Madison & Paulina Hotel & Retail - Building Summary
ALLOWABLEGROSS
NET AREASKEYSPARKING COUNTSSTATISTICS
(FAR)(TOTAL)PARKINGCIRCSERVICESLOBBYRETAILAMENITYLODGING EXTR OPENSGLDBLSUITELUXTOTALNON-ACCHOTELTOTALFLOORAVERAGEEFFICAREAAREAAREAAREAAREAAREAAREAAREAAREAAREAKEYSKEYSKEYSKEYSUNITSPARKINGPARKINGPARKINGHEIGHTAREAIENCY (SF)(SF)(SF)(SF)(SF)(SF)(SF)(SF)(SF)(SF)(#)(#)(#)(#)(#)(#)(#)(#)(FT)(SF)(%) 2,5002,5002,20015.00
NOTES:
1. THERE IS NO PARKING ON SITE
2. SERVICES AREA INCLUDES MECHANICAL ROOMS & ALL HOTEL BACK OF HOUSE SPACES
3. ROOF AREA INCLUDES GREEN ROOF
4. AMENITY AREA INCLUDES FITNESS CENTER, VENDING AREAS, ROOFTOP LOUNGE
5. CIRCULATION AREA EXCLUDES HOTEL LOBBY & RECEPTION.
6. LODGING AREA EXCLUDES BALCONY AREAS (IF ANY), AND IS MEASURED FROM: EXTERIOR FACE OF EXTERIOR WALL CENTER OF DEMISING WALL CORRIDOR FACE OF CORRIDOR WALL
7. ALL AREAS ARE APPROXIMATE AND SUBJECT TO FINAL, AS-BUILT MEASUREMENTS
Madison & Paulina Hotel Schematic Construction Budget Summary
Date: Prepared By:Linn-Mathes Inc.
Prepared For:
Madison & Paulina Hotel
1690 W. Madison St. Chicago, IL
Schematic Construction Budget Detail
Date:
May 16, 2018
Document References:
1FitzGerald Associates Concept Drawings dated 4/16/18
2FitzGerald Associates Building Summary dated 4/16/18
3FitzGerald Associates Zoning Summary dated 4/17/18
4FitzGerald Associates Conceptual Rendering - Option A dated 4/17/18
Prepared By:Linn-Mathes Inc.
Prepared For:JLL Construction Services
Project Data (LM Take-offs from 4/16/18 FitzGerald Concept Dwgs)LegendSchedule
or
be closed and site fenced out to edge of closed parking
is
as it appears there is no paid parking on these streets
Demolition of temporary man/material hoist foundation
Demolition of existing trees (with required forestry permits)
Disconnect of existing utilities (water, storm, sewer, electric, gas, cable, phone) - NIC as site assumed to be clear of these items prior to start
Survey of existing site for environmental (Asbestos, Lead, UST's, PCB's, etc.) - NIC as site assumed to be clear of these items prior to start
Hazardous Material Abatement - NIC as site assumed to be clear prior to start
Removal of UST's - NIC as site assumed to be clear prior to start
Unpaid City Water Bills on existing property - NIC and to be paid by others
Structural Concrete foundation elements, beams, columns, floors, core walls, stairs, etc.
Crane Pad (install)
Tower Crane and Operators (duration of job and approx. 2 weeks post topping out)
Tower crane infill slab on level 2
Upturned parapet concrete at levels 2, 9 and roof evels
Conditions assumed to be required
Floor prep of slabs to turnover to flooring for final skim and prep
Hoist foundation
detention tank under 1st floor slab on grade (approx. 50'x15'x8')
Column and beam structure for window wall screen element at main roof level
4.10UNIT MASONRY
CMU at Interior and Exterior of 1st floor, including:
Reinforced cores as required
CMU Lateral Support at head of walls (assume Heckman #419 dowel and sleeve type)
Loose lintel install (furnished by others) at doors and openings
Interior Movement Joints
Ratings on CMU as noted on plans
Scaffolding
Face Brick Veneer System at Exterior of 1st floor, including:
Over CMU block wall assemblies and a weather barrier system by others
Modular Face brick - assume Endicott Smooth Ironspot or similar
Running bond patterns assumed
1.5" glass-mat faced exterior rigid insulation over CMU in cavity wall
40 Mil flashings, stainless steel drip edges, termination bars, weeps, brick ties
Standard colored and concave tooled mortar joints
Loose lintel install (furnished by others) at doors and openings
Exterior Movement Joints
Scaffolding
Masonry Cleaning
Decorative Wall at Lobby (CMU wall, insulation, Marble panels on girt rain screen system)
Granite and CMU curb at base of 1st floor storefront window system
No masonry assumed above 1st floor (all walls above 1st floor assumed to be metal stud and gypsum board or concrete structural elements)
Masonry Mock-ups are NIC
Masonry testing services are NIC
Cast stone or natural stone elements are NIC as none are shown or assumed to be required
Winter Conditions for Mason (tarping, heater rental, maintenance, gas hoses, hook-ups, etc.) are NIC as work is assumed to be in summer months
5.30METAL FABRICATIONS
Misc. Metals, Structural Steel, Angles, etc. including:
Elevator sump pit covers and frames, shop primed, furnished and installed
Elevator pit ladders, shop primed, furnished and installed
Elevator divider beams and embeds, non-primed, assume one at each floor, furnish and install
Elevator full height guide rail posts, non-primed, assume (1) per level between 1st and 2nd, 8th to 9th and 9th to roof, furnished and installed
Elevator Hoist Beams, non-primed, furnished, installed by elevator trade
Stair Rails for A, B, shop primed, Code and ADA compliant, anchored to concrete stair landings and stringers, furnish and install
Wall mounted access ladder from main roof to penthouse roof for access, galvanized, furnish and install
Loose Lintels for interior CMU wall door openings, shop primed, assume back to back 3x3x3/8 angles, furnish only
Beams for overhead door and storefront head support at 1st floor, galvanized, attached to concrete columns, furnish and install
Loose Lintels for exterior CMU and face brick door and window openings, galvanized, furnish only
Galvanized pipe bollards with studded base for anchoring into concrete base, assume 6 total on project, furnish only
Galvanized brackets and misc. angles at screen wall roof to detail windows to back up concrete framing
5.40DECORATIVE METAL AND RAILINGS
Glass and aluminum rails at 2nd floor terrace and 9th floor terrace
42" high above finished deck, face mounted to building parapet
7/16" thick clear laminated glass panels
Aluminum, pre-finished, vertical posts, wall brackets and top rail
Allowance: 1st floor decorative column cover SW corner (pre-finished aluminum custom cover over concrete)
Allowance: 9th floor terrace decorative steel trellis beams and columns (steel, setting, anchoring, finish painting, etc.)
