24 May 2020 Nesia Cahyono Business Development Division
MAX PROFIT CONSTRUCTION
SUPPLY CHAIN REPORT
page 2
EXECUTIVE SUMMARY
MP Construction is an Australian-based construction company that is well known for its excellence in quality. Being in the industry for more than twenty years, MP Construction is seeking for a way to improve its cost and time efficiency, while keep maintaining the quality. This report is produced to provide the alternatives for improvement. The key problems in MP Construction are identified, and two key initiatives are proposed accordingly.
KEY PROBLEMS Traditional procurement method
separated from the design teams no incentive for the contractor to innovate long time because of sequential process few points of responsibility unbuildable design inefficient expenses
Competitive Tendering Process
nontransparent relation between project stakeholders
KEY INITIATIVES Just-In-Time - Kanban - Line of Balance - Last Planner System - Prefabrication
compromised quality on the final product
Project-byProject Basis Suppliers
low profit margin wasting time and money project-to-project basis
Traditional On-site Construction Techniques
longer time
TIME COST ACTORS
bigger unexpected risk constrained by the workers availability
28 m 90% 1,730
Redesigned Performance
labour intensive and labour expensive
Poor Workmanship
Partnership - Design & Construct - Reduction of partners - Supply chains consolidation
Current Performance
more expensive
July 2021
July 2025
Dec 2025
JIT practices Partnership: subcontractors assessment process
Partnership: Step 1 - D&C implementation Partnership: Step 2 Reduction in numbers
Partnership: Step 3 - Consolidation of Supply Chains
100% 4,660
KEY MILESTONES July 2020
39.5 m
page 3
TABLE OF CONTENTS
0.0 EXECUTIVE SUMMARY
2
2.0 STEP 1: ASSESS 2.1 Traditional Procurement Method 2.2 Competitive Tendering Process 2.3 Project-by-project Basis 2.4 Traditional On-site Construction 2.5 Poor Workmanship
8 8 8 8 10 10
4.0 STEP 2: REDESIGN 4.1 Monitoring and Control 4.2 Implementation
36 36 38
6.0 TOWARDS RESILIENT BUSINESS
42
8.0 REPORT LIMTATIONS
48
10.0 BIBLIOGRAPHY
50
1.0 INTRODUCTION 1.1 Purpose of the Report 1.2 Company Background 1.3 Definition of Supply Chain 1.4 Method of Approach
4 4 5 6 7
3.0 STEP 2: REDESIGN 3.1 Just-In-Time (JIT) 3.2 Partnership
14 14 30
5.0 STEP 4: IMPROVE
40
7.0 FINANCIAL PLAN
47
9.0 CONCLUSION
49
11.0 APPENDICES
52
page 4
1.0
Introduction 1.1 Purpose of the Report
This report is produced along with the new leadership in the company. Despite the success achieved in the past two decades, the new leader believes that Max Profit (MP) Construction can flourish into a much larger business. This report aims to bring this expectation into reality. Although there are several of key areas to be reviewed, this report concentrates on the supply chain as the first area of improvement in MP Construction. MP Construction is well known for the excellent finish quality on every project. The management team claims that this value drives MP Construction to constantly satisfy client’s requirements and brings MP Construction to win a lot of tender bids. Indeed, client satisfaction is essential, especially if the business is aiming for return customers. Yet, it should not be a major indicator of a business success. A company should look at a higher-level parameter, which is profitability. Profitability is not only securing the financial aspect of the business, but more importantly it can be used to develop the business even more. For instance, the research and development that can be conducted if the company makes profit; training for the resources, welfare
PROFITABILITY
of the employee, and many others (Fama & French, 2000). The improvement in the company’s resources will eventually leads to client satisfaction. Therefore, increasing profitability should be the ultimate goal to achieve sustainability in business. This report will provide assessment on the current performance of MP Construction as well as analysis on how to effectively improve company’s profitability.
QUALITY
RETURN CUSTOMER
page 5
1.2 Company Background
“ design for sustainability, build with quality ” Max Profit (MP) Construction is a construction company that focus on delivering small to medium residential and commercial projects in Australia. It was first established in 1999 by an Australian born Italian, Antonio Gurinoz. The influence came from his father, Roberto Gurinoz, who migrated to Australia and started his business as an architect and small house builder. Since then, MP Construction has steadily developed from a 2-employee company to one of the most preeminent familyowned builders in Australia. In the past two decades, MP Construction has been expanding to 3 different states, New South Wales, Victoria and Queensland, with its offices are located at each of the capital cities. Due to the thoughtful management from the family, MP Construction has forged a reputation as a company that always deliver projects with high
Antonio Gurinoz Founder and CEO 1999 - 2020
quality. This recognition is maintained and believed as the predominant aspect of its success in every competitive tendering. MP Construction is very selective in selecting projects and always meets client’s quality requirements. MP Construction believes that the best quality of works is achieved by closely monitoring and supervising each process. Therefore, undertaking the construction works on site and selecting the specific upstream actors are crucial for MP Construction. 2020 is a big year in the MP Construction’s journey because since January 2020, Antonio has passed his passion in construction to his daughter, Maddalena Gurinoz. Having a background in Construction Management, Maddalena is very passionate on evolving MP Construction into a larger business. She believes MP Construction should maintain what has been achieved yet keep adapting to the ever-changing conditions. Her ultimate goal is to bring MP Construction to be sustainable and resilient business. However, at this stage, her focus is to improve MP Construction performance.
