ISSUE
11
Construction Update Newsletter
OCTOBER 2017
Building Together Canterbury on the Lake - Facility Addition & Renovations
Fire Lane Progress
Monthly Funny
PM Summary Great Progress! As the leaves begin to change, the Memory Care continues to change as well. On the exterior, the fire lane around the building has progressed from the Southeast all the way up to the new main entrance. On the inside, the North Wing is deep into finishes with all the resident rooms painted and the resident bathrooms tiled. In the corridors on the North Wing, the lean rails and door casings are all but complete. On the South and West Wings, drywall hanging and finishing is about 85% complete. Above ceiling mechanical rough-in’s continue to take place in the South and West corridors, and resident room trim work is nearing completion. Outside in the Memory Garden, the colored concrete sidewalks have been poured and top soil has been brought in for landscaping. Inside the Health Center the final push is now upon us! Phase 4 finished up this week giving Canterbury back their much needed dining room and new nurse’s station. Phase 4 was our biggest and one of the most challenging phases of the Health Center renovation. We will be starting Phase 9 (which is the final phase) this week as we flip construction over to the other side of the temporary wall from Phase 4.
2016-2017 Michigan Contractor of the Year 2016-2017 WINNER Elzinga & Volkers, Inc.
Best regards,
Joe Novakoski, P.E. Vice President of Operations / Senior Project Manager joenova@elzinga-volkers.com