No permanent site fencing or gates are shown or assumed to be required
No decorative metal rails, grilles, stairs, or other elements are shown or assumed to be required
Window Bucks are NIC and assumed to not be required (windows attached to concrete and/or CFMF)
for toilet accessories in unit bathrooms is NIC and assumed to not be required; done with toggles and screws
60 LF at $300/LF)
Allowance: Lobby Decorative Wall Paneling and Accents, Furnish and Install (assume 350 SF at $80/SF)
Allowance: Lobby Sundry Wall Cubby Millwork, Furnish and Install (assume 2 units or setups at $3,000 each)
Allowance: Kitchen Cabinets/Millwork and Countertops Furnish and Install (assume 50 LF at $450/LF)
Allowance: 9th floor Wood Bookshelves (frame/support, veneer, hardware, etc. for a complete assembly furnished and installed)
Allowance: 9th floor Meeting Room Charge Bar built-in Table (frame/support, veneer, top, hardware, etc. for a complete assembly furnished and installed)
Allowance: 9th floor Lacquered Wall Decorative Panels (panels and hardware for a complete system assembly furnished and installed)
Allowance: 9th floor Credenza Casework (cabinets, top, veneer, hardware, etc. for a complete assembly furnished and installed)
Allowance: Misc. Back of House Shelving, Cabinets, etc. affixed to building, Furnish and Install (assume 200 LF at $50/LF)
1st floor Lobby Fire Alarm Command Panel (FACP) Enclosure is NIC - assume panels are mounted in wall and exposed to view
7.10WATERPROOFING AND DAMPROOFING
Elevator pits - assume bentonite system on exterior walls and under slab
Traffic Coating System at Back of House MEP Rooms at 1st floor and Penthouse
at frost walls
Waterproofing for Storm Water Detention Tank - assume inside tank on floor and walls with cold liquid applied; confined space work
Foundation insulation - assume 2" rigid insulation around perimeter and 3' below grade
Wall and Ceiling thermal and Sound Insulation - Included in Division 09 - Framing and Gypsum Board Assemblies
Wall Stud Cavity Insulation - Included in Division 09 - Framing and Gypsum Board Assemblies
Insulation - Included in Division 07 - Roofing and Flashing
7.30WEATHER BARRIERS
Air and Water Weather Barrier applied to all exterior walls - assume a fluid, roll-on product such as Grace Perma-Barrier behind all metal panel, soffits and face brick systemsLS
7.40ROOFING AND FLASHING
Roofing Systems for Level 2 East Terrace and Level 9 East Terrace
Henry Hot fluid applied roofing system
Reinforcement
Protection Sheet
Modified bitumen flashings
Aluminum termination bars
Stainless Steel counterflashings
EFVM Test and Report
6" 60PSI EPS insulation to achieve R-30
Root Barrier at green areas
20 year warranty
Copings and flashings - .050 aluminum in standard colors
Roofing Systems for Level 2 NW Corner Roof, Main Roof, Penthouse Roof
Modified Bitumen vapor barrier, torch applied to concrete
Minimum R-30, ¼” per foot tapered polyisocyanurate insulation, adhered with foam adhesive
1/2" thick dens deck cover board
.060 TPO roof system, fully adhered
EFVM Test and Report
Walk pads at maintenance paths of main roof and outside roof hatches
Root Barrier at green areas
Stainless Steel counterflashings
20 year warranty
Copings and flashings - .050 aluminum in standard colors
Temporary Roofing at protection canopies, man hoist dock, offices, etc.