Maddalena Gurinoz CEO 2020 - present
page 6
1.3 Definition of Supply Chain
“The supply chain is the network of organisations that are involved, through upstream and downstream linkages, in the different processes and activities that produce value in the form
”
of products and services in the hands of the ultimate consumer
~~ Christopher 1998, p. 13
In the construction industry, supply chain refers to the link of construction industry actors that are engaged in a mutually beneficial program to deliver certain project (Dekker, 2017). The main actors include client, contractor, consultants, subcontractors, and suppliers, although there are other parties such as service crews and logistic firms. Thus, supply chain management in construction industry is the process of managing the relationship between those actors to successfully deliver the client’s project. There might be up to five tiers of supply chain in a construction project. They manage the flow of the raw materials to the finished products on site. The number of actors from the upstream to the downstream can be depicted as an inverted triangle as shown in Figure 1.1.
Figure 1.1. Five Tiers in Construction SC
The number of tiers in a construction project is not definite. It is highly dependent on the supply chain on each trade. In an ideal condition, good collaboration happens across the tiers in a partnership relation, not an adversarial relation. However, construction industry is now facing the opposite situations. As stated by Cox and Townsend (1998), construction supply chains are inefficient. Two of the main problems are the adversarial culture and the fragmented industry structure. The significance of supply chains in construction industry is further reinforced by Egan (1998). Although this report was produced more than two decades ago, the relevance is still emphasised in the today’s construction industry as evident in several articles, such as those by Farmer (2016), Hackitt (2017), and Jones (2018). In his report, he states that the future construction industry will be looking at a competition between supply chains rather than between actors (Egan, 1998). An effective supply chain results in reduction of cost and increase in profitability over a long term, which are what each business should be aiming for.
page 7
1.4 Method of Approach
This report demonstrates the alternative strategies for MP Construction to improve its performance. These strategies are developed based on a four-stage approach by Vrijhoef and Koskela (1999): assess, redesign, control, and improve (Figure 1.2). This cyclic process leads to continual improvement which is the progressive evolution of the supply chain process. In the following sections, the efficiency of MP Construction’s current practices will be assessed, and new approaches will be proposed on the non-efficient practices accordingly. Step 1: Assess This section will identify the weaknesses of MP Construction by identifying its current practices. Each of the approaches that have been adopted by MP Construction will be reviewed. The advantages as well as the disadvantages will be analysed.
Figure 1.2. Four-stage approach
Step 2: Redesign The disadvantages will be prioritised and the most effective strategies will be proposed. The strategies are suggested looking at the theoretical and practical aspects. Each strategy will be supported by at least one case study on how other businesses have successfully implemented it.
Step 3: Control The new performance will be recorded and reported regularly. The success of the strategies will be measured through the predetermined KPIs. Step 4: Improve The strategy that shows a better performance will be adopted as a new standard in the company. By applying a new standard, MP Construction is able do continual improvement (Figure 1.3). On the other hand, the non-performing strategy will be refined by reassessing the issues.
standards
continuous improvement
Figure 1.3. Continual Improvement
page 8
STEP 1: ASSESS
2.0
Overview of the Current Practices
This section provides assessment on the current performance of MP Construction. The performance is assessed based on five practices in MP Construction: 1. traditional procurement method 2. competitive tendering 3. project-by-project basis 4. traditional on-site construction techniques 5. poor workmanship.
2.1 Traditional Procurement Method The projects in which MP Construction are involved are using traditional procurement method. This practice is indicated by the sequential stages where the design development process is undertaken before the contractor selection. MP Construction is hired as construct only contractor which is separated from the designing process. Traditional procurement method has high level of cost certainty and client involvement in both design and construction phases. These result in low variability and high quality of projects. However, these also make no incentive for the contractor to innovate. As a result, the overall quality is high with client requirements are satisfied, but rarely exceeding the client’s expectations. 2.2 Competitive Tendering Process Most of MP Construction’s projects are won through competitive tendering. The purpose of this process is to have transparent and equal opportunity in the process of building delivery. However, the process of competitive tendering is not time effective and cost efficient (Stanley, 2011) (illustration on the next page). The low profit margin often leads subcontractors and suppliers to keep their costs down by compromising quality and safety. Moreover, competitive tendering process allows the downstream actors to select the upstream actors independently. They are individually involved so that there is no necessities for them to think about the benefits of the project as a whole. Not only does this practice hinder open communication and supply chain integration, but also leads to a non-transparent relationship between project stakeholders. 2.3 Project-by-project Basis MP Construction employs different subcontractors for each project. As the process of competitive tendering is very lengthy, MP Construction repeats this process on every project. Providing that MP Construction has few integrated supply chains for its projects, the allocated time and money can be used to develop the business.
