1. SITE + SUB FLOOR PREPATION PLAN

300W×300D RIB TO PAVING EDGE

300WW×600D RIB FOR STRIP FOOTING 500WW×600D WIDEN RIB FOR SLAB EDGE

50MM SEDOWN

SOIL CLASS M

EXISTING GROUND LEVEL TO BE REVISED SHOWN DASHED

SITE SET UP: 50MM COMPACTED SAND BASE FOR SLAB

50MM COMPACTED CRUSHED ROCK BASE FOR PAVING SLAB

1. TEMPORARY FENCING To identify the site

TRENCH FOR STRIP FOOTING

2. PORTABLE TOILET LANDING

ABPL20033 CONSTRUCTION ANALYSIS

3. TEMPORARY FACILITIES AND SERVICES: Power supply, First aid

LIANG CHEN 743080


2. FOOTINGS, SLAB +RETAINMENT

RETAINMENT DETAIL 290 B/W BACKFILL WITH FREE DRAINING, GRANULAR TYPE, LIGHTLY COMPACTED BACKFILL

N16 @ 200 VERTICAL BARS N12 @ HORIZONTAL BARS

N16 STARTER BARS @200 CRS. 600 LAP WITH WALL REINFORECEMENT, 800 COG AT BTM

GROUT FILL CAVITY WITH 15MPa, 6mm MAX. AGGREGATE CONCRETE FILL AT COMPLETION OF WORKS THAT ALLOWS CONCRETE SLAB TO SHRINK

90DIA. 'AGI'. DRAIN IN 20MM SCREENINGS, 150 mm MIN. COVER TO PIPE. CONNECT PIPE TO S. W. D. SYSTEM

25 MPa CONCRETE ACCORDANCE WITH AS3600.

SL82 IN TOP, 30MM CONCRETE COVER SQUARE MESH, LOW DUCTILITY, 12MM REO @200 0.2mm VAPOUR BARRIER (COVER WITHOUT DISTANCE DRAWN FOR OBSERVATION WITH DISTANCE)

COMMENCEMENT OF RETAINING WALL

STARTER BARS FOR COLUMN WITH SAFETY CAPS

TYPICAL EDGE RIB DETAIL

ADD SL82 SIDE FACE REINF. WHERE EXPOSED BEAM FACE IS GREATER THAN 400mm 0.2mm VAPOUR BARRIER

TYPICAL INTERNAL RIB DETAIL SL82 IN TOP WITH 20mm COVER

FOUND 100 MIN. INTO NATURAL SILTY CLAY CAPABLE OF SAFELY SUPPORTING 15 kPa DEEPEN IF REQUIRED

ABPL20033 CONSTRUCTION ANALYSIS

3-L12TM IN BTM WITH 50mm CONCRETE COVER

LIANG CHEN 743080


3. PREPARATION; BUILDING FRAME + STRUCTURE INTERNAL BLOCKWORK REINFORCEMENT DETAIL

FILL WITH 15 MPa 6mm MAX. AGGREGATE CONCRETE OF POURABLE CONSISTANCY. 1-N16 TOP&BTM WITH 50mmCOVER. CONTINUE 200 MIN. BEYOND OPENING.

STRUCTURAL TIMBERS

MACHINE GRADED PINE, (MGP10) 90×45MM×2M. MAJOR MATERIAL FOR TIMBER STUCTURE, LIKE STUDS, USUALLY SPACING MAX. @450.

LAMINATED VENEER LUMBER (LVL F17), H2S IS HAZARD TREAT LEVEL. HAVING MORE STRENGTH THAN MGP10. CAN BE USED AS STRUCTURAL BEAM

ABPL20033 CONSTRUCTION ANALYSIS

LIANG CHEN 743080


4. GROUND FLOOR; FRAME + STRUCTURE 120MM×45MM GALVANISD STEEL JOIST HANGER

100MM×190MM NAIL PLATE

CONNECTION DETAIL

30 MM×0.8MM GALVANISED STEEL BRACING, WITH 6MM&3MM HOLES FOR NAILING. RESISTING T H E L AT E R A L F O R C E S A C T I N G O N T H E STRUCTURE ACCORDANCE WITH AS 1684.

