ISSUE
05
FEBRUARY 2017
Construction Update Newsletter
ON LOCATION
Samaritas - Saginaw Campus - Addition & Renovation
New north elevation windows
Project Update
Making Great Progress! Phase 1 has been kicked into high gear as the end is beginning to come into sight. Drywall hanging and finishing is making its way through the south area of phase 1, working its way north with priming following close behind. Tile installation in the resident room bathrooms continues to make great strides as that too works its way from the south to the north. Exterior work is now complete on the addition with the masonry complete and the new windows in place. Stay tuned as the next month will surely be a busy one! Brad Frey, Senior Project Manager bradf@elzinga-volkers.com
New resident room nearly ready for carpet
www.elzinga-volkers.com www.elzinga-volkers.com
SAFETYMatters
On Location - Construction Update Newsletter Samaritas - Saginaw Campus - February 2017
Looking Ahead Safety Is Our Moral Obligation Mike Chrisman, Field Manager mikeC@elzinga-volkers.com | 616-610-9313
Phase 1 Progress Update:
» Cabinets & millwork have been delivered and installation will start soon. » Doors and hardware, corner guards, and handrails are scheduled for delivery. » Installation of the south wing carpet and base will start soon. » The fireplace in north east wing will have stone installed soon.
Resident shower ready for fixtures
South hallway preparing for ceiling
Safety is not just a speech at Elzinga & Volkers, it’s a lifestyle, a conscious decision, the way we do business. We believe that it’s our moral obligation to send everyone home safely every day. Our families are the reason that we work safely and we will ensure that every single person who steps foot on your project site goes home safely to his or her family each night. The Elzinga & Volkers executive team firmly believes that our safety program is successful because of our corporate culture. We focus on safety not to save time or money, but to save lives. The Elzinga & Volkers ethic is firmly rooted in care for our employees and their families. By creating a family environment among our employees, we encourage them to care not only for themselves, but for those with whom they work every day.
TEAM SPOTLIGHT Who’s Who On Site
Wobig Construction Company is a local general contractor located in Saginaw. They work on site as our framer, drywall hanger and finisher doing ceiling grids and also our concrete work. They have been our go-to contractor to help fill our self-performed labor gaps. A special thanks goes out to Brian Roth who stepped up and added drywall hangers and finishers to help move the schedule along. New private re-hab room nearly ready for paint
Track the Project’s Progress as the View Takes Shape!
92 days
Phase 1
58 days
Phase 2
39 days
Phase 3 Phase 4
79 days
68 days
Phase 5
80 days
Phase 6
www.elzinga-volkers.com
Completion