Metal Wall Panels at Louver vertical bands on all four primary elevations
Soffit Panel System at 1st floor entry area and other 1st to 2nd floor soffit overhangs
Metal Panels at Penthouse Exterior Walls are NIC - walls assumed to be clad with DAFS product described and included in Division 09 (Framing and Drywall)
7.60FIRE AND SMOKE PROTECTION
Fireproofing is NIC as no structural steel appears to be required
Misc. Interior caulking - not covered by finish trades
Misc. Exterior caulking - not covered by window, mason or metal panel trades - control joints, misc. openings and accessories
Firestopping at floor and wall penetrations - misc. not included by MEPFP, mason and framing/gypsum board trades
Firestopping and Firesafing at top of CMU walls
Fire Caulking and Acoustical Caulking at Gypsum Board wall assemblies - Included in Division 09 - Framing and Gypsum Board Assemblies
Expansion Joints and Covers - NIC as none believed to be required
8.10DOORS, FRAMES AND HARDWARE
Guest Room Entries
Hollow Metal Door Frames - Furnish Only - fire rated and labeled, welded one-piece, 2" face frame
Wood Doors (prefinished stained oak grade) - Furnish Only - fire rated and labeled, solid-core insulated
Hardware - assume BB hinges, closer, privacy viewer, battery operated FOB keyed mortise lever lock, seals on door jambs and head, chain
Guest Room Bathrooms
Hollow Metal Door Frames - Furnish Only - non-fire rated, welded one-piece, 2" face frame
Wood Doors (paint grade) - Furnish Only - non-fire rated, solid core
Hardware - assume hinges, privacy mortise lockset, no closer, no seals
Stairs
Hollow Metal Door Frames - Furnish Only - fire rated and labeled, welded one-piece, 2" face frame
Hollow Metal Doors - Furnish Only - fire rated and labeled
Hardware - assume bb hinges, closers as needed, mortise locksets (passage)
Common Areas and BOH (stud walls)
Hollow Metal Door Frames - Furnish Only - fire rated and labeled as required, welded one-piece, 2" face frame
Hollow Metal Doors - Furnish Only - fire rated and labeled as required
Hardware - assume bb hinges, closers as needed, mortise locksets, types as required (privacy, passage, storeroom, etc.)
BOH (Masonry walls)
Hollow Metal Door Frames - Furnish Only - fire rated and labeled as required, welded one-piece, 2" face frame
Hollow Metal Doors - Furnish Only - fire rated and labeled as required
Hardware - assume bb hinges, closers as needed, mortise locksets, types as required (privacy, passage, storeroom, etc.)
Exterior (Masonry walls)
Hollow Metal Door Frames - Furnish Only - Galv, Insulated, fire rated and labeled as required, welded one-piece, 2" face frame
Hollow Metal Doors - Furnish Only - Galv., Insulated, fire rated and labeled as required
Hardware - assume bb hinges, closers as needed, mortise locksets, types as required (Storeroom)
Guest room closet doors are NIC as no closets are planned for in rooms - all FF&E Furniture
Door Frames, Doors and Hardware for openings between guest rooms (interconnecting rooms) are NIC as none are shown or assumed to be required
8.20SPECIALTY DOORS AND FRAMES
Overhead Doors, including:
Dock / Loading Door - assume size of 10'-0" wide and 9'-0" tall
Insulated, sectional door with no windows, standard colors
Non-Fire Rated
Motor Operation with safety photo eyes and safety bottom edge; LV/ push button controls
Weather seals
3" high lift track
100,000 cycle springs
Maintenance of door during construction - assume two (2) trips
8.30WINDOWS
Window Systems for Levels 2 through Roof as follows:
Flush wall, non-captured style slab to slab window wall system
Low-e insulated glass units
Assume 140 operable vents, 20% with ADA compliant hardware
2-coat 70% PVDF standard color paint on exterior exposed aluminum / Powder coated paint on interior aluminum
Assume spandrel glass and insulated back pans at approx. 10% of area for interior wall geometries
Assume pre-finished aluminum brake formed metal panels at backside of glass units at window screen element at roof level
Two (2) terrace doors on level 9
Insulated glass slab edge covers
Window Systems for Level 1 as follows:
Flush wall, non-captured style slab to slab window wall system
Low-e insulated glass units
No operable Vents
2-coat 70% PVDF standard color paint on exterior exposed aluminum / Powder coated paint on interior aluminum
Three (3) medium stile storefront doors with standard hardware
One (1) ADA Door Operator
One (1) Manual Revolving Door
Minimal louvers glazed into head of storefront for MEP exhaust/intake needs in lieu of glazing
Assumes City of Chicago Building code for wind loading of 25 PSF for flat walls and 30 PSF for corners on building under 250' in height
Shop drawings and Stamped PE Calculations
Two Lines of caulking/sealant assumed
Window Consultant - Shop Drawing Review, QA / QC assessment during shop drawings, order process, install and punchlist
Windows - screens for operable vents and doors are NIC as assumed to not be required or part of desired design
Windows - Testing (lab or on site) is NIC and assumed to be by others if required
Windows - Window Washing Stabilization Anchors (Buttons) on exposed Facades - NIC as it assumed building is not tall enough to require them and façade is not steppedNIC
Windows - Any special Glass or systems for sound deadening or increased STC ratings is NIC and assumed to not be required
Windows - Mockups for testing or aesthetics are NIC and assumed to not be required
8.40ROOF HATCHES AND SKYLIGHTS
Two (2) roof hatches at 2nd floor to access East and NW roof levels from 1st floor interior
No skylights assumed
8.50GLAZING, MIRRORS, INTERIOR STOREFRONT
Shower Doors - 6' wide glass enclosure made of a fixed panel and swing door, frameless, 3/8" thick glass, 6" C style pull in chrome, 78" tall - assume all guest room unitsLS
Mirrors at Guest Rooms - assume 42" high and width of vanity tops, frameless with a bottom j-channel
Mirrors at Public Toilet Rooms - framed 24x36 with SS edging, standard sizes, not back lit, furnish and install