page 9
5,790
hours wasted
$132,250 money wasted
a total of
87% inefficient works and expenses
Selected actors
Hours spent
Hours recovered
Wasted hours
Money spent
Money recovered
Money wasted
% of waste
300
100
200
$6,000
$2,000
$4,000
67%
Subcontractors
2,500
200
2,300
$50,000
$4,000
$46,000
92%
Manufacturers
2,000
120
1,880
$50,000
$3,000
$47,000
94%
Suppliers
1,500
90
1,410
$37,500
$2,250
$35,250
94%
Total
6,300
510
5,790
$143,500
$11,250
$132,250
87%
Contractor
page 10
Overview of the Current Practices (cont.)
Summary of the efficiency level: Traditional Procurement Methods
Competitive Tendering Process
specialised works. Hence it is more labour intensive and labour expensive.
Project-by-Project Basis
Traditional On-site Construction Techniques
Poor Workmanship
MP Construction’s performance: COST
MPC
QUALITY
2.4 Traditional On-site Construction Techniques Traditional construction allows a project to achieve high level of uniqueness. The shape of each component can be customised and is not limited to maximum transport size. This method also provides higher structural integrity especially on the connection points between elements. However, this process takes longer time and bigger unexpected risk due to the uncertain condition on site. Specialised labours are also required on site to do
TIME
Time and cost overruns occur because of reworks and the efforts to maintain quality on site
2.5 Poor Workmanship Another problem with MP Construction is the workmanship quality. According to Burer (2016), two major causes of low-quality workmanship are poor supervision on site and poor quality of subcontractors. As MP Construction always gives priority to quality management, the problem should not arise from the supervision process, rather from the subcontractors’ side. Kasun and Janaka (2006) emphasise the importance of employing skilled and competent workers to elevate the quality, which according to Atkinson (2009), is reasonably difficult in a project with a tight timeframe. Moreover, Gandu et al. (2009) assert that subcontractors selection process is often given a compressed time. As a result, difficulties in finding the best quality of workers to work on site are encountered. It is reported that to maintain the quality, reworks reoccur significantly in MP Construction’s projects. Aside from delaying the timeline, a study from Simpeh et al. (2015) shows that rework contributes to an average of 5.12% cost overruns. The research also reveals that there is a likelihood of 76% that a project exceeds the average. This problem becomes inevitable in every MP Construction’s project because of its preference to use traditional on-site construction techniques which arises quality dependency to the onsite workers.
page 11
Advantages 1. Traditional Procurement Method
2. Competitive Tendering Process 3. Project-by-Project Basis Suppliers
4. Traditional Onsite Construction Techniques 5. Poor Workmanship
Disadvantages
Priority
1. high cost certainty 2. client involvement in both design and construction 3. low variability 4. high control on quality 5. well-known process
1. separated from the design teams 2. no incentive for the contractor to innovate 3. long time because of sequential process 4. few points of responsibility 5. unbuildable design 6. inefficient expenses
5 Adv 6 Dis
1.
wide range of tenderers 2. contract to be bid on the same basis 3. competitive tender price
1.
3 Adv 5 Dis
1.
1. longer time 2. bigger unexpected risk 3. constrained by the workers availability 4. labour intensive and labour expensive 5. more expensive
2. 3. 4. 5.
high level of uniqueness 2. higher structural integrity
nontransparent relation between project stakeholders compromised quality on the final product low profit margin wasting time and money project-to-project basis
III
II
2 Adv 5 Dis
I
This whiteboard displays the advantages and disadvantages of MP Construction’s current practices. The traditional on-site construction and poor workmanship bring the most disadvantages and the least advantages, hence, first priority is given. It is followed by the competitive tendering process and project-by-project basis suppliers, and traditional procurement method. The disadvantages are further classified in different colors, and solutions are proposed accordingly. Detail for each solution is elaborated in the next section following the current supply chain map on the next page. This map is presented to better visualise the current flows in MP Construction. It will also be compared with the redesigned supply chain map (after adopting the solutions) later in the report.
I
&
II
II
1. 2. 3. 4. 5. 6.
longer time bigger unexpected risk constrained by the workers availability labour intensive and labour expensive more expensive compromised quality on the final product 7. low profit margin 8. wasting time and money 9. inefficient expenses
&
III
1. non transparent relation between project stakeholders
2. project-to-project basis 3. separated from the design teams 4. no incentive for the contractor to innovate
towards resilient business
5. long time because of sequential process
6. few points of responsibility 7. unbuildable design
Solutions / Strategies Just-In-Time (JIT)
Partnership
Long Term Strategy
MAX PROFIT CONSTRUCTION SUPPLY CHAIN MAP
page 13
page 14
3.0
STEP 2: Redesign Strategies
3.1 Just-In-Time (JIT) I
1. 2. 3. 4. 5. 6. 7. 8. 9.
