2022 Proposition E Tranportation Project Council Quarterly Update

Page 1


2022 Proposition E Transportation Projects

www.forneytx.gov

Lovers Lane

Current Status

Design

ACTIVITY

STATUS

In progress – Scheduled Completion 3/17/2025

Public Meeting Anticipated January/February 2025

Right of Way Acquisitions

In progress – Scheduled Completion 4/18/2025

Utility Relocation

Construction

www.forneytx.gov

March 2025 – May 2025

June 2025 – October 2026 Next Page

www.forneytx.gov

www.forneytx.gov

Community Park Road Ext.

UP Grade Separation Study

Study

Public Meeting

Design

Construction

www.forneytx.gov

January/February 2025 TBD

www.forneytx.gov

Questions/Comments?