IMIESA July 2021

Page 37

POWER SYSTEMS

Substation upgrade for new data centre Actom Power Systems has secured a new data centre self-build substation contract in Gauteng, funded by Growthpoint Proper ties. Wor th over R50 million, the project involves the complete refurbishment of the 132/11 kV Kosmosdal-A substation in Samrand, Centurion.

T

his is the third substation contract that Actom Power Systems has been awarded within the past three years by a private sector company on a self-build basis, by arrangement with a municipality for the supply of power to a new or extended data centre. The previous two contracts were for substations in the City of Ekurhuleni. The first of these, completed in September 2019, involved an extension of the 132/11 kV Airport super substation next to O.R. Tambo International Airpor t in Kempton Park, while the second, awarded in November 2020, and due for completion in October this year, is for the new 88/11 kV Long Avenue substation. Originally referenced as Witfontein Ext. 90, the Long Avenue facility includes provision for additional power supply to enable substantial further development throughout northern Ekurhuleni. Meanwhile, the Kosmosdal-A substation contract, awarded at the end of Februar y 2021, and overseen by consulting engineers Geopower, is scheduled for completion by Januar y 2022.

Responding to the curved balls “Working to an already tight programme, we have had to field a couple of cur ve balls to ultimately achieve a workable execution plan,” says Hannes Horn, senior contracts manager, Actom Power Systems, who is responsible for the Kosmosdal-A substation contract. The first was the discover y that an original equipment manufacturer in Europe,

which Actom had routinely approached to manufacture specialised 132 kV disconnecting circuit breakers in the past, had unexpectedly discontinued its production line after initially quoting for the supply of this equipment. “As a result, we’ve had a mad scramble to explore various alternative compactdesign solutions, as well as tr ying to locate substitute suppliers that could still meet the local deliver y constraint without negatively impacting the overall programme,” Horn explains. The second complication posed an even greater threat of impacting the entire data centre development programme, beyond merely the substation portion of the works. A local manufacturer, with which the order for the two free-issue 40 MVA 132/11 kV power transformers had been placed, suffered a devastating fire at its factor y in March. “This serious setback was successfully overcome by negotiating with our customer to incorporate the supply of the two power transformers into our contract and switch the manufacture thereof to our in-house factor y, Actom Power Transformers, instead. While some overall delay slippage was unavoidable, we have still managed to curtail this to within the constraints of the broader data centre deadline,” Horn remarks.

Turnkey interfaces The other Actom businesses involved in product supply are: • A ctom High Voltage Equipment: conventional circuit breakers, isolators,

Apart from the imported specialised 132 kV disconnecting circuit breakers required for part of the refurbishment of the 132/11 kV Kosmosdal-A substation, due to space constraints, the rest of the substation will have a conventional open-yard configuration. A recent example, shown here, is a portion of a substation extension erected by Actom Power Systems in Kempton Park two years ago

ear th switches, current transformers, voltage transformers and surge arresters • Actom Distribution Transformers: NECRT transformers • Static Power: batteries and chargers • Actom Protection & Control: protection and automation systems • Actom Electrical Products: all power and control cable and accessories required to renew the substation. The 11 kV switchgear will be free-issued by the City of Tshwane for relocation to the substation.

IMIESA July 2021

35


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Admixture accelerators for cold conditions

2min
page 57

Turning concrete waste into a resource

2min
page 54

The FUSO FJ26-280C HYP receives a stamp of approval

6min
pages 50-51

A variety of solutions for driver management

2min
page 53

Lifting with a difference

4min
pages 48-49

Local knowledge key to success of cross border projects

6min
pages 44-45

Affordable technology that builds brick businesses

4min
pages 46-47

Infrastructure news from around the continent

4min
pages 42-43

Inclusionary housing: addressing the elephants in the room

3min
page 40

Youth participation in the social housing value chain

2min
page 41

University switches to green energy

1min
page 39

Working towards a just energy transition

2min
page 38

Substation upgrade for new data centre

2min
page 37

Trenchless techniques are optimal for urban zones

1min
page 35

Energy efficiency starts with consumption

2min
page 36

Riverbank training and protection

4min
pages 28-29

Whistleblowing hotlines for municipalities

5min
pages 30-31

Unpacking barriers for women in construction

4min
pages 32-33

Geogrids in civil engineering applications

5min
pages 26-27

Empowerment through quality, education and training

6min
pages 24-25

uMshwathi Regional Bulk Water Supply Scheme Phase 2

5min
pages 22-23

Asset maintenance is a lifelong journey

4min
pages 18-19

The BUILD programme makes every project count

6min
pages 12-13

The future of surveying

6min
pages 14-16

Editor’s comment

4min
pages 5-6

Repairing concrete with concrete in sewer systems

8min
pages 8-11

The durability of steel for bulk water delivery

4min
pages 20-21

Establishing a new docking site for MSC

3min
page 17

President’s comment

2min
page 7
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.