OTHER KINDS OF BRACING ARE USED LIKE PLYWOOD SHEET BRACING FOR WALLS. AND TEMPORARY PROPPING PROVIDING SUPPORTS DURING OCNSTRUCTION.

STRUCTURE BRACING

ABPL20033 CONSTRUCTION ANALYSIS

LIANG CHEN 743080


5. INTERMEDIATE SUSPENDED FIRST FLOOR STRUCTURE COLUMN CONNECTION DETAIL

8 BASE PLATE, 6 CFW 2-M16 4.6/S BOLTS

GALVANISED JOIST HANGER

KDHW NAILING PLATES TYPICAL M12 BOLTS THROUGH @ 600 MAX. CTS.

ON SITE WELDING WELDING ON SITE ALLOWS TO CREATE RIGID CONNECTIONS, THROUGH WELDING REQUIRES CERTIFIED WELDERS WHO SPECIALISE IN FIELD WELDING TO CERTIFICATION CODE AS1796

ABPL20033 CONSTRUCTION ANALYSIS

LIANG CHEN 743080


6. ROOF STRUCTURE PREPARATION DOWNPIPE

LOWER OFFSET

GUTTER

BRACKET

PLAN 89×89 ×3.5 SHS

90×45 MGP10 PINE ROOF JOISTS @600 MAX. CTS.

ROOF JOISTS SPAN ALL LENGTH

180×75 PFC 200×45 HYSPAN LVL ROOF JOISTS @600 MAX. CTS.

ABPL20033 CONSTRUCTION ANALYSIS

2/90×45F17 KDHW

LIANG CHEN 743080


7. LOCK UP; EXTERNAL WALLS RAFTER CONNECTION DETAIL 180 UB 18 WITHIN RAFTER DEPTH

TRIP-L-GRIPS EACH SIDE.

KDHW NAILING PLATES TYPICAL M12 BOLTS THROUGH @ 600 MAX. CTS.

WALL DETAIL

MGP 10 STUD @ 450MM

VAPOUR BARRIER

EXTERNAL ZINC CLADDING FINISHES

ABPL20033 CONSTRUCTION ANALYSIS

LIANG CHEN 743080


8. LOCK UP; ROOF COVER PLAN 30×0.06MM GALVANISED STEEL STRIP BRACING

NAILABLE SHEETING VAPOUR BARRIER

140×45MM MGP10 PINE

ROOFING SHEET

SIMILAR ROOFING SHEET FOUND IS METLOK 700 ROOFING SHEETS COMPARED TO THE ONE USED IN THE KEW HOUSE. THE FEATURE OF THIS KIND OF RIB SHEETING IS AN IMPROVED RIB STRENGTH FOR EXCELLENT SPANNING CAPACITY. IT IS ALSO EASY TO INSTALL. THE CORRAGATED SHEETING SHOULD FOLLOW AS 1445-2013.

ABPL20033 CONSTRUCTION ANALYSIS

LIANG CHEN 743080


9. LOCK UP; WINDOW SYSTEMS WINDOW FRAME CONNECTION DETAIL

FOLDED ZINC PARAPET CAPPING TO MATCH C1 CLADDING WITH 80MM VERTICAL RETURN

RF1 ROOFING AND ASSOC. FLASHING AS SPEC.

ROOF BEAM TO ENG. SPEC.

C1 ZINC CLADDING OVER 15MM C-D GRADE PLYWOOD SUBSTRATE OVER TIMBER BATTENS AS SPEC. WINDOW SUITE

DOOR FRAME CONNECTION

ABPL20033 CONSTRUCTION ANALYSIS

LIANG CHEN 743080


10. FIXING; SERVICES 'ROUGH IN' PLAN

ABPL20033 CONSTRUCTION ANALYSIS

LIANG CHEN 743080


11. INTERNAL PARTITIONS + CEILING STURCTURE PLAN

10MM PLASTERBOARD

DURING THE LAST STAGE, PLASTERBOARDS ARE FIXTED TO THE TIMBER STUD FRAME FOR INTERIOR FINISHES. ALL ROUGH IN SERVICE SHOULD BE DONE BY THIS STAGE.

