Construction Update Newsletter
ON LOCATION
Samaritas - Saginaw Campus - Addition & Renovation
Above Ceiling MEPs
Project Update It’s been a tough month for the Memory Care portion of Phase 3. We’ve encountered conduits embedded in the floor slab, some of which we accidentally cut. Due to those conduits, we’ve had to reroute much of the new underslab plumbing. We also found existing sanitary lines that are pitched in the wrong direction and damaged plaster in most of the resident rooms toilet areas. Despite these setbacks we keep moving forward. New windows, resident rooms & corridors are progressing well. Only the core area has suffered the setback. Completion of the Memory Care Wing is now scheduled for March 9th.
Brad Frey, Senior Project Manager bradf@elzinga-volkers.com