Construction Analysis – ABPL20033 Flipbook 3 – JCB Hampton House Nesia Cahyono 813807
STAGE 1 - GROUND PREPARATION, PIPES AND CONCRETE SLAB
Fig 1. The old house
Fig 2. Excavation on pool
Fig 3. Manual formworks on site
Fig 4. Curing by watering method
Approximately 7 days until the formwork can be stripped and 28 days until the concrete gains its ultimate strength (AS3600)
STAGE 2 - GROUND FLOOR WALL FRAME
Fig 8. Nail Fig 5. Square Hollow Section
Fig 6. Steel-steel and steeltimber connection
Fig 9. Explosive bolt
Fig 7. Lintel and adjusted studs
The size of lintel is depending on some factors such as opening as listed in AS1684.4
Connectors should comply with AS4100
STAGE 3 - FIRST FLOOR FRAME Blocking Open web allows services to run through
Fig 10. Timber truss floor joist and 2 blockings
Fig 11 & Fig 12. Floor joist with top flange connection
Fig 13 & Fig 14. timber truss floor joist and blocking
STAGE 4 - FIRST FLOOR WALL FRAME
Fig 15 & Fig 16. Particular detail in construction
Fig 17. Similar detail on the other part of the house
Fig 18. Saw horses and circular saw on site
Noggings are still installed because the studs are still higher than 1350 mm, as covered in BCA
STAGE 5 - ROOF FRAMING
Fig 19. Steel frame and timber
Fig 20. Rafter-rafter connection using trip-l-grip
Fig 21. Timber – PFC – timber
Fig 22. Rafter – top plate connection using trip-l-grip
STAGE 6 - GUTTER AND FLASHINGS Sarking is not installed too tight to ensure the reflective function works
Overlapping materials to prevent water leakage
Different color of battens. Battens for metal deck are not painted, while the one for rain screen is painted in black Fig 23. Roof layers from inside
Fig 24. Dark gray corrugated metal roof decking
Sealant on overlapping materials
Fig 25. Black trimdek metal deck for wall
Sump to adjust the unique corner of the house
Metal deck overhangs Fig 26. Sump
STAGE 7 - RAIN SCREEN Flashing Adjusted on site
Running vertically; perpendicular to the rain screen Fig 27. First seal process
Shares the same layer as down pipe Fig 28. 40x40 painted battens
Fig 30. Rain screen does not touch the ground
Fig 29. Rain screen to be matched with skylights, doors and windows
Fig 31. Box gutter is concealed
STAGE 8 – WINDOWS AND DOORS Rain screen Metal cladding Building paper
Door is installed
Window has not been installed Fig 32 & Fig 33. Doors and window installation
Approximately the same thickness as battens to be visually great when hidden by the rain screens
Flashing
Fig 34. Window placement
STAGE 9 – ROUGH IN AND INSULATION
Battens for ceiling hold bulk insulation
Services are installed before insulation
Fig 35. Services and insulation
Fig 36. Battens for ceiling
Fig 37. Bulk insulation on the floor
STAGE 10 – LININGS
Fig 38. Metal bead
Fig 39. Tapered edge
Fig 40. Plasterboards installation and painting
STAGE 11 – PAINTING, JOINERY AND FITTING
Ground fill
Fig 41. Joinery
Fig 42. Tiling
Fig 43. Sanitary
Fig 44. Vertical reinforcement bars
Fig 45 & Fig 46. Agricultural drain
STAGE 12 – FINAL PAINTING POLISHING FLOOR AND LANDSCAPE Fig 47. Touch ups