ISSUE
02
OCTOBER 2016
Construction Update Newsletter
ON LOCATION Samaritas - Saginaw Campus
The Phase 1 addition is ready for underground plumbing
Project Update
Exciting Changes Ahead! Phase 1 demolition is now complete and it’s time to piece it all together again!
New south end plumbing is ready for floor patching
The floors have been cut to allow for our underground plumbing to be roughed-in. With this work complete, we will fill the floors back in and begin framing the new resident rooms. On the exterior of the building, the new addition has it footings in place and the new floor slab will be poured the week of October 10-14 along with the underground plumbing trenches. There will be many exciting changes over the new few weeks as the project ramps up. Brad Frey, Senior Project Manager bradf@elzinga-volkers.com
New east end plumbing is ready for inspection
www.elzinga-volkers.com