ABPL20033 CONSTRUCTION ANALYSIS

LIANG CHEN 743080


12. FIXING; FINISHING TRADES

ABPL20033 CONSTRUCTION ANALYSIS

LIANG CHEN 743080


APPENDIX

TYPICAL EDGE RIB DETAIL 1:20

RETAINMENT DETAIL 1:20

TYPICAL EDGE RIB DETAIL 1:20

INTERNAL BLOCKWORK REINFORCEMENT DETAIL 1:10

PERSEPECTIVE WALL DETAIL(NOT TO SCALE)

RAFTER CONNECTION DETAIL 1:10

PERSEPECTIVE DOWNPIPE DETAIL(NOT TO SCALE)

PERSEPECTIVE JOIST HANGER DETAIL(NOT TO SCALE)

ABPL20033 CONSTRUCTION ANALYSIS

COLUMN CONNECTION DETAIL 1:10 WINDOW FRAME CONNECTION DETAIL 1:10 LIANG CHEN 743080


After getting building permits from the council, the preparation of the construction could begin. Before the existing double storey building has been demolished, the builders need to set up the site, such as the temporary fencing. Clearing the underground pipes would be essential for the services connection later on., The soil classification of the site is Class M. Trenches of 300mm wide *500mm deep are used for the strip footing foundation. Compacted sand would be laid on top as a sand base. Over a layer of waterproof membrane, reinforcements of internal and edge rib supported by bar chairs were laid in place with top layer meshes which prevents concrete from cracking. Due to the A2 exposure class, the concrete cover for bottom layer reinforcements in internal and edge ribs would be 50mm. 25 MPa concrete was poured, compacted and cured. The starter bar for load bearing walls columns will be capped with safety caps. At the same time, the reinforced masonry retaining wall would take place which help resisting lateral forces. Once the retaining wall has done, the ground floor timber structural frame will start as well as the second retaining wall in the other side. Concrete filled in the block work is 15 MPa with 6mm max aggregates. Timber used in the structural system are mainly two kinds, Machine graded pine 10 and laminated veneer lumber F17. LVL F17 has more strength and could be used as a beam. The diagonal metal strap bracing was attached to both top and bottom plate and nailed into studs with tensioner tightening it. It provides more lateral stability of the building structure. Also it could used for connecting other members. Temporary propping are required at this phrase for providing extra supports for the structural system. The suspended first floor structure will continue building on the floor joist system. Parallel flange channel operating as beam is connected with MGP 10 floor joists by bolts. Welding of PFC and square hollow section can create rigid joint. The concrete stump with ant cap were constructed for first floor as well. After the first floor structure done by the builders, it’s nearly finishing the structural system of the building. Starting installing cross bracing and temporary propping same as the ground floor, commencement of roof beams and rafters. Downpipes are installed as a part of roof structure preparation. When coming up to the lock up stage, the external wall will be covered up first in order to create a closed environment. Layers of stud frame, insulation, air gap, vapour barrier and external zinc cladding will add up to finalise the external walls of the building. Kin dried hard wood nailing plate are applied as connections for rafters and universal beams in the roof system. Insulation of the ceiling, nail-able sheet and waterproof membrane are forming up the roof system. Box gutter with 2 degree fall was installed and connected to the downpipes, flashings are also applied to the roof system. The corrugated roof sheeting with an improved rib can provide more strength and also easy to install with lapping. Internal wall structures are finalised at this stage. Windows on non-load bearing walls are installed. Door and other window frames are starting installing. Frame connection details can be vary from the types and positions of the windows. Services are connected from the Mains and the electrical cables are going through the timber studs frame around the building. All door and window installations should be done at this stage. Internal plasterboard are fixed to timber stud frame for painting. Rough in system are complete. Lastly, the joinery installation, carpeting and plumbing will happen in this stage. Before handing it over to the clients, paving and landscape will be completed responding to the clients needs which leads to the completion of the house. Thanks for listening. ABPL20033 CONSTRUCTION ANALYSIS

LIANG CHEN 743080


ABPL20033 CONSTRUCTION ANALYSIS

LIANG CHEN 743080