ISSUE
12
Construction Update Newsletter
NOVEMBER 2017
Building Together Canterbury on the Lake - Facility Addition & Renovations
Iris Dining Room Demo
Monthly Funny
PM Summary Our crews have been working hard on the Memory Care Addition. In the North wing, the resident rooms are close to complete with carpet, tile, sheet vinyl, and final paint installed. The drop ceiling grid is installed in the common areas allowing for trades to put in their final fixtures. In the South Wing, the bathroom tile is nearly complete and the mechanical, electrical and plumbing infrastructure in the corridor is done. The memory garden is complete except the pergolas and a few final touches. I’m sure it will be very popular with the residents! The concrete and sitework crews have been taking advantage of any days without rain to be ready for asphalt paving. This has been a challenge because the clay soil takes a long time to dry out after rain. There has also been great progress on the connector bridge and all the utilities that go through the connector to serve the addition. The Iris dining room was taken offline and we have completed the demolition, framing and exterior walls of the expanded space. Crews have been added to focus on this area while not taking anyone away from our sprint to the finish line in the Memory Care Addition. Unfortunately, this influx has caused parking issues and we are working daily to limit our impact on Canterbury.
2016-2017 Michigan Contractor of the Year
In the Health Center, we are in the 9th and final phase of renovation. The temporary walls have been reconfigured, demolition is complete, and the floor has been cut and removed where new plumbing piping will be placed. This phase has the additional challenge of not having direct access to an outside door within the construction area. So, material and debris routes were carefully planned and are being kept clean throughout the day as we use them. We couldn’t thank the staff and residents enough for their patience through this process! Best regards,
2016-2017 WINNER Elzinga & Volkers, Inc.
Joe Novakoski, P.E. Vice President of Operations / Senior Project Manager joenova@elzinga-volkers.com