&
II
longer time bigger unexpected risk constrained by the workers availability labour intensive and labour expensive more expensive compromised quality on the final product low profit margin wasting time and money inefficient expenses
Inventory Management - Kanban Pull System
wasting time
JustInTime
low productivity wasted money
(JIT)
quality
Total Quality Management - Line of Balance
Production Management - Prefabrication
- Last Planner System
This section analyses the I & II priority group that contains nine problems. These problems can be further classified to four major root causes: low quality, wasted money, low productivity and wasted time. These root causes are strongly related to the control over the work on site. Two possible conditions are: » bad control from the management team on site, e.g. poor quality, ineffective layout » a number of activities that are beyond the ability of the management team to control, e.g. workers availability, weather condition They can be minimised by increasing the ability to control the work and enhancing the quality of the control. Just-in-time (JIT) is an inventory strategy that aims for a higher return on investment by reducing in-process inventory (time) and associated carrying costs (money) (Essay, 2018). It increases the productivity as well as the quality of products. (Pheng & Hui, 2010). Based on this understanding, JIT is a suitable practice to be implemented. This practice is firstly introduced by Toyota in a set of practice named Toyota Production Systems (TPS). Although there are a lot of key aspects in JIT philosophy, this report will focus on the three areas of production management, inventory management and total quality management. These areas are studied as the most effective solution to improve the overall performance. This section will elaborate in detail how the three principles can be implemented in MP Construction’s projects.
page 15
In this report, the process of achieving the ultimate goal, which is the sustainable and resilient business, is illustrated in a process of building a simple high-rise building (Figure 3.1). Each of the processes is equally important that none of them can be left behind. In this process, JIT is depicted as the footings of the building that needs to be constructed first before implementing the second strategy being proposed in the report.
Figure 3.1. Illustration of Resilient Business
TS IN U
E M TI
J
PREFABRICATION
LINE OF BALANCE
KANBAN SYSTEM
LAST PLANNER SYSTEM
page 16
JUST-IN-TIME STRATEGY AND IMPLEMENTATION
Inventory Management
Kanban
Total Quality Management
Line of Balance Last Planner System
Production Management
Pre-fabrication
Inventory is one of the eight types of waste (muda) (Liker, 2003). By definition, inventories mean any goods that are being retained for any length of time, inside or outside the factory. They include excess raw materials, work-inprocess (WIP), defective and finished goods (Liker, 2003). Inventory on site does take up space that potentially disturb construction flow, and it hides problems. The objective of managing inventory is zero inventory on site. In his book, Wild (2018) asserts that the best way to achieve organised and efficient inventory is by implementing kanban. The basic concept of kanban is sending a signal back to the source of inventory when an inventory is used. However, in construction works, dual kanban system is more relevant to be implemented. Schonberger (1983) refers dual kanban system as a system of sending signal for material handling task. In this instance, production kanban and withdrawal kanban are used (Figure 3.2). Production kanban is used to transfer the signal back to the source of inventory after the inventory is handed to the withdrawal kanban. A concrete example of kanban in construction is the use of e-procurement system to pull materials form the manufacturer through suppliers. In this instance, online form performs as the kanban signal between the site and the manufacturer (Khalfan et al., 2008). It results on products made to order and enables just-in-time delivery to the site. The concept of a warehouse is no longer required with this practice (Khalfan et al., 2008).
Figure 3.2. Dual Kanban System
page 17
SUCCESS STORY
PROBUILD Construction Time
“Our Kanban systems ensure that we supply each stage of the build process with the required material when they need it, which stops waste on our projects but also keeps things moving on schedule.” ~~ Luke Stambolis, PROBUILD’s Managing Director
2 mths
5% PROBUILD’s goal to reduce the defects in its apartment buildings is initiated in 2015 (The Urban Developer, 2018). It established a system called PROBUILD Construction System (PCS) as an adoption of Toyota Production System (TPS). It translates TPS in such a way that it eases construction delivery process (Malo, 2018). One of the most effective implementations is the use of stillage by all subcontractors on site. The stillage is customised so that it fits in the hoist. It is used to bring precut materials, and will be taken back empty and hence, be refilled (Bleby, 2018). By using this approach, effective pull system is facilitated with the use of stillage as kanban.
