainage.
Traffic issues: None
Plans for changes in traffic patterns: None
Item(s) of work currently controlling project completion: None
Other items of significance: None
FM 1641
CSJ: 1217-01-019; 2588-01-020
Limits: From FM 548 to FM 148
Estimated Const. Cost:
Funding:
$90,661,674 -019: $87,462,145 -020: $3,199,529
$1,000,000
-019: $500,000: CAT 7 -020: $500,000: CAT 7
Project Description: Widen to a 4-lane divided (6-lane ultimate) urban facility
Commissioner: Skeet Phillips, Precinct 2
Engineer & Key Contact: LTRA, Massoud Manesh
TxDOT Project Manager: Chaikou Bah
Schematic Re-Approval: April 26, 2021
Environmental Clearance: August 31, 2021
ROW Acquisition Completed: September 2023
Utility Relocations Complete: December 2025
100% Plans: February 2025
Ready to Let Date: December 2025
Current Activity:
• PS&E: LTRA continued conversion of bid items to 2024 TxDOT Specifications, addressing TxDOT comments to 95% plan set, and working toward completion of final plan set. Anticipate submittal of final plan set to TxDOT in early February 2025.
• Utilities: Utilities that are clear: Gulf South Pipeline.
• Status of utilities in conflict is below.
o AT&T: Relocations underway. Pending clearance date
o Atmos: Pending design approval.
o Forney: Relocations underway.
o Oncor: Relocations underway.
o NTMWD: Working on relocation plans.
o Peoples Telephone: Relocation plans approved.
o Suddenlink (Optimum): Needs TVEC pole plans for relocation.
o Talty SUD: Working to acquire easements.
o TVEC: Final design in progress; pending relocation start.
CSJ: 1092-01-021; 1092-01-026
Limits: From US 175 to FM 548
FM 741
Schematic Approval: July 20, 2022
Environmental Clearance: March 28, 2023
Project Description: Widen and reconstruct from a 2-lane rural undivided to a 4/6-lane urban divided ROW Acquisition Complete: September 2027
Estimated Constr. Cost: $211,463,549
Funding: $10,000,000 CAT 7: -026
Commissioner: Skeet Phillips, Precinct 2 and Tommy Moore, Precinct 4
Engineer & Key Contact: HNTB, Kyle Riley
TxDOT Project Manager: Solomon Robelie
Current Activity:
• PS&E: The PBLR was approved by Bridge Division on November 8, 2023.
• HNTB completed the 95% PS&E plan set and submitted to TxDOT for review on September 20, 2024. Comment resolution meeting held on December 14, 2024
• TxDOT is negotiating with HNTB regarding a supplemental work authorization to divide the project into two packages: CSJ: 1092-01-026 will begin at US 175 and terminate based on available construction funding; CSJ: 1092-01-021 will begin at the end of CSJ: -026 and continue to FM 548; exact limits to be determined
• ROW: There are 124 parcels to acquire. There are: 1 parcel in appraisal, 1 parcel in negotiations, 25 parcels in ED, and 97 parcels in possession ROW acquisition efforts continue to be on hold due to District budgetary constraints; however, TxDOT was able to close some parcels that were with the title company.
Utility Relocations Complete: September 2029
Ready to Let Date: September 2029
Let Date: *
Construction Completion: *
CSJ: *
Limits: from IH 20 to US 80
Helms Trail
Schematic Approval: March 2025
Environmental Clearance: May 2025
Project Description: widen from 2-lane rural to 4-lane divided urban ROW Acquisition Complete:
Estimated Construction Cost: $38,250,000
Utility Relocations Complete:
Commissioner: Skeet Phillips, Precinct 2 Ready to Let Date:
Engineer & Key Contact: Dannenbaum, Donald Stephanik
TxDOT Project Manager:
Current Activity:
• Design: Dannenbaum submitted the pre-100% schematic on January 3, 2025. ITS is reviewing schematic.
• PS&E: LTRA is addressing comments from the 95% plan set and is working toward completion of final plan set
• PBLR was approved by Bridge Division.