Interior Storefront - 1st Floor Lobby in misc. areas - assume 2x4 standard finish aluminum system with 1/4" thick clear tempered glass
Interior Storefront - 9th Floor Amenity in misc. areas - assume 2x4 standard finish aluminum system with 1/4" thick clear tempered glass
Glazing - Misc. clear, tempered sidelite glass at doors in common areas
Mirrors - Guest Room Living Area Wall Hung Full Length Mirrors - NIC and assumed to be FF&E by Others
Louvers: Assume pre-finished aluminum, 2" standard blade size, approx. 50% free area, drainable and with bird screens
Vertical PTAC units on guest room floors2,730
Exhaust for Com Ed Vault30
Exhaust for Electric Switchgear Room20
Exhaust for EM Generator30
Exhaust for Commercial Laundry Area20
Exhaust for light Kitchen Area20
Intake for Com Ed Vault30
Framing and Gypsum Board Assemblies, including:
Exterior CFMF, sheathing at louver bands and Penthouse
Engineering and shop drawings for CFMF stud work
Interior walls for unit demising (assume 3-5/8" studs at 24" OC, two layers of 5/8" gypsum board both sides, 3 1/2" unfaced fiberglass batt insulation)INCLUDED
Interior walls for corridors - assume same as unit demising walls
Interior rated walls for office, common areas, mechanical areas that are not CMU, misc. areas - assume same as unit demising walls
Interior rated metal stud and gypsum board shaftwalls with batt insulation at elevators chutes and other typical locations
Wall putty pads at electrical boxes, top and bottom wall caulking
Skim Coat Ceilings on all units, floors 2-7
Suspended drywall ceilings on all units at floor 8
Suspended drywall ceilings on all common areas, unit bathrooms, lobbies, offices on floors 1 and 9, corridors 2-8
Drywall expansion joints detailed and located per industry standards
DAFS system applied to exterior penthouse walls
Skim coat exposed round concrete columns in finished spaces and units
Sound and fire caulking of partitions per plans and details
Thermal and Sound Batt Insulation in all wall assemblies
Wall Mounted Strapping for Stair handrail attachment
Soffit assemblies, misc. framing and drywall
Access Panels, Furnished and Installed
Acoustical Ceilings, including:
33% of Lobby/Lounge/Meeting Area: 2'x2' exposed grid suspended ceiling with Armstrong Ultima Vector tiles as clouds or features
Amenity select areas on floors 1 and 9: Hunter Douglas Baffle Ceiling as clouds or features
Sound and acoustic isolation hangars for ceilings are NIC and assumed to not be required
Level 5 taping and skim coats are NIC as they are assumed to not be required
Acoustical consultants, testing, verification of installed systems, etc. are NIC and assumed to be by others if required
SYSTEMS
Public Space Carpeting, including:
Carpet Tile at Common Area Corridors on Floors 2 through 8, Furnished and Installed
Carpet Tile at 1st floor Office, 9th floor Meeting Room and Lounge, Furnished and InstalledMaterial Allowance Included:$40.00SYINCLUDED
Metal Transition Strips As needed at flooring changes and doorways INCLUDED
Moisture Testing on Concrete subflooring as required by the flooring manufacturer INCLUDED
Public Space Tile, including:
Large Format Porcelain Tile Flooring at 1st Floor Bar, Lounge, Reception, Concierge, Elevator lobby and two passenger elevs, F&I.Material Allowance Included:$8.00SFINCLUDED
Matching Porcelain Tile Wall Base at 1st Floor Bar, Lounge, Reception, Concierge, Elevator lobby, F&I.
Allowance Included:$4.00LFINCLUDED
Glazed Porcelain Tile Flooring at Public Toilet Rooms on Floors 1 and 9, Furnished and InstalledMaterial Allowance Included:$3.50SFINCLUDED
Glazed Porcelain Tile Wall Base at Public Toilet Rooms on Floors 1 and 9, Furnished and InstalledMaterial Allowance Included:$4.00LFINCLUDED
Glazed Porcelain Wall Tile (5'-0" wainscot) at Public Toilet Rooms on Floors 2 and 9, Furnished and InstalledMaterial Allowance Included:$3.50SFINCLUDED
Elevator S-1 Quarry Tile Flooring and Base with Underlayment, Furnished and Installed Material Allowance Included:$4.50SFINCLUDED
Metal Transition Strips As needed at flooring changes and doorways INCLUDED
Public Space Tile Floor, Wall Base and Grout Sealer, Furnished and Installed LS
Public Space Resilient Flooring and Wall Base, including: LS
Rubber Wall Base (RWB) 4.25" high at BOH spaces, service elevator lobbies, service elevator cab, stair landings, Furnished and Installed INCLUDED
Vinyl Composition Tile (VCT) 12"x12" Flooring at BOH spaces, service elevator lobbies, service elevator cab, stair landings, Furnished and InstalledINCLUDED
Metal Transition Strips As needed at flooring changes and doorways INCLUDED
Moisture Testing on Concrete subflooring
full height all walls, on Floors 2-8, Furnished and InstalledMaterial Allowance Included:$3.00 SFINCLUDED
Caulking between tile floor/base and shower bases
Metal Transition Strips As needed at flooring changes and doorways
Guest Room Tile Floor, Wall Base and Grout Sealer, Furnished and Installed
Guest Room Resilient Flooring, including:
Luxury Vinyl Tile (LVT) glue-down type with integral backing at Guest Rooms on Floors 2-13, Furnished and InstalledMaterial Allowance Included:$3.00SFINCLUDED
Metal Transition Strips As needed at flooring changes and doorways
Moisture Testing on Concrete subflooring as required by the flooring manufacturer
Floor Protection - labor and material for temp protection on finishes during construction
Allowance: Floor Prep after concrete work for Resilient and Carpet Flooring - assume skim of floor areas to flatten, Furnish and Install by flooring trade
Attic Stock Material is currently NIC
Moisture Mitigation Systems or Product Labor and Material is NIC as it is not known if or where it would be required
Crack Isolation Membranes under tile work (units or common areas) is NIC
Waterproofing systems (labor and material) under flooring or wall tile work is NIC
AND WALLCOVERING
Painting and Wallcovering, including:
Paint Guest Room Ceilings - Flat
Paint Guest Room Bathroom Walls - Eggshell
Paint Guest Room Bathroom Ceilings - Eggshell
Paint Guest Room Bathroom Doors and Frames - Semi Gloss