Cut the total of construction time by two months
Reduce the overtime work on residential construction by 5%
Waste Emissions
3000 m3
Cut the volume waste by 3000 cubic meters in a project
Construction Cost $150,000
5%
Save a total of $150,000 for waste shipping cost in a project
Save 2% to 5% on bills to subcontractors and suppliers
Product Quality Extra time to check on quality while still be ahead of schedule
page 18
JUST-IN-TIME STRATEGY AND IMPLEMENTATION
Inventory Management
Kanban
Total Quality Management
Line of Balance Last Planner System
Production Management
Pre-fabrication
Total Quality Management (TQM) is a management system that aims for customer satisfaction by focusing on employees’ engagement in every process. It accentuates the equal power of management and employees, and the role of human resource management (Wilkinson et al., 1998). This practice introduces quality as everyone’s responsibility and emphasises on how to do it right at the first time. A success indicator of TQM is the elimination of quality inspector team in the process (Singh, 2017). In order to achieve this goal, Ishikawa (1985) proposed his view of understanding the presence of internal customer aside from the external customer. Each process in the construction program has a customer to be satisfied (i.e. the successor subcontractors or traders). Therefore, it is important that each subcontractor delivers the work to the required standards at the required time. As an example, delay in facade installation is a failure in satisfying the requirements of fit-out traders as the internal customers. Keeping all subcontractors work to order and at the same productivity rate, especially those who are working in the same area, is very crucial. To keep track on the subcontractor’ productivity rates, MP Construction can use Line of Balance. It indicates subcontractors’ productivity in sloping lines. The objective is to have the same degree for all lines, or in other words, having the same productivity rates for all subcontractors. By incorporating Line of Balance to practice, quality management is accommodated at all stages. All workers are ultimately engaged and unified in serving the final customer (Grant et al, 1994).
Figure 3.3. Line of Balance
page 19
SUCCESS STORY
NCC Construction
(Seppanen & Aalto, 2005)
OPUS Business Park Development [The Line-of-Balance is best implemented with the Last Planner system (explained in the next section). Hene, the success story will also touch on Last Planner System]
Opus Business Park is a sixfloor office building in eastern Helsinki. The whole project consists of two sections that cover 14,500 m2 area. As the main contractor of the project, NCC Construction has brought together a lot of resources to use flowline-based production control system (Soini et al., 2004). The project has reached its completion in December 2005. In this project, line of balance is applied, and percent plan complete (PPC), part of Last Planner System, is used to measure the performance. The initial performance and the redesigned performance are displayed in Figure 3.4 and 3.5 respectively. In both figures, the master schedule is drawn in solid lines, while the actual situation is in dotted line. The two figures show that there is a change in slope in the dotted lines. The updated line of balance (Figure 3.5) shows a more similar slopes between lines which means that the subcontractors are working with a more similar productivity rate.
Reliability & Productivity
17 %
An increase from 50% to 67% weekly task completion (based on the PPC result)
Figure 3.4. Initial Line of Balance
Figure 3.5. Updated Line of Balance
page 20
JUST-IN-TIME STRATEGY AND IMPLEMENTATION
Inventory Management
Kanban
Total Quality Management
Line of Balance
Last Planner System
Production Management
Pre-fabrication
Last planner system (LPS) is one of the lean construction principles that aims to improve the reliability of the workflow by taking actions at several levels in the planning system. LPS’s key concept is to empower the lowest level of management team, foremen or supervisors, to be involved in the planning process. Four levels of planning in LPS: 1. Master Schedule : includes the project’s critical path and major milestones to determine the overall duration 2. Phase Schedule : maximising value generation of workflow: what should be done, what are needed, where, by whom and how long. Phase Schedule also reviews the flow by assessing through reverse phase scheduling 3. Look-ahead Plan : breaks down task into the level of processes (not operations): what can be done in the next 4-6 weeks. At this stage, constraints should be identified and removed to make tasks ready for execution. 4. Weekly Work Plan (WWP) : filters what can be done to what will be done. Four quality criteria for a task to be performed: • Definition : the details are sufficiently described, the procedure and completion can be determined • Soundness : all prerequisite works and resources are available • Sequence : the sequence matches with the internal logic of the work • Size : the work is at the right amount that the workers are capable to undertake The works that are ready but cannot be assigned are listed under Workable Backlog. The works under this list will be brought up when there are workers who finished their works before the scheduled time.
Figure 3.6. Four Levels of LPS Source: Schimanski et al., 2020
page 21
LPS is well implemented in combination with the obeya and Visual Management Centre (VMC).
Obeya or Big Room is a concept where collaboration with the directly-involved stakeholders happens in a coordination office located on the construction site (Temel et al., 2019). Visual Management Centre is a communication method where data is displayed in a way that can be easily understood at a glance, self-explanatory, and self-improving (Galsworth, 1997; Greif, 1991) The output of the four levels in LPS are collaboratively discussed and updated accordingly. During the discussion, all stakeholders are at the equal levels to give suggestions and inputs. By combining these three principles, LPS promotes effective co-location in the workplace.
1.
Master Schedule It starts by translating the client’s requirements into a program. Milestones and critical path are assessed
2.
Figure 3.7. Master Schedule
3.
Look-ahead Plan breaks down the tasks into the level of process then to the level of operations for the next 3-4 weeks ahead
Figure 3.9. Look-ahead Plan
Phase Plan develop the network of activities and backwards plan to determine the earliest practical start date
Figure 3.8. Phase Plan
4.
