Construction Update Newsletter

ON LOCATION

Samaritas - Saginaw Campus - Addition & Renovation

New Entry Progress

Project Update A lot has occurred in November and early December. The Davenport drop-off drive has been removed. Concrete work is complete for the new entry and therapy gym additions. The new entry and chapel are under roof and will be enclosed soon. Framing is underway for the therapy gym addition. Demolition and asbestos abatement is proceeding in the old entry area and the new memory care wing. We continue to encounter buried treasures of past remodeling that can create unexpected problems and redirection of efforts. The team is currently investigating some adjustments to the kitchen and rehab dining areas in an effort to create a better dining experience for those residents Additionally, the therapy gym will be getting new lighting during the Phase 4 renovation to improve lighting levels. Brad Frey, Senior Project Manager bradf@elzinga-volkers.com

www.elzinga-volkers.com www.elzinga-volkers.com


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
On Location | Samaritas Saginaw December 2017 by EV Construction - Issuu