DECEMBER 2016

Building Together Canterbury on the Lake - Facility Addition & Renovations

Meet Your Team!

Brad Frey Senior Project Manager

Memory Care Building Pad

PM Summary Welcome to Your Construction Update Newsletter! Nick Novakoski, Assistant Project Manager

We are excited to introduce “Building Together,” a monthly newsletter to keep you informed and upto-date on the Canterbury on the Lake construction progression. This newsletter will highlight team members, share tips for working safely on a construction site, provide a look ahead and progress pictures. We hope this newsletter keeps everyone engaged in the project, even if you are not able to see our work in person. The Memory Care addition and the Health Center renovations are now underway, but had a slow start. Due to start delays, mobilization has been a challenge for some of our contractors. It’s a busy year for everyone! Kevin, one of our Field Managers, has been able to successfully resolve all issues to keep the projects moving forward. Let’s hope for a mild winter to ensure project progress! Best regards,

Kevin Frye Field Manager

Brad Frey, Senior Project Manager bradf@elzinga-volkers.com

Anthony Pipitone Field Manager

Health Center Demolition

2016-2017 WINNER Elzinga & V olkers, Inc.


SAFETYMatters

Building Together | Canterbury On The Lake Facility Addition & Renovations | December 2016

Memory Care/Connector Looking Ahead

Cold Weather Protection

Prolonged exposure to freezing or cold temperatures may cause serious health problems such as trench foot, frostbite, and hypothermia. In extreme cases, including cold water immersion, exposure can lead to death. Danger signs include uncontrolled shivering, slurred speech, clumsy movements, fatigue, and confused behavior. If these signs are observed, call for emergency help. Hang in there – the cold weather will end soon!

Kevin Frye, Field Manager kevinf@elzinga-volkers.com | 269-365-8414

Memory Care/Connector Project Happenings » Complete grading of the roadway that will connect the main entrance & independent living center » Begin trench footings & concrete installations to footings » Masonry foundation walls » Underground MEP

Memory Care/Connector

Owner Occupancy Owners FFE Building Finishes Phase 9

OCT

NOV

DEC

Major Milestones

Building / Core and Shell

Phase 1

JAN DEC

2016

Site Cleaning

2017

FEB

MAR

APR

MAY

JUN

JUL

AUG

SEP

Site Excavation

Sitework / Building Pad

Page 2 2016-2017 WINNER Elzinga & V olkers


Building Together | Canterbury On The Lake Facility Addition & Renovations | December 2016

TEAM SPOTLIGHT Who’s Who On Site

& Happy New Years From Elzinga & Volkers

Health Care Renovation Looking Ahead

After initial budget concerns, C&R Plumbing & Heating was able to come in and meet the needs and requirements of the Canterbury on the Lake project. They are a diverse local trade partner from nearby Shelby Charter Township and have experience in all industries, including healthcare. C&R, as well as the rest of our partners, will play an extremely important role in the completion of this project and we are happy to have them aboard!

Major Milestones

Anthony Pipitone, Field Manager AnthonyP@elzinga-volkers.com | 586-265-1410

Health Care Renovations

DEC

Phase 9 - Completion

NOV

Phase 8

OCT

Phase 7 Phase 6

Phase 9

JUL

Phase 5

JUN

AUG

Construct Separation Wall Demo as related to Bulletin 2 Metal Stud Framing MEP in Rough In’s Sound Insulation & Gypsum Finishes

Phase 4 Phase 1

Phase 3

Plumbing installation

Plumbing installation

JAN

FEB

MAR

APR

MAY

Wall framing

2017

» » » » » »

SEP

Renovation Project Happenings

Phase 2 Phase 1 B Phase 1 A

Page 3 2016-2017 WINNER Elzinga & V olkers, Inc.


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.