SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN BACHELOR OF SCIENCE (HONS) IN ARCHITECTURE
INTERNSHIP TRAINING AND REPORT (INT60105) 6 JANUARY 2020 - 28 FEBRUARY 2020 (8 WEEKS)
STUDENT NAME : STUDENT ID : LECTURER : INTERNSHIP COMPANY :
GAVIN TIO KANG HUI 0333373 AR. LEE SZE EE AKITEK AKIPRIMA SDN. BHD.
INT60105 Internship Training and Report
Table of Content
CONTENT 1.0
Report Overview
Page 1
2.0
Company Introduction
Page 2
3.0
Weekly Task Involvement 3.1
Week 1
DUZ - Accolade Land S/B
Page 3
DVQ - Aurelian Land S/B 3.2
Week 2
DVQ - Aurelian Land S/B
Page 8 Page
8
Page 13Page
13
EEX - Glowing Attraction S/B ERB - Low Keng Huat Holdings 3.3
Week 3
ERB - Low Keng Huat Holdings EEX - Glowing Attraction S/B ESE - Edisi Megah
3.4
Week 4
ESE - Edisi Megah
Page 16
3.5
Week 5
DEE - Memang Jati S/B
Page 20
AZB - Atria Damansara S/B 3.6
Week 6
AZB - Atria Damansara S/B
Page 23
ESE - Edisi Megah 3.7
Week 7
ESE - Edisi Megah
Page 28
DQP - Sunway Velocity Two S/B 3.8
Week 8
DQP - Sunway Velocity Two S/B
Page 33
ERS - Sunway Tianjin For Sunway China EEX - Glowing Attraction S/B 4.0
Reflection
Page 37
5.0
Appendix - Weekly Log Sheet
Page 38
i
INT60105 Internship Training and Report
1.0
1.0 Overview
Overview
The internship programme lasted for 8 weeks, starting from 6 January 2020 to 28 February 2020 at Akitek Akiprima Sdn. Bhd. In reference to weekly Log Sheets, the report will summarise the internship experience with the aid of images, drawings and documents by indicating the scope of work undertaken weekly. The experience and involvement will be expressed precisely on weekly basis and be cross-referenced to the scope of works recorded in the Log Sheets.
Page 01
INT60105 Internship Training and Report
2.0
2.0 Company Introduction
Company Introduction Name
: Akitek Akiprima Sdn. Bhd.
Location
: E-01-4, Subang Square Business Park (East Wing), Jalan SS15/4G, 47500 Subang Jaya, Selangor Darul Ehsan
Year of Establishment
: 1980
Website
: https://www.akiprima.com.my/
: akiprima-kl@akiworld.com
Contact Line
: +60-3-5633 5877
Figure 1.1 Akitek Akiprima Company Logo
“Inherent in all operations is the philosophy of building from within. Just as a building without a strong structure tends to ruin, we believe in first building our company structure, then we can begin serving our clients. Weekly team meetings to discuss on-going projects, and person senior supervision on-site to ensure building and material quality are common occurrences in this company.” -
Akiprima Philosophy
Akitek Akiprima Sdn. Bhd. was founded first in Penang. Until today, the head office is located in Subang Jaya, with domestic branches in Kuantan and Johor Bahru and also internationally in Phnom Penh, Cambodia. Akiprima has been involving in an array of projects ranging from residential and service apartment to institution and town planning. Some of the projects are Sunway City Ipoh, New Atria PJ, Impiana City Penang, Sunway Lost World Hotel Tambun, Sunway Hotel Hanoi, Water Theme Park Penang, 3 Storey Bungalow SS19, Semi-D & Terrace Factory Lots Hulu Langat and so on.
