Construction Update Newsletter
INSIDE SCOOP
June 2019
Clark at Franklin | Renovation Project
Ramp Demolition Exit 18
Where has the time gone? Spring is quickly fading towards summer and the project is charging towards the September finish line. Three and a half months from now all 22 apartments will be completed and the new residents we begin settling into their new accommodations, an exciting time for all of us! Exit 19 on the west side of the building is all but complete with some finish work that will take place towards the end of the project. To the north, Exit 18, on the Sherman Street side of the building is now in full construction mode. Last month, crews were able to demolish the old ramp, stairs and brick overhang. This allows for the new grand staircase to begin, giving this side of the building a nice face lift. Inside the building, progress continues to charge on as well. On the 2nd floor East, the drywall has been completed and the resident units are starting to be primed for paint. Along with that, installation of the new trim and casing has begun as well as setting many of the kitchen cabinets. The 2nd floor East phase continues to be on track for its end of July completion. On the 2nd floor West, mechanical, electrical and plumbing rough-ins have been completed and drywall is being hung throughout the phase. Last month I mentioned that we had broken this phase into 3 mini-phases, doing so has allowed for a great flow of the project and a smooth transition up to the 3rd floor West. On the 3rd floor West, framing has been completed with mechanical, electrical and plumbing rough-ins will continue to press on through the early part of June with drywall starting shortly thereafter. Stay tuned for next month’s update! Nick Novakoski, Project Manager
TRADE CONTRACTOR
SPOTLIGHT I would like to recognize Doug from Hurst Mechanical for leading the effort towards mechanical rough ins in the new independant living apartments. There definitely was some pressure to make sure the MEP rough ins stayed on schedule at Clark. Doug pulled in more guys to get his portion done on time. It’s a joy to work with guys like Doug that work hard, meet deadlines and just do what it takes to get the job done. Nice work Doug!
www.elzinga-volkers.com www.elzinga-volkers.com
Prep for New Stair Layout Exit 18
Upcoming Project Milestones: EJ Calloway, Field Manager
Prep for New Stair Layout Exit 18
Bathroom Rough-Ins 2ND Floor West
Trimwork 2ND Floor East
Kitchen Cabinets 2ND Floor East
The most recent milestone is that we completed all of our rough in inspections for the project. We are on to finishes. Woo-Hoo!
Track the Project’s Progress: Phase 1 - 3 East Phase 2 - 3 West Phase 3 - 2 East Phase 4 - 1 East Phase 5A - 3 West Phase 5B - 2 West Phase 6 - 1 West September 2018
October 2018
November 2018
December 2018
January 2019
February 2019
March 2019
April 2019
May 2019
June 2019
July 2019
August 2019
September 2019
www.elzinga-volkers.com www.elzinga-volkers.com