On Location_Clark at Keller Lake

Page 1

Construction Update Newsletter

INSIDE SCOOP

March 2020

Clark at Keller Lake | Renovation Project

Concrete Foundation Wall - Reinforcing Steel

Greetings All, As we turn the page on another month, we continue to turn many pages on progress here onsite. February was a big month for the project team as the buildings have begun to rise out of the ground in the form of the concrete foundations and walls. To date, the concrete crews have installed over 250,000 lbs. of reinforcing steel and have poured over 800 yards of concrete. To put into perspective how much work has been done, the amount of steel installed in pounds, equals the weight of a Railroad Locomotive Engine and the amount of concrete in yards placed, is enough to fill 161,580 gallons of milk! Placing this much concrete in such a short period of time required the sitework crews to work diligently to keep up with the concrete trucks coming in and out of the job site. Towards the end of the month, the city imposed their road weight restrictions which meant that we would not be able to haul off as much soil as we had initially planned in order to keep the job running smoothly. Our sitework contractor was adaptable though and found areas onsite where we could stock pile soil and keep the job moving. This was a big win for the team! As we look forward to next month, we will continue to have a month full of concrete and sitework. The masons will also join us onsite to begin erecting the stair and elevator shafts. Stay tuned for next month’s update! Nick Novakoski, Project Manager NickN@elzinga-volkers.com

TRADE CONTRACTOR

SPOTLIGHT This month’s Trade Contractor spotlight goes to Kent Companies. They have had multiple crews onsite and have done an outstanding job with the concrete foundation footings and walls. They have integrated well with the other trades on the project and their commitment to safety has been exceptional. A big thank you to Mike, Darryl, Mark and the rest of the team!

www.elzinga-volkers.com www.elzinga-volkers.com


Lower Level Parking Foundation Wall

Field Management Team E.J. Calloway Field Manager

&

Dan Jenema Sr. Field Manager

February Project Milestones Moving into March look out for Integrated Exteriors to begin constructing the masonry stair and elevator shafts. Soon we will get a good idea exactly how tall these buildings will be once the first shaft is fully constructed. We will continue constructing the foundation walls and we will also begin some underground electrical and plumbing which may not have much of a visual impact, but will be very import to the functionality of the building.

Lower Level Parking Foundation Wall

Concrete Footings

Concrete Footings

Concrete Foundation Wals

Track the Project’s Progress: Tree Clearing & Sitework Building Concrete & Precast Concrete Structural Steel & Wood Framing Building Dried In Drywall Interior Finishes Project Complete DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL 2019 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2021 2021 2021 2021 2021 2021 2021

www.elzinga-volkers.com www.elzinga-volkers.com


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.