BUILDING TOGETHER United Methodist Retirement Communities | Chelsea
ISSUE
12
December 2018
AERIAL VIEW OF THE PROJECT SITE
PROJECT MANAGEMENT UPDATE
Matt Wintjes Assistant Project Manager
Hang in there folks, the Kresge Addition is almost complete! Over the past month, the construction team has been focusing their attention on the center area and west wing. All of the flooring in the west wing is complete and the final touches are coming together. The final coat of paint and wallpaper is finished on the east wing and is also nearing completion on the west wing. All of the local MEP (mechanical, electrical, plumbing) have been completed. The bakery is almost ready for inspections as all the food service equipment is installed and the final connections are wrapping up. The trade contractors onsite have done a great job installing some intricate details, including suspended millwork panels and a stacked stone fireplace. Kudo’s to Dobie Construction and CIR for their attention to detail! Fun Fact: Over 77,250 man hours, involving approximately 468 trades people, have been worked onsite thus far! The common theme for the McMullen Wellness Center has been “coordination”. With the elaborate tile work on the horizon, the construction team has been working towards wrapping up all the work necessary to allow for the tile setters to do what they do best. This past month brought all the focus in on the trade contractors work above the pool deck. This included the HVAC trade contractor installing the hangars for the duct sock, the electricians installing their recessed can lights, framing of soffits and finishing of the wallboard. The masons also completed all of the block work for the restrooms/locker rooms for the pool and, last but not least, the architectural staircase has been installed on the south side of the building. From the construction team, we hope you all had a wonderful holiday and thank you for joining us for another edition of Building Together.
www.elzinga-volkers.com www.elzinga-volkers.com