Weekly Work Plan filter what will be done to what can be performed in one week. Non-ready tasks are placed in workable backlog/plan b
Figure 3.10. Weekly Work Plan
page 22
JUST-IN-TIME STRATEGY AND IMPLEMENTATION
Inventory Management
Kanban
Total Quality Management
Line of Balance
Last Planner System
Production Management
Pre-fabrication
An assessment on the WWP is measured through Percent Plan Complete (PPC). PPC is a metric to measure the reliability of the weekly work planning process and the process of making reliable promises. The reliability is measured by tracking the number of commitments made and the realisations. By having PPC, MP Construction can monitor the performance of every subcontractors in the project. This is a very powerful statistic to document, especially when MP Construction is implementing partnership with other supply chain actors (see 3.2 Partnership). Following a PPC, MP Contractor can develop a Root Cause Analysis for the “promises� that are not undertaken. Root Cause Analysis enables MP Contractor to reflect on the mistakes and undergo continuous improvement for the tasks on the following weeks. All in all, LPS allows subcontractors to understand the overall construction process better. It drives the subcontractors to work integrated as a team than individually. Professor Ballard states that there are at least 3 benefits of the LPS implementation: 1. reduce cost risk by improving productivity 2. reduce durations by improving coordination between trades 3. develop corporate and individual capability by reflection, learning and continual improvement
Figure 3.11. Promises - PPC
Figure 3.12. Make Ready - PPC
page 23
IMPLEMENTATION CONT. & SUCCESS STORY
PPC compares the tasks that are planned to be done and the tasks that have been completed. A task on PPC board means a commitment from the front-line supervisor to do the task. The simplest measurement is done through an interactive board with sticky notes that can be moved from “promises” to “make ready” (Figure 3.11, Figure 3.12). The PPC for the day is to be calculated at the end of the day. PPC =
Tasks completed as planned Total tasks planned
x 100%
Although PPC is measured in percentage, it should be understood as a measurement of a team’s ability to reliably plan and execute work rather than a measurement of completed work. Hence, performance analysis and root cause analysis that lead to improvement should follow (Figure 3.13, Figure 3.14). Root cause analysis monitors duration of the executed activities and the reasons why certain activities are performed early, late or are not performed.
Figure 3.13. Performance Analysis
Figure 3.14. Root Cause Analysis
SKANSKA FINLAND (Ballard et al., 2010) This case study combines the implementation of LPS and Location-Based Management System (LBMS), which has the same concept of Line of Balance.
Skanska Finland is one of the construction companies in US. It brings to practice the implementation of LPS and LBMS. This case study is based on Skanska Finland’s project, a 21-story residential building. The result emphasises the significance of integrating LPS and LBMS in the master scheduling, pull phase scheduling, lookahead scheduling, and weekly planning.
Construction Time
4 days
The tight schedule of 5 days for each floor is further reduced to 4 days for each floor Reliability & Productivity
14 %
An increase from 64% to 78% weekly task completion (based on the PPC result)
page 24
JUST-IN-TIME STRATEGY AND IMPLEMENTATION
Inventory Management
Kanban
Total Quality Management
Line of Balance Last Planner System
Production Management
Pre-fabrication
Prefabrication is a method that supports the application of Just-in-Time philosophy in the industry. Schonberger (1982) defines prefabrication as a process that includes producing finished sub-products off site and delivering to the site to be assembled into a finished product. Prefabrication is evident to bring higher quality, more effective and efficient construction process. The efficiency is driven by the exclusion from the unconducive on-site conditions. Prefabrication allows each sub-product to be produced under a controlled environment in the factory. This does not only hinder obstructions by inclement weather, but also by workers availability. Research by Gann 1996; Venables et al. 2004; Lu 2009 also asserts that prefabrication also increase safety performance on site. However, the best practice of prefabrication can be achieved only with mature planning, especially during the design process (Luo et al., 2005). Prefabrication will only be possible if it is included in the design (McGrawHill 2011). The designer team, contractor, suppliers and manufacturers have to work together to ensure the demand from the client is delivered clearly and proceed without any defects. Planning process becomes very crucial in this practice because prefabrication products are generally leadtime products. Defects and reworks in this practice will significantly prolong the project planned duration. The implementation of prefabrication can be started from the lower degree (non-volumetric products or components) such as unitised curtain wall, wall panel, pracast staircase.
Table 3.1. Levels of Prefabrication
Blismas and Wakefield Smith
-
Non-volumetric preassembly
Volumetric preassembly
Modular building
Material
Component
Panel
Module
page 25
SUCCESS STORY
The success story for prefabrication is taken from a lot of cases instead of one project. Overall, prefabrication brings advantages such as reduction of waste and dust, reduction of material, reduction of labour demand, and others (Jaillon & Poon, 2013). The full advantages are shown in Figure 3.16.