Paint Common Area and BOH Walls - Eggshell
Paint Common Area and BOH Ceilings - Flat
Paint Common Area and BOH Doors and Frames - Semi Gloss
Paint Common Area Doors and Frames - Semi Gloss
Paint exposed ceilings in basement - Flat
Blockfill and Paint all CMU in BOH spaces - Semi Gloss or Eggshell
Paint Stair Handrails and Guardrails on all levels - Semi Gloss
Paint Stair walls - Flat
Paint wall base in Guest Rooms and Common Areas - Semi Gloss
Wallcovering - Furnish and Install VWC for Guest Room walls (assume 2 walls)
Wallcovering - Furnish and Install VWC at Elevator Lobbies, all floors
Material cost assumed per SY:$20.00INCLUDED
Material cost assumed per SY:$25.00INCLUDED
Wallcovering - Furnish and Install at 1st floor and 9th floor Amenity spaces (2 walls each at Lobby, Bars, Lounge, etc.)Material cost assumed per SY:$25.00INCLUDED
Paint exposed to view shelf angles and lintels at exterior doors and windows
Misc. Painting and Touchups
Elevator Doors and Frames are pre-finished and no paint in field is assumed to be required
All stair landings, treads, risers are assumed to be concrete and no paint required
All Exterior items other than those listed are pre-finished and assumed to need no field painting
Exposed concrete ceilings in BOH spaces, storage rooms, mechanical rooms/closets, etc. are assumed to be left unpainted - Paint is NIC
Room and Directional Interior Signage (Assume vinyl two-color signs with ADA text and braille, tape/adhesive applied to wall surfaces) Furnish and Install
Informational Kiosks, directories, other misc. specialty displays are NIC and assumed to be by owner or management if required
Allowance: Corner Guards (Assume stainless steel 4'-0" tall x 4" x 4" at wall and door corners of high traffic areas on all floors, adhered to surface, furnish
Guest Room Medicine Cabinets are NIC and assumed to not be required
Guest Room Consumable Dispensers and Consumable Products (soap, shampoo, lotion, etc.) are NIC and assumed to be provided by others
Public Toilet Room Consumable Products (soap, lotion, etc.) are NIC and assumed to be provided by others
10.30FIREPLACES AND STOVES
Allowance: Lobby Fireplace Feature - assume furnish and install of ventless unit, including electric hook-up, necessary special framing, supports, finishes on surrounding
Allowance: 9th Floor Amenity Fireplace Feature - assume furnish and install of ventless unit, including electric hook-up, necessary special framing, supports, finishes on surrounding
Allowance: Lobby Water Feature - assume furnish and install of wall mounted unit, including water, electric hook-ups, necessary special framing, supports
Guest Room fireplaces are NIC and assumed to not be required
10.40SAFETY SPECIALTIES
Fire Extinguishers and Fire Extinguisher Cabinets - assume wall mounted FE's in back of house areas and recessed Aluminum cabinets for FE's in public areas
Hose Valve Cabinets are NIC as standpipes and valves are in stairs and hoses / hose cabinets are assumed to not be required
Emergency First Aid Stations, Supplies, AED Defibrillator Machines are all NIC and assumed to be provided by the owner or management as needed
10.50STORAGE SPECIALTIES
Post Office Delivery and Drop Boxes for Lobby - assume two (2) total boxes that meet USPS standards and are wall mounted in lobby or near front door
Staff Locker Room Lockers - assume 64 total lockers (32 double stack units) pre-finished steel, ventilated, with sliding handles for separate lock
Staff Locker Room Benches - assume one (1) bench in each room
Closet Shelving, Hooks and Hangers are NIC as none are shown in public or guest room areas
Storage Lockers are NIC as none are shown or assumed to be required
Interior Bike Racks are NIC as none are shown or assumed to be required
Exterior Bike Racks are listed in Division 32 under Landscaping
Package Room Storage Systems and shelving and lockers are all NIC as none are assumed to be required
Flag poles
accessories are NIC as none appear to be shown or required
Domed Mirrors for vehicle access are NIC as there appears to be only exterior loading space at rear of building accessible via alley
Pest Control (except for during construction) is NIC and all work and devices assumed to be by owner / operator
Flags, Banners and non-permanent signs are NIC and assumed to be by owner / operator
Allowance: Commercial Laundry Washers and Dryers, assume two (2) of each - Furnish and Install
Office
computers, fax machines, etc. all are NIC and assumed to be provided and installed by Owner/Manager of Property post construction
No appliances, equipment or special devices are included for Guestrooms - all are NIC and assumed to be provided and installed by Owner/Operator of Property post constructionNIC
Engineered, Stamped Layout and Shop Drawings
Cast in place roof anchors, exposed at roof areas, concealed at paver areas, furnished only
Cast in Place Roof Davit Bases, exposed at roof areas, concealed at paver areas, furnished only
Davit Arms and Adaptors, furnished only - Assumed two (2) sets of two (2) arms each set
On Site Load Tests and Certifications of Installed Anchors and Bases - OSHA required mandate - assume two separate mobilizations
Swing Stages, Ropes, Equipment, etc. for use in window washing and façade work - NIC and assumed to be provided by vendor(s)
Façade Stabilization Anchors or Tie-Backs are NIC as the building is assumed to be not tall enough to require them
Trash Containers and Dumpsters for operations and daily use by Owner are NIC and assumed to be provided by refuse vendor
Trash Compactor for operations and daily use by Owner is NIC and assumed to be provided by refuse vendor
12.10ARTWORK
All Wall hung artwork and framed itemsNIC and assumed to be provided and installed as FF&E by Others
All applied graphics, stickers, banners, etc.NIC and assumed to be provided and installed as FF&E by Others
12.20WINDOW TREATMENTS
Roller Shades for Guest Room Unit Windows - Furnish and Install, assumed scope as follows:
Mechoshade Thermoveil Dense Basketweave 1300 Series 5% Openness Factor
