Construction Update Newsletter

ON LOCATION

Samaritas - Saginaw Campus - Addition & Renovation

New northwest resident rooms

Project Update

Making Great Progress! Substantial progress has been made over the past month on both the existing Phase 1 and the Rehab addition. Under floor plumbing is complete and floor patches have been poured. Wall framing is currently underway. Challenging structural steel installation has been completed in order to accommodate a two-hour fire rated structural separation between the old Rehab addition and the original building. Asbestos pipe insulation had to be abated at locations where connections needed to be made for new heating equipment. Rough-ins are underway for plumbing, fire protection, heating, and electrical systems.

New office waiting for drywall mud

Brad Frey, Senior Project Manager bradf@elzinga-volkers.com

www.elzinga-volkers.com www.elzinga-volkers.com


SAFETYMatters

On Location - Construction Update Newsletter Samaritas - Saginaw Campus - January 2017

Looking Ahead

A Clean Jobsite is a Safe Jobsite

Keeping a construction site clean is not just about aesthetics, but is a crucial step to ensure a safe workplace to prevent slips, trips, and falls. According to OSHA, cluttered working conditions are distracting, unsafe, and unsanitary, but a tidy jobsite improves morale, encourages good work habits, saves time, and promotes safety.

Mike Chrisman, Field Manager mikeC@elzinga-volkers.com | 616-610-9313

Phase 1 Progress Update: » » » »

Installation of replacement windows Woodworking to be delivered and installed The addition will be opened up to the existing building A new “Life Safety” electrical panel will be online

Elzinga & Volkers and our trade contractor teams work very hard to keep their jobsites clean and organized. If clean-up is neglected, the jobsite can quickly become hazardous. Nails, screws, sharp tools, dust, and debris are only a few of the things that must be continuously cleaned up. Safety is always a top priority for E&V and impacts everyone from the crew to the client and guests.

TEAM SPOTLIGHT

Resident bath and shower

Who’s Who On Site

Dobson Industrial, Inc. is a well-known local steel erector from Saginaw. The first part of their work on the Samaritas-Saginaw project was also their most challenging. The project required the addition of a two-hour fire wall through the middle of the existing building. Dobson Industrial needed to separate the structure of the building by adding columns and beams in a very tight space. Due to their planning and determination, phase 1 work is complete with the remainder of the two-hour fire wall finishing to take place in phase 6. A special thanks to Bob, with Dobson Industrial, for his many visits to the job site!

Shower nearly ready for tile

Track the Project’s Progress as the View Takes Shape!

92 days

Phase 1

58 days

Phase 2

39 days

Phase 3 Phase 4

79 days

68 days

Phase 5

80 days

Phase 6

Completion

www.elzinga-volkers.com www.elzinga-volkers.com


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.