ISSUE
09 JULY 2013
Construction Update Newsletter
New Views Spectrum Health - Gerber Memorial
SPOTLIGHT ON SAFETY Extension cords are used everywhere on construction sites. Normal wear and tear on cords can loosen or expose wires. Cords that are not 3-wire type, not designed for hard-usage or that have been modified increase your risk of contacting an electrical current. Here are some guidelines that Elzinga & Volkers uses to regulate the use of extension cords: »» Use only equipment that meets OSHA standards »» Do not modify or use cords incorrectly »» Use factory-assembled cords and only use the 3-wire type »» Remove cords from receptacles by pulling on the plugs, not the cord. Elzinga & Volkers takes electrical safety seriously. If an extension cord is found to be out of compliance with the rules above, our personnel are instructed to destroy the cord immediately.
Upcoming Milestones
»» Work Begins on ED Addition P »» New Surgical Waiting and PAT Open P »» Foundation Walls Complete on ED Addition
Executive Summary
Building a Strong Foundation
It’s been an exciting two weeks at the project site. What was once the ambulance drive and drop-off area for the emergency department has now been transformed into a large excavation for the new building addition. Concrete footings for the 14-foot basement walls were poured this week, along with the continued installation of underground utilities. Off-site, our steel building structure is in the final stages of fabrication. We are scheduled to have steel onsite and begin installation by the end of August. On the second floor, the new Surgical Waiting and PAT Offices have officially opened, which has allowed demolition crews to take over the west side of the new Pre-Post OP and Endoscopy unit. This area will quickly be
stripped down to the building structure so that framing crews can start on new wall layout. We anticipate that this area will catch up to the east side of the floor in just a few short weeks. On the east side of the second floor, workers continue to install new utilities and reroute existing utilities through new walls and chases. This work requires careful coordination with other areas of the hospital, as some utilities may be disrupted temporarily. As always, the Gerber staff has been very understanding and helpful in this process and we thank them all for that. - John Parker, Project Manager jparker@elzinga-volkers.com
www.elzinga-volkers.com