BUILDING MATERIALS RECYCLABILITY AND CONSTRUCTION WASTE RECYCLABILITY (Pons & Wadel, 2011)
50%
45%
40%
35%
30%
Recyclable construction waste
25%
20% 10%
10%
5%
3%
2%
1% Nonprefabricated
Concrete
Timber
Recyclable building materials
Steel
SOLID WASTE PER BUILDING PHASE (Pons & Wadel, 2011) Nonprefabricated Concrete Timber Steel
Figure 3.15. Solid Waste
TOTAL SOLID WASTE IN BUILDING LIFECYCLE
ADVANTAGES OF USING PRECAST ELEMENTS
(Pons & Wadel, 2011)
(Jaillon & Poon, 2013) Reduction of construction time Reduction of dust
4178 kg/m2 ~ 100%
Reduction of noise
SOLID WASTE
2490 kg/m2 ~ 60%
Improved health and safety
2229 kg/m2
Improved site management
~ 53% 1253 kg/m2
Improved productivity
~ 30% Nonprefabricated
Improved ease of construction
Concrete
Timber
Steel
Reduction of program time Reduction of program time Reduction of material use Improved quality control Reduction of labour demand
Project cost savings
Average score in dense urban environment
Figure 3.16. Advantages of Prefabrication
page 26
3.0
Section 2: Redesign Strategies
3.2 Partnership II
&
III
1. non transparent relation between project 2. 3. 4. 5. 6. 7.
stakeholders project-to-project basis separated from the design teams no incentive for the contractor to innovate long time because of sequential process few points of responsibility unbuildable design
Identification
Implementation 1
separation of team unhealthy relationship
Partnership
wasted time
Implementation 2
Implementation 3
Performance
D&C
Reduction in
Supply chains
assessment
Contract
number
consolidation
Partnership is defined as a commitment by parties to work closely or cooperatively (integration of team) based on trust and respect rather than suspicion and skepticism (healthy relationship) (Gunn, 2002; Australian Government, 2015). The end goal of partnership is coalescence between parties at the organisational level (alliancing), which is rather a long term than at the project-to-project basis (MacDonald, 2005). The implementation of partnership at the organisational level enables the involved parties to save money and time for the competitive tendering (time and money). The seven problems listed in the II & III priority group can be summarised into three root causes: separation of team, unhealthy relationship, and wasted time. These problems are arisen from MP Construction’s current practices: traditional procurement method, competitive tendering, and projectby-project basis subcontractors and suppliers. By forging partnership with the selected subcontractors and suppliers, MP Construction is able to enhance its performance. MP Construction can start building partnership with its subcontractors and suppliers after implementing JIT philosophy. The steps are as follows: 1. Performance assessment : based on the PPC output from the JIT 2. Design & Construct contract : enter the market of D&C procurement projects to understand the holistic process of project delivery 3. Reduction in number : shortlist the subcontractors and suppliers based on their performance 4. Supply chains consolidation : build and maintain the commitment based on trust This section will elaborate in detail the steps that MP Construction should undertake, and how these steps are effective to overcome the problems listed above.
page 27
IP H S
R E N
T R PA
SUPPLY CHAINS CONSOLIDATION
TS IN U
E M TI
J
REDUCTION IN NUMBER
D&C CONTRACTS
PREFABRICATION
LINE OF BALANCE
KANBAN SYSTEM
LAST PLANNER SYSTEM
page 28
PARTNERSHIP STRATEGY AND IMPLEMENTATION
Identification
Level 1 - Traditional
According to Ellison and Miller (1995), there are four levels of partnership in the industry. From the lowest to the highest, the levels are as follows: 1. Traditional : adversarial arms-length contractual 2. Basic Partnering : collaborative team oriented 3. Full Partnering : value added integrating team 4. Alliancing : synergistic strategic partnership
Implementation
1 - Design and Construct Contract 2 - Reduction in number of partners 3 - Supply chains consolidation
The detail of each term is elaborated in Table 3.2 on the next page. Although the terms partnership and alliancing are often used interchangeably, this table clearly shows that they are different under definitions. Partnership is a commitment where the independence between parties is still retained often by establishing a new entity for the partnering purpose. Alliancing, however, is the most advanced level of partnership. Both parties are jointly coalesced to fully share rewards and risks. Since its establishment, MP Construction has been maintaining relationship with its subcontractors and suppliers with the following characteristics: contractual relationship with the options of disputes resolution
continuous supervision to maintain quality
interconnected work with independent responsibilities
one off relationship or project-byproject basis
Based on these characteristics, the relationship developed by MP Construction is considered as the level 1 - adversarial arms-length relationship (Table 3.2 on the next page). Ellison and Miller (1995) define this lowest level as “traditional” relationship rather than a “partnership”. This is because the fundamental notion of partnership is trust, which is not yet found in the Level 1 - Traditional relationship. The recommendation for MP Construction at this stage is to implement Level 2 - Basic Partnership. Establishing alliancing with the upstream parties will be very challenging as MP Construction has limited experience in this practice. It is suggested that MP Construction improves its relationship gradually. In this instance, MP Construction should take into consideration the readiness of its subcontractors and suppliers. Improving the partnership level step by step ensures that MP Construction and its subcontractors are at a greater readiness.
