ISSUE
13
SEPTEMBER 2013
Construction Update Newsletter
New Views Spectrum Health - Gerber Memorial
Upcoming Milestones
»» Steel Structure Begins P »» Foundation Walls Back Filled »» Drywall Installation Complete on the 2nd Floor
Executive Summary Steel is in the air!
We hit a major milestone this week on the ED expansion project. Crews from VanDellen Steel arrived on Monday and began installing the new building frame. Crews began with the basement columns and first floor structure. With this structure in place, crews can start backfilling the soil against our foundation walls. This allows work to begin on parking lots and sidewalks around the building. This process may sound fast, but since we are working hard to install asphalt this year, we have to finish before mid-November. On the second floor, crews are working to reroute plumbing and medical gasses to accommodate the location of new walls. The hospital staff has been fantastic in helping our team research utility routes and schedule shutdowns for service relocations. We could not be successful without their support. Thank you again!
In other areas of the second floor, drywall is being installed and sanded. We are still installing 10% of the framing, plumbing is being moved and new electrical, plumbing and medical gas lines are being roughed in. Overhead, new ductwork and fire protection lines are being positioned. Soon, all walls will receive drywall and finishes can begin. - John Parker, Project Manager jparker@elzinga-volkers.com
Wall Board Finishing at the East Nurse Station
www.elzinga-volkers.com