Construction Update Newsletter
ON LOCATION
Samaritas - Saginaw Campus - Addition & Renovation
Phase 2 demolition is well underway
Project Update
Phase 1 is Complete! Asbestos abatement is complete for Phase 2 and interior demolition is about 80% complete. Next, we will be laying out the new walls and removing the floor slab in areas where new underground plumbing will be installed for the new rehab bathrooms.
Demo of old walls reveals hidden MEPs
We are still plagued with hot water issues in Phase 1 that we are working to resolve. Brad Frey, Senior Project Manager bradf@elzinga-volkers.com
Demo of plaster ceilings in old resident rooms