Construction Update Newsletter

INSIDE SCOOP

October 2018

Clark on Franklin | Renovation Project

Welcome to the first edition of Inside Scoop – Clark on Franklin Renovation. My name is Nick Novakoski and I am the Assistant Project Manager overseeing the project along with Field Manager EJ Calloway. On August 27th, Elzinga & Volkers began work on the Clark on Franklin Renovation and Exterior Improvements. The project is slated to be complete by the end of September, 2019. The renovation consists of 5 phases ranging from minor interior updates all the way to a complete demolition of the 2nd floor and 3rd floor west wing to make way for 22 new independent living apartments, 12 of which will have balconies to the outside. On the exterior we will make room for a new 12 stall garage that will take the place of the old carport on the west end of the building. Out front, a new 18 space pre-engineered carport will be constructed along with a brand new entrance made out of stone and block to give the north side of the building a face lift. Over the last month, the first phase of the renovation, 3rd Floor East Aldersgate Skilled Nursing (3 East SN), has been tracking right on schedule. The construction team completed demolition, plumbing and electrical work needed to service the newly added resident room and office, as well as the pantry reconfiguration. New drywall, paint and flooring have also been installed to give the space a refreshed look. This first phase is scheduled to be turned over to Clark on November 6th, with residents moving back in on the 6th, 7th and 8th. On the exterior, the team continued to battle the elements and wet conditions while building the new 12 stall garage. The masons have worked diligently to get the block structure in place and ready for the trusses to arrive this week. Once the trusses are set the team will begin work on the roofing components to completely dry in the garage. Stay tuned for next months update! Nick Novakoski, Assistant Project Manager nickn@elzinga-volkers.com

TRADE CONTRACTOR

SPOTLIGHT Kenowa Plumbing, Inc Kenowa has been very enjoyable to work with. They are always responsive to the needs of the job. They are easy to work with but fun to joke around with as well. They follow our safety procedures and had there Site Specific Safety Plan, Company Safety Manual and SDS sheets turned in on time. Thanks for the great work Kenowa and keep it up so you continue your chance at the grill!

www.elzinga-volkers.com www.elzinga-volkers.com


Upcoming Project Milestones: EJ Calloway, Field Manager One major upcoming milestone is that our first phase of the job will be completed November 1st, allowing for resident moves the following week. And, although the weather has hindered our progress outside at times, we are still ahead of schedule with the new garage.

Garage floor.

Demolition of existing car ports.

Aldersgate office.

Split faced block walls for the new garage.

Track the Project’s Progress: Phase 1 - 3 East Phase 2 - 3 West Phase 3 - 2 East -Epworth Independent Living Phase 4 - 1 East Phase 5A - 3 West - Bristol Independent Living Phase 5B - 2 West - Oxford Independent Living Phase 6 - 1 West September 2018

October 2018

November 2018

December 2018

January 2019

February 2019

March 2019

April 2019

May 2019

June 2019

July 2019

August 2019

September 2019

www.elzinga-volkers.com www.elzinga-volkers.com


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.