Figure 1.2 3 Storey Bungalow SS19
Figure 1.3 Semi-D & Terrace Bungalow SS19
Figure 1.4 Impiana City Penang
Page 02
Figure 1.5 Sunway Lost World Hotel, Tambun
INT60105 Internship Training and Report
3.0
Weekly Task Involvement
3.1
Week 1
3.1 Weekly Task Involvement
Project Name
DUZ - Accolade Land S/B
Location
Jalan Lancang, Taman Seri Bahtera, Cheras 56100 Kuala Lumpur
Category
Project Authority Liaison
The project was at Bomba Submission Stage. I was assigned to calculate the NFA of the office & service apartment of type A, B & C. From the task, I learned that the ratio of different type of spaces such as M&E, fire staircases, circulation spaces, living units and so on are crucial in maximising the building overall profit. Also, I was assigned to tabulate number of carpark provided in respect to each floor. The total number of carpark should be wisely considered to cater to all apartment units.
Figure 1.6 8th Floor Plan Showing Typical Apartment Unit A, B & C and Office Suite at Five Different Blocks
Page 03
INT60105 Internship Training and Report
3.1 Weekly Task Involvement
Figure 1.7 Fasa 2D - Service Apartment Typical Layout
Figure 1.8 Ground Floor Plan - Carpark Layout
Page 04
INT60105 Internship Training and Report
3.1 Weekly Task Involvement
Project Name
DVQ-Aurelian Land S/B
Location
Lot 9088, Bentong, Pahang
Category
Drawing - Detailing
I was assigned to prepare tender drawings for Staircase 5 and Staircase 8. Firstly, I was to draw detail plans for the staircases up to roof level (27th floor) according to the standard drawing convention of the company. The number and height of risers were to double check with each floor height. From this I learnt further in-depth about the By-Laws regarding to fire staircases. The risers should not exceed 180mm and turning of landing should not be overlapping with fire door swing. Also, I was exposed to the construction materials and techniques of fire safety shaft such as 150mm thick brick wall and 230mm thick R.C. shear wall and beam alignment in relation to air pressurization shaft and fire rated wall placement at each floor. After that, I was to draw the section of the fire safety shaft, projecting from the plans respectively. In this case, I learnt about the minimum headroom of 2300mm for all landings and staircase construction. At Level 9A, a double landing staircase was introduced into staircase 5 whereas a triple landing staircase was introduced into staircase 8. With the guidance of my colleagues, I managed to resolved the headroom issue by taking into account of alignment of steps and height of risers. Beam alignment is crucial for precast r.c. staircase installment and drop is to be taken care of for the area with no roof at level 9A.
Figure 1.9 Detail Staircase 5 Floor Plans S
Page 05
INT60105 Internship Training and Report
3.1 Weekly Task Involvement
Figure 1.10 Detail Staircase 5 Floor Plan - Level 10 with Specifications
Figure 1.11 Detail Staircase 5 Section with Specifications
Page 06
INT60105 Internship Training and Report
3.1 Weekly Task Involvement
Figure 1.12 Detail Staircase 5 Section - Level 7 to Level 9A (Double Landing)
Figure 1.13 Staircase 5 Layout
Page 07
INT60105 Internship Training and Report
3.2
3.2 Weekly Task Involvement
Week 2
Project Name
EEX - Glowing Attraction S/B
Location
Lot 96 (GM885), Mukim Pulai, Johor Bahru, Johor
Category
Drawing - Detailing
I was assigned to draw tender drawings of detail plans and sections for toilet. I was to detail up the toilet layout plan with reference to the main drawings. I added in sanitary fittings such as water closet, water tap, basin, paper holder, soap tray, mirror, shower head, etc. accordingly. For instance, all taps for water closet are always on right hand side of water closet. Through this task, I learned about the standard specifications for toilet such as drop difference, tiles setting out, water-proofing, window louvres orientations etc. After that, I projected two sections for each detail toilet plans. I learned to position lintel with doors and windows, tile setting height in relation to ceiling height, standard drop dimension, standard height for sanitary fittings, etc. Also, I have more understanding for the construction materials and connection details of generic wall, partywall, ceiling, door and window, etc. by drawing the sections.
