Construction Update Newsletter
New Views Spectrum Health - Gerber Memorial
QUALITY CONTROL The State of Michigan has jurisdiction over construction
Upcoming Milestones
projects at licensed
»» Final Inspections Complete »» Exterior Paving Complete »» Landscaping Complete
hospitals. When plans for a new addition or renovation are first created, they are
P
reviewed by an engineer in Lansing before being sent to a regional inspector. Once the construction is complete, the regional inspector comes to the project site and ensures compliance with both the design and health codes. This process is yet another level of verification that the new unit is safe for patient use.
Executive Summary Final Touches
We are pleased to announce that the new Emergency Department at Gerber Memorial Hospital passed a major milestone this week. On Monday, we received our official certification for occupancy from the State Health Department. This means that the new unit is ready for patients and staff, although there are still a few things left to complete before the new department is opened.
monitor locations in an effort to make the new space as efficient as possible for patient care.
Inside the building, Elzinga & Volkers and its team of trade contractors are completing the punch list, which is a list of small repairs and adjustments that need to be made to the building. Some examples of these small items include paint touch up and hanging final wall mounted accessories.
We hope everyone enjoyed the public open house this weekend and got a chance to see the new unit in person. If you were unable to attend, we will continue sharing photos of the new space in these final issues of New Views and on our Facebook page!
As the Gerber Memorial staff experiences the space for the first time, the construction team is making small tweaks to medical equipment and
On the exterior of the building, security cameras landscaping are being installed. Final touches on the parking lot include striping, signage and a thorough cleaning. This final area of construction will start in the third week of July.
- John Parker, Project Manager jparker@elzinga-volkers.com