A FIRST AND LAST IMPRESSION The Fredericton International Airport opens new expansion earlier this year

By Shayna Wiwierski

Travelers coming to and from

was a decade in the making, according

the building was designed to handle

Fredericton by air will now be greeted

to Kate O’Rourke, manager of PR

about 200,000 people a year and in

in style.

and marketing for the Fredericton

2019 we had 427,000 people. We were

International Airport Authority.

well over capacity and had been for

The Fredericton International Airport

about a decade,” says O’Rourke. “So,

completed their two-year expansion

“The Fredericton airport was built

the airport authority got creative and

project this past February, several

in the 1960s and has been added to

worked with our partners to find ways

months ahead of schedule. The project

here and there over the years, but

to move people through the building more efficiently, but there are limits to

The Fredericton International Airport completed their two-year expansion project this past February.

how much capacity you can add that way. We were desperately in need of an expansion and renovation.” Although the airport had seen numerous additions over the years, the airport authority decided to strip the current airport down to the steel girders, upgrade the space, and then add more than 50 per cent to the footprint. The original building, which was built in 1963, was 14,000 square feet, and with the numerous additions over the years it was 38,000 square feet before this significant expansion.

Although the airport had seen numerous additions over the years, the airport authority decided to strip the current airport down to the steel girders, upgrade the space, and then add more than 50 per cent to the footprint.

The new footprint of the airport is now 62,000 square feet. Construction started in June 2019 on the $32 million project, with $9 million each being funded by the federal and provincial governments. The remainder of the cost was financed by the airport authority. The expansion includes new foundations on the air side of the building, high ceilings for a new hold room, a new baggage room, a new security screening area, and a new in-bound bag room. They also renovated the entire ticketing hall and baggage handling system. In addition to that, the expansion is aimed to accommodate traveler comfort and includes lots of natural light, new