Figure 1.14 Detail Toilet Plans and Sections Arranged in Templates
Page 08
INT60105 Internship Training and Report
3.2 Weekly Task Involvement
Figure 1.15 Detail Plans of Bath 2 and Bath 3
Figure 1.16 Detail Sections of Bath 2 and Bath 3
Page 09
INT60105 Internship Training and Report
3.2 Weekly Task Involvement
Figure 1.17 Detail Drawings of Bath 4 and Master Bath
Figure 1.18 Detail Sections of Master Bath
Page 10
INT60105 Internship Training and Report
3.2 Weekly Task Involvement
Project Name
ERB - LOW KENG HUAT HOLDING
Location
Villa U Thant PT 2631, Mukim Ampang KL/09
Category
Drawing - Digitalising Manual Drawings
The project tasked to renovate a villa. I was given a set of manual drawings of elevations and sections. The drawings were to be digitalised for renovation design scheme proposal. From the set of manual drawings, I have better understanding on projection lines and lineweight. Manual drawings allow occurrence of errors to the extent of selected scale, hence, some of the details of the drawings were to be ďŹ gured out in the process based on other drawings.
Figure 1.19 Digitalised Front Elevation
Figure 1.20 Railing Detail
Figure 1.21 Balcony Detail
Page 11
INT60105 Internship Training and Report
3.2 Weekly Task Involvement
Figure 1.22 Rear Elevation
Figure 1.23 Sections
Page 12
INT60105 Internship Training and Report
3.3
3.3 Weekly Task Involvement
Week 3
Project Name
EEX - Glowing Attraction S/B
Location
Lot 96 (GM885), Mukim Pulai, Johor Bahru, Johor
Category
Drawing - Detailing
For this task, I was assigned to produce tender drawings such as plans, sections and details for staircase. It is a typical staircase for a residential double storey terrace house. With reference to main drawings, details such as specifications, wall material, number of risers, dimensions, arrows, etc. were being added to plans. I learned to position staircase properly according to the alignment of beam and to locate railings properly for easier construction. Door for store under staircase is better to swing outwards to provide more room for store. Next, I was to project two sections from the plan. Through this, I have better understanding on the construction of ground and first floor beams in relation to wall and staircase position whereby the construction of ground beam and ground floor slab is divided into two steps whereas first floor beam and first floor slab are being casted simultaneously. Then, details of selected part of staircase were drew under guidance of supervisor.
Figure 1.24 Residential Double Storey Terrace Staircase Tender Drawings
Page 13
INT60105 Internship Training and Report
3.3 Weekly Task Involvement
Figure 1.25 Staircase Plans and Sections
Figure 1.26 Staircase and Railing Details
Page 14
INT60105 Internship Training and Report
3.3 Weekly Task Involvement
Figure 1.25 Staircase Plans and Sections
Figure 1.26 Staircase and Railing Details
Page 15
INT60105 Internship Training and Report
3.4
3.4 Weekly Task Involvement
Week 4
Project Name
ESE - EDISI MEGAH
Location
PT 60670 and PT 60671, Cybersouth, Dengkil, Sepang
Category
Drawing - Detailing
I was assigned to produce door and window schedule for single storey terrace with reference to main drawings. All window and door types were being identified and arranged in order with numbering. I have more in-depth understanding for the window and door specifications regarding to its building material and construction method. For instance, all bath doors will have waterproofing membrane and will be 2100mm in height whereas the other will be 2400mm in height. In addition, I learned to label and provide dimension with proper drawing conventions.
