Spectrum Health East Beltline Integrated Care Center

Page 1

Volume 1, Issue 3

Created By:

June 22, 2012 Project Update Since our last update we have made a few changes to our newsletter that we hope everyone enjoys. In regards to the project, we have wrapped up our first round of programming meetings with all of the practices. We have been assembling the information that we received and developing a programming summary which will explain the requested needs/wants of each practice. We would like to thank all of the practice managers and staff for working with us on the scheduling aspect because our needs are taking precious time away from their jobs; we want everyone to know that it is greatly appreciated.

Fun Fact Over the past couple of days everyone has been dealing with the extreme heat in this area, but did you know that the record high in the month of June is 102 degrees? The Grand Rapids area has reached this high twice in history: June 1, 1934 and then again on June 20, 1953. On the other end of the spectrum

We have also been continuing with the due diligence process to get the current PUD rezoned. Just this past Wednesday we submitted a package to the township for review that included phase one site plans, a master campus site plan, building elevation and some photos of 588 E. Lakewood. This submittal is intended to provide a representation of what our intention is with the site and the type of building that will be constructed. The township will review these documents and comment so we know what to expect at the June 26 public hearing. Attached to the end of this newsletter is a copy of the submittal package. Dustin Kuzee Project Manager dkuzee@elzinga-volkers.com

the record low temperature for the Grand Rapids area is 32 degrees on June 4, 1944.


Page 2

Track the Project’s Progress as the Forest Grows!

Programming

Basis of Design/SD

Design Documents

Construction Documents

Project Forecast In the upcoming weeks there will be two major project tasks that will occur. The first task is the Township public hearing when the submittal package will be introduced to the community. This is a meeting that is critical to our success because it will be where the rezoning will be recommended. There have been numerous conversations regarding this project and there shouldn’t be an issue with this review, but it will be the first time the public will get to see the concept plans. It will be interesting to hear what the community thinks of the plans. The second task that will start next week is round two of programming meetings. Currently we have the following practices scheduled for a second meeting: Continuing Care Radiology Primary Care and Urgent Care Pediatrics Women’s Health Neurosciences In these meetings we will be reviewing the information that was given in the first meeting as well as sharing potential agencies and needs. After this meeting, we will be one step closer to starting schematic design documents. Along with programming meetings, E&V + IA will be finalizing the Basis of Design in the next couple of weeks. With this document finished, E&V will be able to start doing some budgeting so we can start validating the project’s current budget.

+


June 20th New PUD Submittal Package to Grand Rapids Township (Located on the following pages)

+


non-motorized path - not required along 3 mile phase 1

3 Mile Road NE

building setback line along adjacent parcels

75’ 140’

parking setback line along adjacent parcels 50’

building setback line along NE Beltline Overlay District

top

East Beltline Ave (northbound)

bus s

storm water detention

potential future walking path around site- connects to sitewalk along street

172

proposed shmg clinic

non-motorized path

drive to u/g parking

future addition 75’

11 99

outside edge of northbound lane (solid white line)

potential future driveway to Dunnigan Street

110

building summary: phase 1:

building area

50’

proposed shmg mob: underground parking:

75’

parking setback line along NE Beltline Overlay District

50’

drop off

90’

Dunnigan Street

145

100,000 sf 15,000 sf

parking provided: (typ space 9’x18’, 24’ drive aisle) surface parking under-building parking

N scale

Phase 1 Concept Site Plan

0'

20120205 80'

160'

320'

parking required

500 -

537 40 577

18 June 2012

SHMG East Beltline

© 2012 Integrated Architecture All rights reserved No part of this document may be used or reproduced in any form or by any means, or stored in a database or retrieval system, without the prior written permission of Integrated Architecture

1


site amenities

non-motorized path- not required along 3 mile phase 1

1. intuitive access

• drives “lead” to building without stops • entry very visible • direct access to front door or parking

3 Mile Road NE

25’

2. convenient public transportation access

75’

• proposed bus stop on site • convenient pedestrian access to building along “greenway”

140’

outparcel b

outparcel a

75’

• landscaped pedestrian walkway links bus stop and future parcels • unique and identifiable element that leads to garden at building entry • screens staff parking • establishes a “softer”, less institutional expression

parking setback line along adjacent parcels

4. pedestrian collector

• patient flow from vehicles is guided to central walkay • improves pedestrian safety, controls pedestrian/ vehicle intersection • improves patient experience by extending the formal entry sequence to the building through the canopy

50’

building setback line along NE Beltline Overlay District

5. dedicated patient drop off | pick up

1

• covered for protection from weather • unique curvalinear architectural element that is identifiable as SHMG

3

• located close to building entry and out of vehicle flow

7. under-building parking

top

East Beltline Ave (northbound)

6. safe / convenient barrier-free parking

storm water detention

2

bus s

9

6 5 drop off

90’

6

Dunnigan Street

walking path around siteconnects to sitewalk along street

proposed shmg clinic

6

7

outdoor pedestrian walkway

10

• provides dedicated outdoor link between MOBs • campus landscape feature that potentially contains seating

9. visitor parking

• nearly all of visitor parking within 300’ radius of entry • safe pathway to building

10. staff parking

building summary:

future addition

outside edge of northbound lane (solid white line)

8. pedestrian building link

• distributed around building w/ access to dedicated staff entries

8

building area

proposed shmg mob: underground parking:

500 -

shmg mob addition: 38,000 sf future mob: 32,000 sf total medical parking required (5/1k sf)

190 160 850

surface parking under-building parking

future outlot phases: N scale

Concept Master Plan

0'

outparcel a: outparcel b:

14,300 sf 16,000 sf 20120205

80'

160'

parking required

100,000 sf 15,000 sf

parking provided: (typ space 9’x18’, 24’ drive aisle)

50’

75’

phase 1:

future medical phases:

future mob

1

50’

4

• maximizes site efficiency • secure / weather protected parking

10

75’

non-motorized path connects to walking path on site

parking setback line along NE Beltline Overlay District

3. “greenway”

building setback line along adjacent parcels

320'

873 40 913 parking provided

80 140

18 June 2012

SHMG East Beltline

© 2012 Integrated Architecture All rights reserved No part of this document may be used or reproduced in any form or by any means, or stored in a database or retrieval system, without the prior written permission of Integrated Architecture

2


3 2 1 0

scale

Concept Site Section

0'

20120205 30'

60'

120'

18 June 2012

SHMG East Beltline

Š 2012 Integrated Architecture All rights reserved No part of this document may be used or reproduced in any form or by any means, or stored in a database or retrieval system, without the prior written permission of Integrated Architecture

3


20120205

SHMG Holland Facility

18 June 2012

SHMG East Beltline

Š 2012 Integrated Architecture All rights reserved No part of this document may be used or reproduced in any form or by any means, or stored in a database or retrieval system, without the prior written permission of Integrated Architecture

4


20120205

SHMG Holland Facility

18 June 2012

SHMG East Beltline

Š 2012 Integrated Architecture All rights reserved No part of this document may be used or reproduced in any form or by any means, or stored in a database or retrieval system, without the prior written permission of Integrated Architecture

5


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.