On Location - Samaritas Saginaw - March 2017

Page 1

ISSUE

05 MARCH 2017

Construction Update Newsletter

ON LOCATION

Samaritas - Saginaw Campus - Addition & Renovation

Rehab addition

Project Update

Proceeding On Schedule Work is proceeding on schedule in Phase 1. Finishes and fixtures are being installed in the south wing while drywall work is nearing completion and painting is underway in the north section. 50% BFS approval has been received along with rough-in approvals for HVAC, plumbing and electrical from local authorities. A planning meeting will occur near the end of March for the move out for Phase 2 Brad Frey, Senior Project Manager bradf@elzinga-volkers.com

Rehab addition hallway

www.elzinga-volkers.com www.elzinga-volkers.com


SAFETYMatters

On Location - Construction Update Newsletter Samaritas - Saginaw Campus - March 2017

Looking Ahead Extension Cord Safety Guidelines Mike Chrisman, Field Manager mikeC@elzinga-volkers.com | 616-610-9313

Phase 1 Progress Update:

» Tile for our new 19 resident room bathrooms and showers is nearly complete. » Cabinets and counters are being installed. » Handrails, doors, and hardware are being installed. » State BFS and HFES final inspections are coming up soon. » All the new beds and furniture for 19 new re-hab rooms will be delivered and set up soon.

Extensions cords are used everywhere on construction sites. Normal wear and tear on cords can loosen or expose wires. Cords that are not 3-wire type, were not designed for hard use, or have been modified, increase the risk of contacting an electrical current. Here are some guidelines that Elzinga & Volkers uses to regulate the use of extension cords: » Use only equipment that meets OSHA standards » Do not modify or use cords incorrectly » Use factory-assembled cords and only use the 3-wire type » Remove cords from receptacles by pulling on the plugs, not the cord.

TEAM SPOTLIGHT

Resident room

Who’s Who On Site

Quality Air Heating and Cooling, Inc. is our site HVAC (Heating, Ventilation and Air Conditioning) contractor. Their field team has had a lot of challenges due to old systems and old problems with them. Quality Air’s team has done a great job of blending old systems with new systems to create a comfortable atmosphere for Samaritas’s new re-hab rooms. A big thanks goes out to their team for their commitment to this job.

Salon

Track the Project’s Progress as the View Takes Shape!

92 days

Phase 1

58 days

Phase 2

39 days

Phase 3 Phase 4

79 days

68 days

Phase 5

80 days

Phase 6

www.elzinga-volkers.com

Completion


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.