Figure 1.27 Single Storey Terrace Window Schedule
Page 16
INT60105 Internship Training and Report
3.4 Weekly Task Involvement
Figure 1.28 Window Schedule with SpeciďŹ cations
Figure 1.29 Single Storey Terrace Door Schedule
Page 17
INT60105 Internship Training and Report
3.4 Weekly Task Involvement
Next, I was assigned to produce reflected ceiling plan for Community Centre and terrace detail for Double Storey Terrace. I had a better insight to ceiling materials such as plaster ceiling and aluminium strip ceiling and their functions that cater to different rooms function specifically. I learned about general ceiling height for different spaces of different buildings. For instance, toilet ceiling height for residential building is usually kept at 2400mm whereas for public building such as community centre is generally kept at 3000mm. For terrace detail of Double Storey Terrace, I learned to draw copings and sliding door details and its connection to floor slab and lintel. Natural anodised aluminium frame sliding door is usually selected as its material due to its feasibility and economy.
Figure 1.30 Reflected Ceiling Plan with Hatching and Legends
Figure 1.31 Ceiling Height Annotation
Figure 1.32 Legends with Specifications
Page 18
INT60105 Internship Training and Report
3.4 Weekly Task Involvement
Figure 1.33 Terrace (Balcony) Detail of Double Storey Terrace
Figure 1.34 Terrace Plan Showing Sliding Door Detail and Door Coping
Page 19
INT60105 Internship Training and Report
3.5
3.5 Weekly Task Involvement
Week 5
Project Name
DEE - Memang Jati S/B
Location
Lot 29015 - 29025, Jalan Wangsamas, Mukim Setapak, KL
Category
Drawing - Detailing
My task was to produce detail plans and sections for master bath, baths and powder room. I started with plan with reference with main drawings. The project was at the stage of construction drawings. Under the guidance of my supervisor, I was able to produce the construction drawings with proper drawing convention. I had better understanding for the construction of toilet, from wall and ceiling to wall tiles and sanitary fittings. Positioning of each fittings regarding to the height and separation is crucial in maximizing user’s comfort level in the toilet.
Figure 1.35 Detail Plans and Sections
Page 20
INT60105 Internship Training and Report
3.5 Weekly Task Involvement
Figure 1.36 Powder Room and Bath 3 Detail Plans and Sections
Figure 1.37 Master Bath and Bath 2 Detail Plans and Sections
Page 21
INT60105 Internship Training and Report
3.5 Weekly Task Involvement
Project Name
AZB - Atria Damansara S/B
Location
Tingkat 9, Plaza OSK, Jalan Ampang, 50450 Kuala Lumpur
Category
Drawing - Plot, Print, Fold and Documentation
The project has completed the construction stage and the management requested for the full set of construction drawings for reference for renovation. I plotted, printed, folded and documented the sets of drawings. With this task, I had the opportunity to study the full set of as-built drawings and had an insight of which drawings are to be done for a building to be constructed. For instance, expansion joint drawings, statutory signages, landscape, facade treatment drawings, carpark marking, smoke curtain, ramp details, etc.
Figure 1.38 Categorising 932 Construction Drawings
Figure 1.39 Printed Drawings To Be Folded
Figure 1.40 Completed Set of Construction Drawings
Page 22
INT60105 Internship Training and Report
3.6
3.6 Weekly Task Involvement
Week 6
Project Name
ESE - EDISI MEGAH
Location
PT 60670 and PT 60671, Cybersouth, Dengkil, Sepang
Category
Drawing - Detailing
I was assigned to produce tender drawings for Townhouse, Single Storey Terrace and Double Storey Terrace. Firstly, I worked on reflected ceiling plan detail and tile setting out. Tile setting out drawing is important to minimize material wastage with strategic setting point. Next, based on main drawings, I were to prepare door and window schedule with proper dimension and specifications. Each types of door and window were to be identified according to their location. Then, I was to produce kitchen detail plan and section drawings. Through this, I had better understanding towards the specifications of drop and how does it function at different locations within a building. Next, I was assigned to draw carporch detail plans and sections. I learned about cement render flooring and concrete imprint and their functions. The column at carporch was integrated with piping system that allows water collected from scupper drain at first floor above to be discharged into the drain. After that, I continued with yard detail plan and sections where yard is a double volume void established up to roof level. Lastly, I was assigned to colour code the main drawings for BP Submission. I learned about the different finished represented by each colour. For instance, cement render represented by light yellow, ceramic tile represented by pink, rainwater downpipe represented by blue, etc.
