Volume 1, Issue 32
Created By:
October 14, 2013
Project Update The overall project progress is coming along nicely. The brick façade on the east elevation was completed on Friday. With this task finished, the majority of the brick on the building is in place. The remaining three elevations have more glass and metal panels than the east elevations so TL Masonry will continue to make significant progress. While TL Masonry focused on the east elevation, Bouma was able to install the rest of the metal studs, sheathing and Tyveck on the other three elevations. Vos Glass has also been making great progress. They mobilized on-site last week and have been building their fabrication shop where they will cut each aluminum frame to length on-site as opposed to fabricating in their shop and shipping it out to the jobsite.
As the exterior continues to move along, the interior does the same. Van Dyken, Allied and Godwin are all working on the overhead main runs while the slab is still free of obstructions. Godwin’s main focus has been getting the roof drains tied in. When this is finished, Mikalan can start installing the roof to get one step closer to being in the dry. In addition, Elzinga and Volkers will begin placing temporary enclosures around the west elevation. This temporary wall will create a controlled space within the building, opening up the ability to increase production on the below-floor systems.
There is still a long way to go, but we continue to make progress every day!
Dustin Kuzee, Project Manager dkuzee@elzinga-volkers.com