Construction Update Newsletter

ON LOCATION

Samaritas - Saginaw Campus - Addition & Renovation

Phase 2 demolition is well underway

Project Update

Phase 1 is Complete! Asbestos abatement is complete for Phase 2 and interior demolition is about 80% complete. Next, we will be laying out the new walls and removing the floor slab in areas where new underground plumbing will be installed for the new rehab bathrooms.

Demo of old walls reveals hidden MEPs

We are still plagued with hot water issues in Phase 1 that we are working to resolve. Brad Frey, Senior Project Manager bradf@elzinga-volkers.com

Demo of plaster ceilings in old resident rooms

www.elzinga-volkers.com www.elzinga-volkers.com


.

On Location - Construction Update Newsletter Samaritas - Saginaw Campus - June 2017

Looking Ahead

SAFETY Matters Surviving the Heat

Mike Roney, Field Manager miker@elzinga-volkers.com | 586-482-4102 » Over the next few weeks a fast pace schedule has been set and we will be working on rough framing of interior partitions, MEP rough-in, drywall, and interior finishes. » Due to hot water issues, which began in Phase 1, we have reached out to a Mechanical Engineer at MacMiMillan and Associates located in Bay City.

Construction workers really feel the heat during the hot, humid months of summer. Here are a few tips to help avoid dehydration and beat the heat: » Hydrate. Drink cool water frequently, even if you’re not thirsty. » Exercise. Stay in good physical condition. Extra weight means more work, sweat, and risk. » Eat right. Eat light meals during the hottest hours and avoid highfat greasy foods, which will bring on fatigue. » Avoid air conditioning. Try not to go in and out of air conditioning since it will make it more difficult for you to adjust to the heat. » Watch for Heat Exhaustion/Heat Stroke. Symptoms include dizziness, headache, sweaty skin, weakness, cramps, nausea or vomiting, and rapid heart beat. Heat stroke symptoms also include hot, dry skin, mental confusion, convulsions, and loss of consciousness. If anyone shows these signs, call 911 right away.

TEAM SPOTLIGHT

Ready for debris removal

Who’s Who On Site

David Eastman

Phase 2 demolition progress

David is part of the Elzinga & Volkers (E&V) Facilities Services Division (FSD) and travels across the US working on a variety of projects. Over the past year, David has been a valuable asset to the project team by doing carpentry and also facilitating the E&V quality standards and safety program with our trade partners. In his free time, David enjoys spending time with his family and friends back in Greenville, Michigan. When you see David around the office or jobsite, please take a moment and say hello.

Track the Project’s Progress as the View Takes Shape!

92 days

Phase 1

58 days

Phase 2

39 days

Phase 3 Phase 4

79 days

68 days

Phase 5

80 days

Phase 6

www.elzinga-volkers.com

Completion