Manual chain operation, no power
Aluminum Finish Valance
Assume one (1) shade per window lite, not framed opening - assume approx. 665 shades
Assumed to be mounted to ceiling, not direct to window system
Roller Shades for Amenity and Lobby Area Exterior Windows - Furnish and Install
Mechoshade Thermoveil Dense Basketweave 1300 Series 5% Openness Factor
Manual chain operation, no power
Aluminum Finish Valance
Assume one (1) shade per window lite, not framed opening - assume approx. 87 shades
Assumed to be mounted to ceiling or to framed wall jamb returns - not direct to window system
Drapery at all Amenity Areas (1st floor Lobby/Office, 9th Floor Amenity Spaces)
Assume a Sheer fabric, such as Carnegie, Space 101555-111 on white track - fullness, folds and hems per specs
Roller Shade Attic Stock is NIC
Drapery Attic Stock is NIC
12.30CASEWORK AND COUNTERTOPS
Public restroom wall hung floating wood and framed vanities, Furnish Only
Public restroom counters, White Quartz, 2CM thick, Furnish and Install
Guest Room wall hung floating wood and framed vanities, Furnish Only
Guest Room Vanity Counters, White Quartz, 2CM thick, Furnish and Install
Three (3) passenger elevators and one (1) service elevator using MRL technology and Layouts
Passenger: Each car is 3,500 lb capacity, 350 FPM speed, 9 total stops, center opening 3'-6"x7'-0" door
Passenger: Each car 1st and 9th floor landings have SS doors and frames; all other floors have Manuf. Standard pre-finished baked enamel paint on doors and
Passenger: Each car has standard cab interiors with Plastic laminate wall panels, SS hand rails and SS ceiling system with 6 light LED downlighting
Passenger : Car group has standard hall lanterns and single station call buttons
Service: 4,000 lb capacity, 200 FPM speed, 10 total stops, center opening 4'-0"x7'-0" door
Service: All floors have Manuf. Standard pre-finished baked enamel paint on doors and frames
Service: Steel Shell interior walls, SS hand rails and painted white ceiling system with 6 light LED downlighting
Service : Car has standard hall lanterns and single station call buttons
Maintenance, Protection, Refurbishment of one (1) car during construction
Temporary Communication System for one (1) car during construction
Linen Chute - 24" diameter, 16 gauge, 'B' label rated doors at floors 2 through 9
Eight (8) 15x8 bottom hinged hand operated "b" label intake doors with lever handles and UL listed
Rubber Baffles on doors
One (1) flushing spray head located at top floor
One (1) disinfecting unit with access door
One (1) coat of sound dampening material with isolator floor pads at support frames to structural floor
One (1) rolling discharge charge with fusible link at base of chute
wet and dry pipe sprinkler systems for Project. All design, material and installation will be in accordance with City of Chicago Fire Prevention
for storm water detention vault work
System Training, Commissioning and closeout for/with Ownership
Design Review Consultant (review base design, misc. coordination items, misc. field visits, closeout and commissioning work)
per the provided plans and narrative
Vertical PTAC Units with exterior grilles, remote mounted thermostats and distribution ductwork for approx. 27 of the 140 units based on current layoutsINCLUDED
Condensate drainage system
Toilet Exhaust riser system with duct collection and regulating dampers tied to bathroom light switches
Corridor make-up air unit located on roof with duct work down through building
Two (2) packaged roof top units to serve 9th floor amenity spaces
One (1) DX VAV system to serve 1st floor
Eight (8) FPB/VAV boxes with electric heat and duct distribution
Gas piping for two (2) commercial laundry dryers, two (2) DHWH's, one (1) MAU and two (2) RTU's
One (1) cooling RTU for elevator control room
One (1) Ductless split system for the 1st floor MDF room cooling
Exhaust systems for Pump Rooms, EM Generator, Com Ed Vault, Switchgear Room, 1st floor rooms
DDC Controls
Project System Training, Commissioning and closeout for/with Ownership
MEPFP Design Review Consultant (review base design, misc. coordination items, misc. field visits, closeout and commissioning work)
Typical floor electrical and low voltage closets/rooms - no exhaust system required
Stairwell pressurization systems are NIC and assumed to not be required
Smoke Exhaust systems are NIC and assumed to not be required
Black iron kitchen exhaust is NIC
26.10ELECTRICAL SYSTEMS
Complete Electrical Systems, including:
Electrical system per plans and narrative and as outlined below
Design-Build Services
Hotel Room lighting consists of:
Semi-surface LED downlight at entry and at bathroom
LED vanity wall sconce fixture over mirror at bathroom
Lighting fixture allowance included for guest rooms is $56,000
Typical corridor lighting consists of:
Surface mounted LED ceiling fixtures
Two LED Drum fixtures at the elevator lobby
Wraparound style LED surface mounted lights for stairs and utility rooms
Lighting fixture allowance included for corridors s $35,000
Common area lighting consists of:
Wraparound style LED surface mounted lights for stairs, utility rooms, storage rooms, BOH corridors, MEP rooms
Occupancy sensors as required - local room types
250 KW diesel indoor EM generator with day tank, fuel system and exhaust system
Exit signs, EM lighting, EM outlets as required by code
Elevators to be sequenced to run one at a time on EM power for recall; EM power in elevator cabs via batteries (by elevator trade)
One (1) 1200 Amp 208/120 bus duct riser for guestrooms, One (1) 600 Amp 480/277 feeder riser for mechanical equipment,
One (1) 250 Amp 480 riser for penthouse elevator equipment, One (1) 200 Amp 480 service for the fire pump
Grounding as required
Lighting control for the main lobby and entrance area included; all other areas use switches or sensors as necessary to control lighting
Exterior lighting includes service lights at exit doors and service doors and also includes a $10,000 allowance for decorative sconces or other misc.