• Utilities: Utility coordination kick-off meeting to be held. Status of utilities in conflict below:
o AT&T: Reviewing TxDOT plans and conflict matrix.
o Atmos: Reviewing TxDOT plans and conflict matrix.
o Enterprise: Reviewing TxDOT plans and conflict matrix.
o Oncor: Reviewing TxDOT plans and conflict matrix.
o Oneok: Reviewing TxDOT plans and conflict matrix.
o Optimum: Reviewing TxDOT plans and conflict matrix.
o Rose Hill SUD: Consultant reviewing TxDOT plans and conflict matrix.
o City of Terrell: Reviewing TxDOT plans and conflict matrix.
o TVEC: Consultant reviewing TxDOT plans and conflict matrix.
o Zayo: Reviewing TxDOT plans and conflict matrix.
TxDOT Project Manager: Marlena Kelly
I-20 Frontage Roads – Kaufman
CSJ: 0095-14-036
Limits: From west of FM 741 to Big Brushy Creek
Project Description:
Estimated
Engineer & Key Contact:
Schematic Approval: January 31, 2019
Environmental Approval: April 10, 2020
Current Activity:
• PS&E: WSB is reviewing and responding to 60% plan set comments and working toward completion of the 95% plan set Anticipate submittal of the 95% plan set in February 2025.
• H&H report and Preliminary Bridge Layout approved at the TxDOT District. Submitted to TxDOT Austin for review on March 25, 2024. District is discussing comments to PBLR with Bridge Division.
• ROW: There are 84 parcels to acquire. There are: 1 parcel in negotiations and 83 parcels in possession. ROW acquisition is on hold due to District budgetary constraints.
CSJ:
US 80 Widening
0095-03-080; -085
Limits: From Lawson Road to FM 460
Project Description:
Reconstruct and widen from 4 to 6 main lanes and reconstruct 2/4-lane discontinuous to 4/6-lane continuous frontage roads
Estimated Construction Cost: $128,902,801
$146,274,571
Funding:
$139,443,588: CAT 4; $1,882,263: CAT 6
$3,944,904: CAT 10; $1,003,816: CAT 11
Schematic Approval: August 24, 2018
Environmental Approval: April 13, 2020
ROW Acquisition Completed: February 2022
Utility Relocations Complete: June 2023
100% Plans: March 2022
Engineer & Key Contact: Halff Associates, Jeremy McGahan Let Date: June 29, 2022
TxDOT Project Manager: Lane Selman
Construction Completion: September 2026
Current Activity:
• Construction: The project let on June 29, 2022. The project was awarded to Webber, LLC, with a low bid of $128,902,801.08, at 7.40% above engineer’s estimate. There are 42 months of barricades and 1,086 working days. See attached TxDOT construction report.
Narrative description of last month’s activities: Embankment. Flexbase. Excavation Bridge panels. Drill shafts. Columns. Caps. Beams. Asphalt.
Narrative description of activities planned for next month: Embankment/Excavation. Flexbase. Drill shafts. Columns. Caps. Beams. Bridge deck Trinity River. Concrete curb and gutter. Asphalt paving.
Traffic issues: None
Plans for changes in traffic patterns: None
Item(s) of work currently controlling project completion: None
Other items of significance: None
US 80/Spur 557 (FM 460 to IH 20)
CSJ: 0095-03-106; 0095-04-076; 0495-01-081
Limits: From FM 460 to IH 20
Project Description: Widen and add lanes
Estimated Construction Cost: $1,407,562,206
Funding: *
Schematic Approval: December 2023
Environmental Approval: April 3, 2024
ROW Acquisition Complete: March 2028
Utility Relocations Complete: March 2030
100% Plans: *
Engineer & Key Contact: * Ready to Let: March 2030
Current Activity:
• Environmental: A public hearing was held on February 8, 2024, in Forney. Finding of No Significant Impact (FONSI) was issued on April 3, 2024.
• PS&E: Awaiting TxDOT determination of priorities and next steps to advance project to PS&E phase.
TxDOT Project Manager: Doreen Choo
CSJ: 0918-11-109
Outer Loop
Schematic Approval: May 2025
Limits: From SH 205 to FM 148 Environmental Approval: November 2025
Project
Engineer
Current Activity:
• Design: HDR continues coordination with project stakeholders. HDR also continues coordination with TxDOT, Halff Associates (Rockwall County Outer Loop project), NCTCOG, and ITS.
