Building Together - Canterbury on the Lake - February 2017

Page 1

ISSUE

03

Construction Update Newsletter

FEBRUARY 2017

Building Together Canterbury on the Lake - Facility Addition & Renovations

Continue trench footings at interior walls

PM Summary

Monthly Funny

Project Activity is Ramping Up! The Memory Care & Health Center projects are starting to ramp up activity. Despite wintery conditions, foundations are underway for the Memory Care building. We’ve been employing traditional cold weather protections, which includes a ground thaw system to remove frost and insulated blankets to protect thawed ground as well as constructed foundations. For the Health Center, the Trellis between the Leas and Health Center entries has been removed. We are beginning the Rehab addition foundations, continuing on Phase 1 (Rehab Area) and beginning Phase 2 demolition. We’re wrapping up Phase 1A, awaiting a Bureau of Fire Safety inspection and some possible color changes. Best regards, Brad Frey, Senior Project Manager bradf@elzinga-volkers.com

2016-2017 Michigan Contractor of the Year

Freshly poured footing

2016-2017 WINNER Elzinga & Volkers, Inc.

2016-2017 WINNER Elzinga & Volkers, Inc.


SAFETYMatters

Building Together | Canterbury On The Lake Facility Addition & Renovations | February 2017

Memory Care/Connector

Safety Is Our Moral Obligation

Safety is not just a speech at Elzinga & Volkers, it’s a lifestyle, a conscious decision, the way we do business. We believe that it’s our moral obligation to send everyone home safely every day. Our families are the reason that we work safely and we will ensure that every single person who steps foot on your project site goes home safely to his or her family each night.

Looking Ahead Kevin Frye, Field Manager kevinf@elzinga-volkers.com | 269-365-8414

Memory Care/Connector Project Happenings » Trench Footings will be completed by the end of next week » Masonry Foundations are starting Monday, Februrary 13/ » Wall panels will be going up on Monday, February 27 (or sooner). » Storm Sewer is in progress, which should be complete by Monday, February 27. » Sanitary Sewer is following Storm Sewer and expected to be complete at the same time.

The Elzinga & Volkers executive team firmly believes that our safety program is successful because of our corporate culture. We focus on safety not to save time or money, but to save lives. The Elzinga & Volkers ethic is firmly rooted in care for our employees and their families. By creating a family environment among our employees, we encourage them to care not only for themselves, but for those with whom they work every day.

Major Milestones

Memory Care/Connector

Owner Occupancy Owners FFE Building Finishes Phase 9

Pouring concrete into trench footings

Building / Core and Shell

Phase 1

JAN DEC

Preparing for sanitary and storm sewer instalations

2016

2017

FEB

MAR

APR

MAY

JUN

Continuing to excavate for trench footings

JUL

AUG

SEP

OCT

NOV

DEC

» Water piping is starting Monday, February 20.

Sitework / Building Pad

Page 2 2016-2017 WINNER Elzinga & Volkers, Inc.


Building Together | Canterbury On The Lake Facility Addition & Renovations | February 2017

Health Care Renovation Looking Ahead Anthony Pipitone, Field Manager AnthonyP@elzinga-volkers.com | 586-265-1410

Renovation Project Happenings

Clearing brush to prepare ground for insulating blankets

DEC

Phase 9 - Completion

NOV

Phase 8

OCT

Phase 7

SEP

Major Milestones

Phase 6

Health Care Renovations

Phase 9

JUL

Phase 5 Phase 4

New carpet

Phase 1

Phase 3

Install sprinkler head location

JAN

2017

FEB

MAR

APR

MAY

Removing old carpet

JUN

AUG

» Phase 1: 90% complete with the exception of newly selected wall finish to better match furniture and the COTL style. » Phase 1A: 50% complete. Phase 1A and the Phase 1A Addition complement each other in respect to the schedule and will be given back to COTL on the same date. » Phase 1 Addition: Clearing of bushes and ground ivy is complete and the footing excavation has begun. » Phase 2: Demolition has begun. Carpet, toilets, sinks and counter tops have been removed. Concrete removal and underground plumbing is about to begin for the resident room bathroom reconfiguration.

Phase 2 Phase 1 A Phase 1

Selecting paint for corridor wall

Page 3 2016-2017 WINNER Elzinga & Volkers, Inc.