Construction Update Newsletter
INSIDE SCOOP Talecris Plasma Resources - Champaign, Illinois
Storefront
Project Update Staying on Track
Over the past month we have completed selective demolition and started asbestos abatement. Both activities have gone very well and we are keeping to our construction schedule. We have built a great team of trade partners and I’m confident this project will be very successful. Brad Giha, Project Manager bradg@elzinga-volkers.com
EIFS work
Asbestos Abatement
Demolition
www.elzinga-volkers.com
Inside Scoop - Construction Update Newsletter Talecris Plasma Resources - Champaign, IL - July 2016
Scott Chamberlain Field Manager scottc@elzinga-volkers.com Highest Honor... 3rd Consecutive year!
2016 DIAMOND AWARD
Office floor plan
The Look Ahead
Over the next couple of weeks we will be finishing up the asbestos abatement. Once completed we will hit the ground running with plumbing and electrical underground. Next, we will start framing walls and roughing them in with plumbing and electrical.
You can expect the following upcoming work: » Finish demolition » Finish asbestos abatement » Underground plumbing » Underground electric » Metal stud framing
SAFETY FIRST
MILESTONES COMPLETION FINISHES
ROUGH IN Roof structure FRAMING UNDERGROUND DEMOLITION
Crawl space
A term you might hear on our site but may not be familiar with is PPE, which stands for Personal Protective Equipment. Examples of PPE include items such as gloves, high visibility clothing, foot and eye protection, protective hearing devices, and hard hats. Some of these items, like hard hats and eye protection, are required 100% of the time on-site, while others, like gloves, are required only when performing certain tasks. Elzinga & Volkers exceeds MiOSHA standards when it comes to PPE to ensure that all of our workers return home safe every day.