Construction Update Newsletter
MAY 2017
Building Together Canterbury on the Lake - Facility Addition & Renovations
Memory Care Addition
Monthly Funny
PM Summary Crews making great progress despite a rainy spring I’ve joked with the project team that every time I visit the project site, it rains. Some think there's a black cloud following me to Waterford Twp. every week or two, but I’m hoping it’s just a coincidence. While the wet spring has slowed progress a bit, it has not stopped the crews from making great strides on the Memory Care Addition. As you can see, most of the roof trusses and sheathing are now in place. What you can’t see are the large areas of concrete floors that have been poured. The progress on the Connector and Bridge has also been slowed by the weather, as well as a few buried “opportunities” that had to be worked through. The good news is that the issues have been worked out and progress can continue.
Some guys can really make their job look like a lot of fun!
2016-2017 Michigan Contractor of the Year 2016-2017 WINNER Elzinga & Volkers, Inc.
Over at the Rehab Addition, the steel has finally been installed and the concrete floor poured. After all the challenges in this area, it feels good to have this small addition out of the ground! In the Health Center, Phase 3 was started and finished in just 3 short weeks. The crews found their groove and everyone hit their marks to turn over this space in great shape and ready to receive its new residents. Best regards, Joe Novakoski, P.E. Vice President / Senior Project Manager joenova@elzinga-volkers.com
2016-2017 WINNER Elzinga & Volkers, Inc.
Rehab Addition steel structure
SAFETYMatters
Building Together | Canterbury On The Lake Facility Addition & Renovations | May 2017
Memory Care/Connector Looking Ahead Kevin Frye, Field Manager kevinf@elzinga-volkers.com | 269-365-8414
Memory Care/Connector Project Happenings
Elzinga & Volkers has a contract with a third party safety consultant who makes visits to our construction sites as project scopes warrant or at a manager’s request. Our consultant audits the site for current and upcoming safety violations and potential risks. A summary from each visit is shared with our trade contracting team stating, not only safety concerns, but what the teams are doing well. This third party consultant does not fine companies for safety violations, but focuses more on protecting worker safety and helping contractors avoid costly write-ups from organizations like MiOSHA, the state occupational safety authority. These audits save time, money and, most importantly, the lives of workers on-site.
Major Milestones
Memory Care/Connector
Owner Occupancy Owners FFE Building Finishes Phase 9
SEP
OCT
NOV
DEC
» Complete concrete slab-on-grade at the Memory Care building (see concrete progress pictures below) » Place interior demising walls » Complete roofing system to Memory Care building » Install vinyl windows » Begin in-wall MEP rough-ins » Set steel for bridge » Pour concrete slab-on-grade at the Connector » Begin framing at the Connector and bridge
Third Party Safety Consultant Visits
Building / Core and Shell
MAY
JUN
JUL
AUG
Concrete-1
Phase 1
JAN DEC
Concrete-3
2016
2017
FEB
MAR
APR
Concrete-2
Sitework / Building Pad
Page 2 2016-2017 WINNER Elzinga & Volkers, Inc.
Building Together | Canterbury On The Lake Facility Addition & Renovations | May 2017
TEAM SPOTLIGHT
Health Care Renovation Looking Ahead
Who’s Who On Site Meet Joe Novakoski
Anthony Pipitone, Field Manager AnthonyP@elzinga-volkers.com | 586-265-1410
Upcoming Renovation Project Happenings »» Beginning Phase 7-8 with new finishes and ceramic tile in the hospice rooms »» CC117-SNN volunteer office will get new wall and flooring finishes »» Phase 1 addition work includes plumbing/mechanical roof penetrations, roofing, rough framing, and MEP wall rough wall
Joe Novakoski is the VP of Project Management at Elzinga & Volkers Construction Professionals (E&V) and is the Senior Project Manager for the Canterbury on the Lake Facility Addition and Renovation. Joe’s 22 years of industry experience (all at Elzinga & Volkers) have given him the opportunity to work in all facets of the construction process on a variety of project types, sizes, and levels of complexity. In his free time, Joe enjoys spending time with his family. He has four daughters who keep him very busy. He and his wife, Jen, are anxiously awaiting the arrival of baby number five by the end of May! Joe also enjoys golfing, yard work, and training to run marathons. He uses destination marathons as a reward for the long training cycles and a chance to see new places.
Health Care Renovations
Phase 9
Phase 9 - Completion
OCT
NOV
DEC
Major Milestones
Phase 4 4 week duration
Phase 6
JUL
Phase 5
JUN
32 day duration
Phases 7 and 8
MAY
AUG
SEP
Phase 3 corridor
Phase 3
4 week duration
Phase 1
JAN
2017
FEB
MAR
APR
Phase 3 resident room
4 week duration
Phase 1 Rehab and Addition work in progress. The expected completion date for the addition is the week of June 5-9.
Phase 3 bathroom
Page 3 2016-2017 WINNER Elzinga & Volkers, Inc.