Figure 1.41 Reflected Ceiling Plan - Townhouse
Page 23
INT60105 Internship Training and Report
3.6 Weekly Task Involvement
Figure 1.42 Tile Setting Out - Townhouse
Figure 1.43 Door and Window Schedule - Double Storey Terrace
Page 24
INT60105 Internship Training and Report
3.6 Weekly Task Involvement
Figure 1.44 Kitchen Detail - Townhouse
Figure 1.45 Drop Detail of Door to Backyard - Townhouse
Page 25
INT60105 Internship Training and Report
3.6 Weekly Task Involvement
Figure 1.46 Carporch and Balcony Detail - Townhouse
Figure 1.47 Yard Detail - Townhouse
Page 26
INT60105 Internship Training and Report
3.6 Weekly Task Involvement
Figure 1.48 Colour-coded Double Storey Terrace Main Drawings
Figure 1.49 Colour-coded Ground Floor Plan
Page 27
INT60105 Internship Training and Report
3.7
3.7 Weekly Task Involvement
Week 7
Project Name
DQP - Sunway Velocity Two S/B
Location
Lot 135, Jalan Peel, Seksyen 90, Bandar Kuala Lumpur, KL
Category
Drawing - Detailing
My task was to constitute Statutory Signage, Directional Signage and Architectural Signage for Tower C and D. Starting from Ground Floor Plan where the carpark circulation connects with adjacent highway, I inserted pylon signages accordingly, followed by pole signages and directional signages to indicate direction towards residential and commercial carpark area. Next, I assigned architectural signage such as floor level indicator for internal staircase, room and retail signage, loading bay, carpark signage, level indicator for lift lobby, etc. After that, directional signages were established for first floor to 8A floor to indicate carpark circulation such as exit direction, one-way or two-way vehicular circulation, more parking, etc. Finally, the legends were categorised according to residence (RA & RD) and commercial (CA & CD) in excel sheet respectively.
Figure 1.50 Signages Indication on Ground Floor Plan
Page 28
INT60105 Internship Training and Report
3.7 Weekly Task Involvement
Figure 1.51 Colour-coded Double Storey Terrace Main Drawings
Figure 1.52 Documentation of Signage Legend
Page 29
INT60105 Internship Training and Report
3.7 Weekly Task Involvement
Figure 1.53 Directional Signages for Residence (RD) and Commercial (CD)
Figure 1.54 Carpark Circulation on Second Floor
Figure 1.55 Signages Detail Indication
Page 30
INT60105 Internship Training and Report
3.7 Weekly Task Involvement
Project Name
EEX - Glowing Attraction S/B
Location
Lot 96 (GM885), Mukim Pulai, Johor Bahru, Johor
Category
Drawing - Detailing
I was assigned to produce door and window schedule. With reference to main drawings, different types of doors and windows were tabulated including door roller shutter. After that, I was to produce detail sections for door, roller shutter and windows. Through this task, I learned about the sectional details of doors and window such as aluminium frame detail, galvanised steel door head details, door leaf frame offset from floor, etc.
Figure 1.56 Door and Window Schedule
Figure 1.57 Roller Shutter Door Detail
Figure 1.58 Window Schedule
Page 31
INT60105 Internship Training and Report
3.7 Weekly Task Involvement
Figure 1.59 Door and Window Detail Sections
Figure 1.60 Casement Window Detail Section
Page 32
INT60105 Internship Training and Report
3.8
3.8 Weekly Task Involvement
Week 8
Project Name
DQP - Sunway Velocity Two S/B
Location
Lot 135, Jalan Peel, Seksyen 90, Bandar Kuala Lumpur, KL
Category
Modelling
I was assigned to produce two physical 1:1 detail models for door frame detail and R.C. ramp detail whereby one of the ramp gradient was 1:35 and the other was 1:2. They were two options provided to client regarding to the bath toilet door. The option whereby the ramp gradient is 1:35 is easier to be constructed and is more economic. More tiles are needed for the other option since there are two surfaces to be tiled : 38mm at cut tile adjacent to timber capping and ramp. Through this, I have more understanding towards the details of door, drop and ramp. It is important to wisely consider each details position and evaluate them in section and plan to ensure the details to be workable, economic, eďŹƒcient and also aesthetic.