• HDR submitted the 90% schematic to TxDOT for review on October 11, 2024. Schematic comments provided by TxDOT; HDR is reviewing and addressing.
• Revised IAJR memo submitted on October 31, 2024.
• Environmental: TxDOT has approved this project for an EA in lieu of an EIS Environmental technical reports continue. Two environmental technical reports have been approved to date; twelve reports are in progress.
• Other: Project website is available at: https://kaufmanouterloop.com
FM 740
CSJ: 2249-01-009; 1091-01-023
Limits: from Kaufman/Rockwall County Line to Ranch Road
Project Description: reconstruct FM 460 and FM 740 to 4lane (6-lane ultimate) divided urban roadways
Schematic Approval: August 2025
Environmental Approval: June 2026
Current Activity:
• Design: Atkins is addressing TxDOT comments to 90% schematic.
• Atkins continued drainage efforts and working on hydraulic model and evaluation of mitigation for detention pond layouts
• Atkins continued updating forecasts and providing recommendations for all intersections based on traffic analysis.
• Coordination meetings with Atkins, TxDOT, and ITS are ongoing.
• Atkins continues preparing for public meeting. Second public meeting is tentatively scheduled for March 6, 2025.
• ROW: ROW footprint is being finalized.
US 175 Grade Separations – Kemp
CSJ: 0197-05-063
Limits: from Business US 175 to FM 1895
Project Description: construct interchange at BUS 175 and FM 1895
Estimated Construction Cost: $89,486,203
Funding: *
Commissioner: Tommy Moore, Precinct 4
Schematic Approval: November 2023
Environmental Approval: November 26, 2024
ROW Acquisition Complete: NA
Utility Relocations Complete: *
100% Plans: *
Ready to Let Date: *
Engineer & Key Contact: Halff, Melanie Cleavelin Let Date: *
TxDOT Project Manager: Liang Ding
Current Activity:
• Environmental: Project was environmentally cleared on November 26, 2024.
• Design: Halff Associates is preparing a supplemental agreement to advance project to PS&E phase.
Construction Start: *
CSJ:
US 175 Safety Improvements – Kaufman
0197-04-086; 0196-04-087
Limits: from 0.5 miles south of SH 34 to Fair Road
Project Description: relocate existing crossovers, construct U-turns and deceleration lanes
Estimated Construction Cost: $8,911,637
Funding:
$8,773,402
$2,788,596: CAT 8
$5,984,806: CAT 11
Schematic Approval: NA
Environmental Approval: December 2023
ROW Acquisition Complete: NA
Utility Relocations Complete: NA
Final Plans: May 2024
Commissioner: Terry Crow, Precinct 1 Ready to Let Date: August 2024
Engineer & Key Contact: Quiddity, David Unger
TxDOT Project Manager: Lane Selman
Current Activity:
• Construction: Project let for construction on August 2, 2024. The project was awarded to Granite Construction Company, with a low bid of $12,103,561.02, at 0.92% below engineer’s estimate. There are 150 working days and 10 months of barricades. Construction began on December 4, 2024. See attached TxDOT construction report.
Construction Completion: February 2026
TxDOT Monthly Project Report for Kaufman County
Date of report: January 8, 2025
Report prepared by: Cody Jolley
Control: 0197-04-086
Project: F 2B24 (336), ETC.
Limits: US 175 – west of SH 34 to south of FM 153
Highway: US 175
Contractor: Granite Construction Company
TxDOT Project Manager: Jason Hyde
Contractor’s Superintendent: Ben Simpson
Date Work Began: December 4, 2024
Anticipated Completion Date: February 2026
Phone: (972) 962-3617
Phone: (214) 254-6503
Current activities: Mobilization. Place project signs. Prepare ROW for construction.
Narrative description of last month’s activities: Mobilization. Prepare ROW for construction.
Narrative description of activities planned for next month: Construct temporary detours. Prepare for Phase 1 traffic shift (no date set currently).
