IMIESA July 2021

Page 17

CORROSION MSC required berth repairs for its new docking site next to the new passenger terminal at the Port of Durban

Establishing a new docking site for MSC

Mediterranean Shipping Company, better known as MSC, required berth repairs for its new docking site next to the new passenger terminal at the Port of Durban. A multidisciplinary approach, employing purpose-designed products from Sika, provided an enduring solution.

S

tefanutti Stocks, as the main contractor, was awarded the project for both the berth repairs and the construction of the passenger terminal. The berth repairs entailed removing and replacing 42 bollards, as well as 21 fenders, together with the rehabilitation and strengthening of the concrete surrounding these installations. The entire rehabilitation programme took eight months to complete. The primary specialist was Engineering Projects and Naval Architecture, which designed and planned the project. Doing the specialist work were main contractor Stefanutti Stocks Coastal, together with two subcontractors – Structural Maintenance as well as Holmes Cutting and Coring. The project and quality managers were sourced from Turner and Townsend.

Process To start, Holmes cut out and removed the existing damaged bollards and their anchoring bolts. The team then cored 16 holes per bollard, at a racked angle to allow for the new reinforcing – each 80 mm in diameter and 8 m deep. The existing

Various Sika products were employed to ensure structural integrity

tyre fenders were removed and the quay wall stabilised. On completion, each of the 16 core holes were filled with a high-strength cementitious grout, SikaGrout-212. Sika UCS-01 ZA, an underwater admixture that forms a jellylike substance when used with a cementitious product, was used in conjunction with SikaGrout-212 to prevent small sand particles washing away. Sika UCS-01 ZA was also used by Structural Maintenance for the grouting installation on the new bollards and core holes. Once the installation of the bollards was complete, rehabilitation between the new and existing concrete was required. This was carried out using SikaGrout-212 and a joint sealant system comprising Sika Primer-3N and Sikaflex Pro-3i. This joint sealant system filled in and sealed all cavities, voids, gaps, and recesses. The use of these products created a neat, uniform look around each bollard and allowed for movement between the old and new substrates. Sika’s joint sealant system was also used around the outer edges of the repaired areas.

Deadman anchor block The so-called ‘deadman anchor block’ needed to be rebuilt 20 m inside of the main quay wall, spanning the full 400 m length of

the berth. It’s a massive concrete anchor that supports the bollards and helps resist the forces exerted on them by the huge, docked ships. Construction of the deadman anchors required an initial base unit of cast concrete. Sika Rugasol-2 liquid was used as a surface retarder to prevent the concrete from setting, and to provide a key before the second layer was cast upon it. To ensure the berth wall was structurally sound, three new anchoring rods were installed between the deadman anchors and the bollards. Sika Antisol E was applied to cure the concrete and prevent shrinkage cracking from rapid water loss.

Challenges Along with the ever-changing tides, and seawater seeping into the core holes, the contractors also had to deal with the narrow tolerances around the large Y40 reinforcing bars. The areas surrounding the construction site were also situated on reclaimed land. This presented problems through the presence of old oil, fuel pipes, old railway lines, water lines and the main electrical feed to the entire port. Working around these historical objects made every task a little more difficult. Despite the unique conditions, and unexpected challenges of this project, Sika’s specialised products ensured success.

IMIESA July 2021

15


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Admixture accelerators for cold conditions

2min
page 57

Turning concrete waste into a resource

2min
page 54

The FUSO FJ26-280C HYP receives a stamp of approval

6min
pages 50-51

A variety of solutions for driver management

2min
page 53

Lifting with a difference

4min
pages 48-49

Local knowledge key to success of cross border projects

6min
pages 44-45

Affordable technology that builds brick businesses

4min
pages 46-47

Infrastructure news from around the continent

4min
pages 42-43

Inclusionary housing: addressing the elephants in the room

3min
page 40

Youth participation in the social housing value chain

2min
page 41

University switches to green energy

1min
page 39

Working towards a just energy transition

2min
page 38

Substation upgrade for new data centre

2min
page 37

Trenchless techniques are optimal for urban zones

1min
page 35

Energy efficiency starts with consumption

2min
page 36

Riverbank training and protection

4min
pages 28-29

Whistleblowing hotlines for municipalities

5min
pages 30-31

Unpacking barriers for women in construction

4min
pages 32-33

Geogrids in civil engineering applications

5min
pages 26-27

Empowerment through quality, education and training

6min
pages 24-25

uMshwathi Regional Bulk Water Supply Scheme Phase 2

5min
pages 22-23

Asset maintenance is a lifelong journey

4min
pages 18-19

The BUILD programme makes every project count

6min
pages 12-13

The future of surveying

6min
pages 14-16

Editor’s comment

4min
pages 5-6

Repairing concrete with concrete in sewer systems

8min
pages 8-11

The durability of steel for bulk water delivery

4min
pages 20-21

Establishing a new docking site for MSC

3min
page 17

President’s comment

2min
page 7
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.