Combination SD/CO detectors, hard wired, in each unit
SD and CO detectors, hard-wired, where required by narrative and code outside units
Buildout allowances currently included for electrical and lighting systems are assumed to be as follows: Additional Allowances included for Decorative Lighting:
Utility work includes Three (3) 5" raceways from Property line to Com Ed Vault, two (2) 4" PVC raceways from Property Line to MDF room
Power and Raceway for illuminated Marquis Signs
Conduit and rough-in as needed for Low Voltage Scope described in Division 27, and as follows:
Fire caulking for electrical work
Temporary power and lighting for site and construction offices
Project System Training, Commissioning and closeout for/with Ownership
MEPFP Design Review Consultant (review base design, misc. coordination items, misc. field visits, closeout and commissioning work)
Utility work engineering, design or construction work is NIC
High Tower Lock release relays and circuits for stair doors are NIC as not believed to be required
Lightning Protection is NIC and is an alternate bid if desired
Life Safety System, including:
Design-Build Services
Fire alarm system with main command panel and 1 remote DGP panel
Smoke Detectors at required MEPFP rooms, elevator machines and lobbies
Heat Detectors at generator and elevator machines
Duct Smoke Detectors with sampling tubes and remote test stations
One (1) FA speaker in each guest room unit
Visuals in communication type rooms as required
Speaker/Visuals in Common Areas and exterior public areas/roof decks
Sprinkler System monitoring devices
Stairway telephones and Speakers (4 assumed)
Elevator Recall Relays - recall via sprinkler system and lobby smoke detectors
Elevator Cab Speakers
Stair Gate unlocking circuits (2 assumed)
Project System Training, Commissioning and closeout for/with Ownership
High Tower Lock release relays and circuits for stair doors
Voice, Data and Television Systems, including:
Design-Build Services
Cables on J-hooks directly from outlets in guestrooms to IDF (1 CAT-6 bedside, 1 RG-6 and 2 CAT-6 to TV/Desk area typical)
Outlets trimmed with standard voice, data, TV jacks by Leviton or similar
Assume IDF closets on 4th floor and 10th floor minimum (not currently shown on plans) but ideally every floor for LV scope
Voice and Data cabling punched down to CAT-6 patch panels / TV cabling coiled in closets for service provider
Approx. 50 locations for common area voice, data and TV outlets (cables on J-hooks directly from outlets to MDF or IDF locations)
CAT-6 cabling to 24 wireless access points throughout building (2 per guestroom floors assumed)
CAT-6 cabling to 6 wireless access points throughout first floor spaces
Backbone cabling and for voice and data (CAT-3 cabling and 6-strand MM Fiber)
Fire caulking of cabling through sleeves or other penetrations (not in conduit)
Project System Training, Commissioning and closeout for/with Ownership
MEPFP Design Review Consultant (review base design, misc. coordination items, misc. field visits, closeout and commissioning work)
Television backbone and head end equipment
Phone, cable, satellite head end equipment
Phones, phone hardware, software, etc. for hotel system
Guestroom jackpacks or other special distribution devices
Wireless access point devices, programming, etc.