Traffic issues: None
Plans for changes in traffic patterns: None
Item(s) of work currently controlling project completion: None
Other items of significance: None
SH 34-US 175 Connector Road
CSJ: NA
Roadway No. 1: south of US 34 to new Roadway No. 2
Limits:
Project Description:
Roadway No. 2: southwest of US 175 to new Roadway No. 1
Construction of new 2-lane (4-lane ultimate) divided (Roadway No. 1) and new 2-lane (4-lane ultimate) undivided (Roadway No. 2) connection roads for new Kaufman County justice center
Construction Cost: $3,270,425
Schematic Approval: NA
Environmental Approval: NA
ROW Acquisition Complete: *
Funding: 2019 County Bond Funds 100%
Commissioner: Terry Crow, Precinct 1
Engineer & Key Contact: TNP, Matt Atkins Construction
Current Activity:
• Construction: Pavecon Public Works, LP was the lowest bidder, with a bid of $3,450,477.70. The county awarded the project to Pavecon on December 19, 2023 A pre-construction meeting was held on February 9, 2024. Construction began on March 14, 2024. See attached construction report.
TxDOT Project Manager: NA
US 175 Feasibility Study
CSJ/Project ID: A00190822
Limits:
Project Description:
Estimated Construction Cost:
From west of FM 1389 (Kaufman County line) to east of SH 198 (Henderson County line)
Feasibility study to investigate capacity improvements including main lanes expansion and addition of continuous frontage roads and new interchanges
Engineer & Key Contact: BGE, Hossein Hosseiny
Schematic Approval:
Environmental Approval: *
ROW Acquisition Complete:
Current Activity:
• Design: BGE continues developing design with an urban typical section throughout the county to minimize ROW impacts.
• Meeting to present design concepts and impacts to TxDOT Dallas District was held on December 18, 2024.
• BGE is preparing and analyzing an urban section for the corridor and comparing impacts.
• BGE is updating presentation to outline design concepts and impacts. BGE will meet with TxDOT on February 10, 2025, to present findings.
Glossary of Acronyms
• AADT – Annual Average Daily Traffic
• AFA – Advanced Funding Agreement
• ARPA – Archeological Resources Protection Act
• ASED – Annual Scope & Estimate Documentation
• CE – Categorical Exclusion (environmental clearance process for projects that do not involve significant environmental impacts)
• CLOMR – (FEMA’s) Conditional Letter of Map Revision
• Conformity – Federal requirement in nonattainment areas to conduct air quality analysis on projects, programs, and policies identified in transportation plans, transportation improvement programs, federally funded projects, or projects requiring federal approval
• CSJ – (TxDOT’s) Control Section Job Number
• EA – Environmental Assessment
• ED – Eminent Domain
• EIS – Environmental Impact Statement
• EPIC – Environmental Permits, Issues, and Commitments
• FONSI – Finding of No Significant Impact
• IAJR – Interstate Access Justification Request
• ICA – Interlocal Cooperative Agreement
• IFP – Initial Financial Plan
• MAPO – Meeting with Affected Property Owners
• MPO – Metropolitan Planning Organization
• MTP – Metropolitan Transportation Plan
• NCTCOG – North Central Texas Council of Governments
• NEPA – National Environmental Policy Act
• NOPC – Notice of Proposed Construction
• NORA – Notice of Required Accommodation
• NTTA – North Texas Toll Authority
• PBLR – Preliminary Bridge Layout Review
• PS&E – Plans Specifications and Estimate
• PUA – Possession and Use Agreement
• ROW – Right-of-Way
• RTC – Regional Transportation Council
• RTL – Read to Let (date project is clear for construction but lacks funding for actual let)
• RTR – Regional Toll Revenue (funds resulting from certain toll/managed lane projects in DFW region)
• RULIS – Right-of-Way, Utilities, Leasing, and Information System
• STBG – Surface Transportation Block Grant
• STIP – Statewide Transportation Improvement Program
• SUE – Subsurface Utility Engineering
• SW3P – Storm Water Pollution Prevention Plan
• TIA – Time Impact Analysis
• TPP – Transportation Planning and Programming
• TPWD – Texas Parks & Wildlife Department
• TTC – Texas Transportation Commission
• TxDOT – Texas Department of Transportation
• UTP – Unified Transportation Program
• VE – Value Engineering
TxDOT Funding Categories
• CAT 1: Preventive Maintenance and Rehabilitation
• CAT 2: Metropolitan and Urban Area Corridor Projects / NCTCOG