On Location - Samaritas Saginaw - June 2017

Page 1

ISSUE

07 JUNE 2017

Construction Update Newsletter

ON LOCATION

Samaritas - Saginaw Campus - Addition & Renovation

Phase 2 demolition is well underway

Project Update

Phase 1 is Complete! Asbestos abatement is complete for Phase 2 and interior demolition is about 80% complete. Next, we will be laying out the new walls and removing the floor slab in areas where new underground plumbing will be installed for the new rehab bathrooms.

Demo of old walls reveals hidden MEPs

We are still plagued with hot water issues in Phase 1 that we are working to resolve. Brad Frey, Senior Project Manager bradf@elzinga-volkers.com

Demo of plaster ceilings in old resident rooms

www.elzinga-volkers.com www.elzinga-volkers.com