East Channel Bulkhead Replacement Project

By Ally Cherko, Project Coordinator/Property Manager and Kirk Wooldridge General Manager

THE EAST CHANNEL BULKHEAD REPLACEMENT PROJECT began on June 21st, 2021 and is project is contracted with Anvil Builder Inc. (ABI). ABI has successfully completed the first phase of the project in driving the Steel sheets into the ground directly in front of the existing bulkhead wall. ABI has completed a trench behind the wall where the helical anchors, and drainage system will be installed. ABI has completed half of helical anchors installation with preliminary performance testing to ensure that the anchors are install per specifications. The testing and overall project work thus far has been inspected and documented by Noble Consultants Inc. (NCI) the contracted construction management for this project, as well as by TKPOA project coordination staff.

The next steps in the project are to finish installing the helical anchors, tie backs and walers completely the entire distance of the wall. The last phase of the project is the backfilling the trench, installation of the bulkhead cap, and rip rap and natural vegetation at each end of the bulkhead. NCI and TKPOA staff will continue to monitor, inspect and manage this project until completion.

Unfortunately, due to the smoke from the Caldor Fire and the hazardous air quality, ABI did not work the week of August 30th to August 27th. As of August 30th, 2021, Cal Fire issued an evacuation order for South Lake Tahoe, so work could not continue the week of August 30th to September 3rd. The Caldor Fire evacuation and potential hazardous air quality conditions may cause a 2–4 week delay for this project.

The future of this project will be determined by the events as they unfold with the Caldor Fire and the timeline in which repopulation into the City of South Lake Tahoe as allowed by Cal Fire and local law enforcement.

For any questions or comments regarding the East Channel Bulkhead Replacement project, please contact the Project Coordinator/Property Manager, Alison Cherko at Acherko@tahoekeyspoa.org, or visit www.tkpoa.com.

2021 ARCHITECTURAL CONTROL COMMITTEE MEETING SCHEDULE

IMPORTANT!

ACC Meetings have been moved from Mondays to Tuesdays for 2021.

All meetings are held at the Pavilion and begin at 9:00 am unless otherwise posted. ACC application submittals are due by Wednesday prior to the meeting date. For more information please contact Linda Callahan, ACD Manager, at (530) 542-6444, ext. 239, or lcallahan@tahoekeyspoa.org.

SEPTEMBER 28 OCTOBER 12 NOVEMBER 9 DECEMBER 7

SEE YOU THERE!

A trusted name in Tahoe Keys real estate for over 30 years. PETER DELILLI A trusted name in Tahoe Keys real estate for over 30 years.

428 Wedeln Court | Sold

4 Bd 3 Bth 2179 Sq. Ft. $2,175,000

The Tahoe Keys real estate market is always changing. Whether buying or selling, allow Peter to guide you using his expertise and reliable service to get the job done!

PETER DELILLI 530.308.4331

The Tahoe Keys real estate market is always changing. Whether buying or selling, allow Peter to guide you using his expertise and reliable service to get the job done!

2187 Shasta Court

3 Bd 2.5 Bth 2176 Sq. Ft. $849,900 1935 Kokanee Way | Sold

3 Bd 2.5 Bth 2756 Sq. Ft. $1,367,500

PETER DELILLI 530.308.4331

Tahoe Keys Real Estate Expert and Resident CalBRE# 00923047 PeterDeLilli3@gmail.com PeterDeLilli.com for all Tahoe Keys properties Call or email me and I can quickly tell you the value of your property

Tahoe Keys Real Estate Expert and Resident CalBRE# 00923047 479 Lido Drive | Sold Call or email me and 3 Bd 2.5 Bth 2229 Sq. Ft. $1,355,000 I can quickly tell you the value of your property

1664 Venice Drive | Sold 4 Bd 2.5 Bth 2536 Sq. Ft. $1,049,000

PeterDeLilli3@gmail.com PeterDeLilli.com for all Tahoe Keys properties

This article is from: