Mare Island Bridge Project Informational Sheet

Page 1

C I T Y O F VA L L E J O :

Mare Island Causeway Bridge PREVENTATIVE MAINTENANCE PROJECT

Towers

Traffic Signals

Railing & Posts

Causeway Lighting

Sidewalk

Concrete Deck Concrete Piles

Movable Span

Fenders

Steel Piles

About the Mare Island Bridge If you work or live nearby Mare Island, then you’ve probably crossed this bridge. The Mare Island Causeway Bridge is located at the north end of the Vallejo Waterfront. This bridge connects Mare Island to the Greater Vallejo area and is accessible to vehicles, pedestrian, and rail traffic.

THE BRIDGE AT A GLANCE: 165 feet long and 48.5 feet wide

Minimum Clearance (span down) 12.4 feet

Maximum Clearance (span fully raised) 99.7 feet


WHAT’S HAPPENING ON THE BRIDGE?

THESE REPAIRS ARE EXPECTED TO INCLUDE:

In 2016, the City of Vallejo completed an upgrade project on the bridge, replacing a 50-foot span of bridge timber with steel. However, the iconic bridge now requires additional maintenance repairs to extend the Bridge’s serviceable life and improve pedestrian and driver safety.

Bridge deck and pile repairs

Repairing damaged concrete surfaces

Sidewalk replacement and ADA improvements

Repairing the fender system that directs ships through the correct opening under the bridge

Lighting and handrail repairs

Replacement of underwater anodes which protect the bridge’s steel against saltwater corrosion

Repainting the Bridge’s steel lift span, towers, and historic logo

HOW WILL THIS PROJECT IMPACT ME? The City anticipates that when construction begins, the bridge may experience partial lane closures.

Broadway

er Riv

ve dA

ve ut A

Sacramento St

ve nA

so Wil

pa

Na lroa

Rai

Please plan accordingly.

Mare Island t Causeway GS

29

Tuolumne St

37

ln Wa

However, the bridge is not anticipated to be fully closed during the project.

Redwood St

Tennessee St Florida St

WHEN SHOULD I EXPECT TO SEE CONSTRUCTION ON THE BRIDGE? Environmental studies and final design

Construction

2020

2022-23

HOW IS THIS PROJECT FUNDED? Bridge Preventive Maintenance Project (BPMP) BUDGET (Engineer’s Estimate):

2021 Preparations for construction, permitting public outreach

$13.8 M FEDERAL:

LOCAL:

$12 M

$1.8M

To learn more and sign up for project updates, visit bit.ly/MareIslandBridge