June 2012
The Inside Scoop Progress Report Saint Mary’s Health Care—Psychiatric Medical Unit
Upcoming Milestones Low Voltage Wiring Start Ceiling Grid
Executive Summary
Complete Wall Tile
With all of the activity currently going on within the walls of the sixth floor, it’s hard to believe that only a month has gone by since our last update. Finish work is in full swing throughout the project. Drywall crews are completing their very last sections with painters following closely behind applying prime and finish coats. Within the patient rooms, bathroom tile is being laid, casework is being set, and plumbing fixtures are getting installed. Exciting times are approaching as several areas are revealing their completed form.
Begin Installation of Flooring
Project Progress and Major Milestones
Casework
The nature of the jobsite during this final phase is very busy and fast paced. Tradesmen are literally working on top of one another in order to complete an area and move to the next. The peak in worker activity makes it more important than ever to continue our full time infection control duties.
Flooring Ceilings Painting
Looking forward, our completion date is within sight. Finish work will continue, gradually moving from one end of the floor to the other. Meanwhile, many workers will be terminating and putting the final touches on a variety of low voltage systems. As you’ll see in the pictures on the following page, this is going to be a very beautiful unit when it’s all finished. Joe Novakoski—(616) 836-1810 Vice President / Senior Project Manager
Drywall Rough-in
Demolition