IMIESA July 2021

Page 22

WATER & WASTEWATER

uMshwathi Regional Bulk Water Supply Scheme Phase 2 Umgeni Water appointed Hatch to design and manage the construction of the uMshwathi Regional Bulk Water Supply Scheme Phase 2. This comprised a 15 km, 700 mm diameter steel pipeline between War tburg and Dalton, two booster pump stations, and a 10 Mℓ reser voir.

T

he project was located in the uMshwathi Local Municipality north-east of Pietermaritzburg in KwaZulu-Natal. The municipality falls within the uMgungundlovu District Municipality, which is responsible for the supply of water to consumers within this region.

Booster pump stations The 58 Mℓ/day Mpolweni pump station was designed and constructed at km 19.3 on the 27.7 km long 850 mm diameter pipeline built in Phase 1. The pipeline had been constructed under a separate contract and was practically complete at the time of commencement of the construction of the pump station. The

20

IMIESA July 2021

Mpolweni pump station consists of three pumpsets in parallel with a combined installed capacity of 900 kW, with future upgrading planned to 2.25 MW. The pumpsets installed for the initial two duty points were designed to run at 860 rpm and 1 065 rpm, respectively, using variable-speed drive (VSD) technology – allowing for flows rates from 1 620 m3/h to 2 180 m3/h. The pump station has been configured to operate with a single duty pump when required. Consisting of two pumpsets with a combined installed capacity of 1.5 MW, the 41 Mℓ/day Dingle pump station operates with one pump on duty and one pump on standby. These pumpsets are designed to run at 1 350 rpm and 1 450 rpm, respectively, using

The Dalton Reservoir site

PROJECT TEAM Client: Umgeni Water Principal design consultant and construction manager: Hatch Electrical consultant: Adamastor Consulting Cathodic protection consultant: Paradigm Projects Environmental consultant: Afzelia Health and safety agent: ORM Principal contractor: Icon Construction Mechanical and electrical subcontractor: Oro Projects / Electron

VSD technology. This allows for flow rates from 980 m3/h to 1 320 m3/h. A future third pump was allowed for in the design, where two pumps will operate as duty with a third pump on standby. The Dingle pump station was constructed about two thirds down the Phase 2 pipeline route to boost pressure in order to supply the Dalton Reservoir. Using the VSDs, these pump stations can meet projected system demands to 2035 using the same mechanical and civil infrastructure (including pumps). In order to achieve the ultimate 40-year demands, only the motors and the electrical switchgear would need to be upgraded, which will be necessary due to their design life in any event.


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Admixture accelerators for cold conditions

2min
page 57

Turning concrete waste into a resource

2min
page 54

The FUSO FJ26-280C HYP receives a stamp of approval

6min
pages 50-51

A variety of solutions for driver management

2min
page 53

Lifting with a difference

4min
pages 48-49

Local knowledge key to success of cross border projects

6min
pages 44-45

Affordable technology that builds brick businesses

4min
pages 46-47

Infrastructure news from around the continent

4min
pages 42-43

Inclusionary housing: addressing the elephants in the room

3min
page 40

Youth participation in the social housing value chain

2min
page 41

University switches to green energy

1min
page 39

Working towards a just energy transition

2min
page 38

Substation upgrade for new data centre

2min
page 37

Trenchless techniques are optimal for urban zones

1min
page 35

Energy efficiency starts with consumption

2min
page 36

Riverbank training and protection

4min
pages 28-29

Whistleblowing hotlines for municipalities

5min
pages 30-31

Unpacking barriers for women in construction

4min
pages 32-33

Geogrids in civil engineering applications

5min
pages 26-27

Empowerment through quality, education and training

6min
pages 24-25

uMshwathi Regional Bulk Water Supply Scheme Phase 2

5min
pages 22-23

Asset maintenance is a lifelong journey

4min
pages 18-19

The BUILD programme makes every project count

6min
pages 12-13

The future of surveying

6min
pages 14-16

Editor’s comment

4min
pages 5-6

Repairing concrete with concrete in sewer systems

8min
pages 8-11

The durability of steel for bulk water delivery

4min
pages 20-21

Establishing a new docking site for MSC

3min
page 17

President’s comment

2min
page 7
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.