Adjacent Wall
Timber Door Frame
Timber Floor Capping
Adjacent Timber Door Frame Wall
Figure 1.61 Door Frame and Ramp 1:1 Detail Model
Page 33
Timber Floor Capping
INT60105 Internship Training and Report
3.8 Weekly Task Involvement
Figure 1.62 and Figure 1.63 Door Frame 1:1 Detail Model with Ramp of 1:35 Gradient
Figure 1.64 and Figure 1.65 Door Frame 1:1 Detail Model with Ramp of 1:2 Gradient
Page 34
INT60105 Internship Training and Report
3.8 Weekly Task Involvement
Project Name
ERS - Sunway Tianjin for Sunway China
Location
Tianjin, China
Category
Drawing - Plot, Print and Fold
I was tasked to plot and print construction drawings of the project. Through this, I have better understanding towards building constructions. Beams will be ush with column if not stated otherwise. Due to China climatic condition, heater system such as active and passive fan rooms, heater room, heater piping to all apartment units, oor section details, etc.
Figure 1.66 Printed Construction Drawings
Figure 1.67 Staircase Detail Plans
Figure 1.68 Structural Plan Showing Beam Position
Page 35
INT60105 Internship Training and Report
3.8 Weekly Task Involvement
Project Name
EEX - Glowing Attraction
Location
Lot 96 (GM885), Mukim Pulai, Johor Bahru, Johor
Category
Drawing - Detailing
I was assigned to produce detail drawings for air-con ledge. Firstly, plan was detailed up with reference to main drawing. After that, I projected sections from plan with details. The hollow steel sections were connected to R.C. slab with anchor bolt and base plate. The separation of each horizontal hollow steel sections were kept at 125mm, 5 times of the height of each steel sections.
Figure 1.69 AC. Ledge Detail Drawings
Figure 1.70 AC. Ledge Detail Plan
Figure 1.71 AC. Ledge Detail Section
Page 36
INT60105 Internship Training and Report
4.0
4.0 Reflection
Reflection
Through this module, I gained up-to-date knowledge and get the opportunity to brush up my skills in a professional working environment. I realised that all the reverie and imagination towards architecture will end up compromising under practicality and economy issue. I learned how a good design would work under real-life situation with proper construction details and reasonable dimension to all spaces. An architect must not only possess the ability to design but knowledge to all related fields. A workable building design would always come with comprehensive construction details proposal. I would like to express my sincerest appreciation towards Mr. Azmi, my supervisor at Akitek Akiprima. I gained insight towards different phases, from conceptual and schematic design stage to construction and issued drawings stage by working on different projects under his extensive guidance. I was exposed to multiple real-life issues regarding to practicality and cost-efficiency of design which were not thoroughly considered during design studio projects in university. Also, I would like to express my gratitude for Ar. Lee Sze Ee as my academic supervisor during the internship period for her enlightening encouragement and commitment.
Page 37
INT60105 Internship Training and Report
5.0
5.0 Appendix
Appendix
Page 38
INT60105 Internship Training and Report
5.0 Appendix
Page 39
INT60105 Internship Training and Report
5.0 Appendix
Page 40
INT60105 Internship Training and Report
5.0 Appendix
Page 41
INT60105 Internship Training and Report
5.0 Appendix
Page 42
INT60105 Internship Training and Report
5.0 Appendix
Page 43
INT60105 Internship Training and Report
5.0 Appendix
Page 44
INT60105 Internship Training and Report
5.0 Appendix
Page 45