OF RESCUE COMMUNICATION SYSTEMS
Area of Rescue two-way communication system, including:
Services
AOR station at each stair landing
with cabinet and power supply
mounted master headset
No access control system included - assume all access granted through traditional physical keys or with door hardware equipped with reader technology (as a guestroom)NIC 27.50VIDEO SURVEILLANCE SYSTEMS
Video Surveillance System, including:
Services
22 cameras with licenses, software upgrades, fixed cameras, mix of interior and exterior grades
Head-end equipment, network switches, UPS, workstation (used in combination with access control system)
Sound System for 1st floor common area
Furnish and Install 2 conductor 16 gauge speaker cabling to ten (10) locations, mount 8" speakers
Run cabling back to closet head end for connection to equipment (final equipment and final connections to be by others)
mounted TV's and brackets are NIC and assumed to be provided and installed by ownership
Dock Intercom System (intercom at dock and main desk or security office)
Automation systems are NIC and assumed to not be required
31.10EXCAVATION AND SITE WORK
Site Clearing and Excavation
Clear asphalt parking lot, curbs, misc. fencing, planters, etc. remaining after owner demolition activities
Furnish, Install, Remove Temporary Construction Entrance (stone or brick ramp from ROW into site area)
Cut and Fill site profile to level out as needed
Pothole for caissons
Excavate detention tank, Elevators, Slab on Grade, grade beams, caisson caps; haul off as clean fill
Clean out rebar cages on caissons
Backfill elevator pit areas with recycled CA6 stone
Backfill grade beams and caisson caps with recycled CA6 stone
Furnish and Install recycled CA6 stone for slab on grade
Excavate for thickened slabs as needed
Sawcutting terminations of sidewalk, curb and gutter demolition
Remove curbs, gutters, sidewalks around property
Excavate for new curbs, gutters, sidewalks
Erosion Control Measures
Minimal dewatering of site as needed to keep work continuing
Place new stone for sidewalks, curbs and gutters with recycled CA6 stone
Flagger
Haul off of caisson spoils as CCDD clean qualified - assume approx. 600 CY of spoils
Street Cleaning - assume machine street sweeping during excavation operations
Dewatering Site - assume trash pumps in excavated areas with hoses to grade level to deal with perched water - assume no active groundwater
and stone work for tower crane base
Earthwork and Excavation and Site Prep
Allowance: Concealed & Unknown Conditions (obstructions, utility conflicts, existing foundations, tanks, soil conditions, etc. that were not known)
Soil testing and sampling and verification is NIC as it assumed the geotechnical report will qualify the site conditions
Caisson Spoil Removal for Non-CCDD type is NIC as all spoils removed from the site are assumed to be clean and qualified for CCDD disposal
Excavated Material Disposal for Non-CCDD type is NIC as all spoils removed from the site are assumed to be clean and qualified for CCDD disposal
Utility relocations required for remediation of contaminated soils in Right of Way is NIC and assumed to be by others or not required
31.20EARTH RETENTION AND SHORING $0$0.00
ERS Systems are NIC as it is assumed grade beams, grease trap, detention tank, elevator pits and crane pad can be open cut within confines of site
AND DESCRIPTIONS OF WORK
31.30SPECIAL FOUNDATIONS
Drilled Caissons - twenty seven (27) per plans:
Survey Layout of all caissons
As-Built drawings
F&I 5,000 PSI concrete assumed for all caissons
F&I Approx. 20' long reinforcing cages assumed
F&I Permanent corrugated liners
F&I Temporary heavy wall casings
F&I Flowable grout backfill for the annular spaces
F&I Sand backfill 2'-0" above caisson cut off elevations
Load caisson spoils
Assume one (1) mobilization with one (1) drilling rig, one (1) service crane and one (1) loader
Flagger
Street Cleaning
Extra caissons for tower crane pad are NIC - assume can use the cluster of caissons for building at SE corner of site
Camera Inspections of caisson bells is NIC and assumed it will not be required
Misc. Standby Time for caisson related work is NIC and assumed to not be required - See separate Allowance in Division 31 Excavation for Unknown & Concealed
Misc. Drilling Delays due to obstruction removals - NIC and assumed to not be required
Handling and disposal of special non-CCDD spoils - NIC and assumed to not be required
Special Installation Procedures and/or Monitoring requested by the City - NIC and assumed to not be required
on
and Paulina
lengths of site from East PL on Madison to North PL on Paulina)
(assume lengths of site from East PL on Madison to North PL on Paulina)
ADA crosswalks at alley (assume one (1) detectable embed)
ADA crosswalks at NE corner of Madison and Paulina (assume two (2) detectable embeds)
32.20EXTERIOR ASPHALT PAVING
Asphalt restoration work:
Mill, Resurface, Crack Fill Madison St. from new curb south to center of street as reqd by CDOT, striping to match exist. (assume PL east to CL of Madison/Paulina Intersection)INCLUDED Mill, Resurface, Crack Fill Paulina St. from new curb west to CL of street as reqd by CDOT, striping to match exist. (assume north side of alley south to Madison/Paulina Intersection)INCLUDED Mill, Resurface, Crack Fill entire alley as reqd by CDOT (assume entire width from Paulina east to PL) INCLUDED
32.30LANDSCAPING
Grade Level landscaping (trees, sidewalk grates, planting soil) - Four (4) trees with standard grates assumed
Grade Level Bike Racks - Four (4) steel standard loops bolted to sidewalk assumed
9th Floor Terrace Paver System; assume 67% of roof area (protection fabric, pedestals, Hanover Tudor finish architectural pavers, 2'x2'x2" thick)
2nd Floor Green Roof (root barrier, alum. edge restraints, drain mat, filter fabric, 4" deep media, prevegetated mat, river rock ballast, burmed media, twelve (12) shrubs)LS
9th Floor Green Roof; assume 33% of roof area (root barrier, alum. edge restraints, drain mat, filter fabric, 4" deep media, prevegetated mat, river rock ballast)
Main Green Roof; assume 50% of roof area (root barrier, alum. edge restraints, drain mat, filter fabric, 4" deep media, prevegetated mat)
Irrigation System is NIC and assumed to not be required
City Required Bond for Right of Way Landscaping is NIC and assumed to be provided by others
32.40EXTERIOR SIGNAGE
Allowance: F&I Exterior Building Address Signage Element at Lobby or Canopy (permit included)
Hotel Venue / Marquis signs are NIC - power and raceway for signs are included in Division 26 but signage is assumed to be F&I by others