Construction Update Newsletter
ON LOCATION
Samaritas - Saginaw Campus - Addition & Renovation
New northwest resident rooms
Project Update
Making Great Progress! Substantial progress has been made over the past month on both the existing Phase 1 and the Rehab addition. Under floor plumbing is complete and floor patches have been poured. Wall framing is currently underway. Challenging structural steel installation has been completed in order to accommodate a two-hour fire rated structural separation between the old Rehab addition and the original building. Asbestos pipe insulation had to be abated at locations where connections needed to be made for new heating equipment. Rough-ins are underway for plumbing, fire protection, heating, and electrical systems.
New office waiting for drywall mud
Brad Frey, Senior Project Manager bradf@elzinga-volkers.com