Construction Update Newsletter

ON LOCATION Talecris Plasma Resources - Flint, MI

Meet Your Project Manager!

Building exterior 95% complete.

Name: Brad Frey Role: Sr. Project Manager Did you know? Brad has worked in the construction industry for 40 years?

Meet Your Field Manager!

Executive Summary Welcome to On Location!

The project is in the final stages of completion and is looking great. Everyone has stepped up admirably. Asphalt paving was installed on Sunday. Striping was completed with snow flurries in the air. It would have been nice to be a week further ahead at punchlist time, but given obstacles that had to be overcome I’m very pleased. Punchlist completion is progressing on schedule and should be complete by December 16th. Donor beds have been delivered. These will be assembled and set in place this week. Grifols furniture is also starting to arrive. Given that this project is less than one week from completion, this will be our final newsletter. We hope that you have enjoyed the project updates and found the information useful! Brad Frey, Senior Project Manager bradf@elzinga-volkers.com

Name: Larry Wolters Role: Field Manager Did you know? Larry has completed over $250,000,000 worth of construction projects during his 40 years in the industry?

Upcoming Milestones » » » »

Installation of Grifols Phone Line Final Inspection for Fire Protection Obtain the Certificate of Occupancy Complete Punch List Continued progress on the building interior.

alive365 safetymatters

www.elzinga-volkers.com www.elzinga-volkers.com


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Talecris Plasma Resources - Flint - December, 2016 Newsletter by EV Construction - Issuu