page 29
Table 3.2. Four levels of partnership Source : Ellison and Miller (1995), adapted from Walker & Hampson (2003) Level 1 – Traditional
Level 2 – Basic Partnering
Level 3 - Full Partnering
Level 4 - Alliancing
Adversarial Arms-
Collaborative Team
Value added Integrating
Synergistic Strategic
length Contract
Oriented
Team
Partnership
Competition
Cooperation
Collaboration
Coalescence
Each side has
• Each side knows and
• One integrated team
• Elements of shared risk
clearly established
commits to the goals of the consisting of both client
also defined
responsibilities
project and to each other’s
and contractors personnel
• Joint sharing of liabilities
• Client ‘monitors and goals – requires a degree
is created – requires a high
for project failure
inspects’ contractor
degree of trust
• Joint sharing of gains
• This team has one set
• Both sides share their
of goals for a successful
goals and cost – requires
project
extremely high trust
of trust
• Little or no trust
• Team often creates a separate organisational entity for the life of the project • Often adversarial
• Significant energy in
• Accountability is
• Curve on benefits is
• Often creates
communications and ‘win-
collective among the
logarithmic – based
disputes, sometimes
win’ conflict resolution
integrated team
on meeting and then
litigation
• Disputes typically
• Both client and
exceeding project goals
resolved in some degree of
contractor provided senior
• The essence of the
compromise and harmony
level ‘sponsors’ to remove
relationship is to increase
barriers and support the
the mutual profitability of
project
both parties • Neither at the expense of the other • Both at creating new and synergistic solutions
Both sides are
• Established for early
Typically included some
• Requires extensive
plagued by schedule
positive intervention
incentive for exceeding
communication,
slips and cost
• Projects often
project goals
collaboration and
overruns
accomplished on schedule
organisational
and within budget
commitment and sponsorship • Creates the opportunities for major breakthrough
current practice in MP Construction
first target for MP Construction
end goal of partnership
page 30
PARTNERSHIP STRATEGY AND IMPLEMENTATION
Identification
Level 1 - Traditional
Implementation
Step 1 - Design and Construct Contract Step 2 - Reduction in number of partners Step 3 - Consolidation in supply chains
Currently, MP Construction is engaged in all projects under traditional type of contract. It is a procurement method that is widely used on simple projects with non-complex management techniques and engineering skills (Seng & Yusof, 2006). This contract requires MP Construction to manage the construction risks from the perspective of a construct-only contractor. MP Construction’s responsibilities are limited mainly due to the fact that the projects are often architect-led, and the design has been fully documented (Cooke & Williams, 2009). In contrast, Design and Construct (D&C) procurement method, that is experiencing a significant increase in the number of users, allows contractor to have higher control and responsibilities in the overall delivery stages (Hibbert & Djebarni, 2017). Rather than led by the design team, the contractor is the only party engaged by the client. In this instance, the contractor is responsible for the project from the planning process, including the design, to the execution process. A shift from a construct-only contractor to a D&C contractor enables MP Construction to get a complete experience in delivering a project. The learning takeaway that can be obtained are: » balance out the design and buildability » value engineering management to find the most valuable solution in the project » adjust the schedule and program of a project » maintaining and controlling the quality on site (Seng & Yusof, 2006)
Therefore, the recommendation is for MP Construction to gradually reconstruct the organisation to facilitate the practice of D&C in the projects. These are strategies to prepare for D&C procurement:
Set up an inhouse designer team to prepare the design, in case designer is not novated
Set up an in-house value engineering team to achieve the most valuable design and planning process
Hire capable consultant team to provide consultancy and monitor the process
Establish success criteria as benchmark to control and improve performance
Learning and development for all workers about D&C procurement method
page 31
PARTNERSHIP STRATEGY AND IMPLEMENTATION
Identification
Level 1 - Traditional
Implementation
Step 1 - Design and Construct Contract
Although partnership can bring positive impacts to the MP Construction performance, establishing partnership for all subcontractors and suppliers is not feasible. It is because partnership relies on win-win and lose-lose relationship. Having too many parties will not be profitable for all parties. MP Construction must select the most suitable subcontractors and suppliers to be partnered with. The assessment can be started from the outcome of the PPC assessment from the JIT practice (Figure 3.17). On top of this, MP Construction should assess at least the following factors:
Step 2 - Reduction in number of partners financial condition
managerial competency
quality
cost
business scope
corporate value
Step 3 - Consolidation in supply chains
MP Construction should establish weighting criteria with a benchmark to assess the performance of each subcontractor. A template of the weighting criteria is attached in Appendix F for MP Construction to review. This matrix can be adjusted to suit MP Construction’s requirements. Based on this score, MP Construction selects the potential partners. It should be kept between:
2 or 3 subcontractors / trade These numbers are suggested with the foundation of Bennet & Jayes‘ research in 1995. Two or three subcontractors are believed as the right number to maintain the level of competition while keep preserving the effective partnership (Bennet & Jayes, 1995). If there is no subcontractors or suppliers that hit the benchmark, MP Construction should conduct further investigation as well as engage consultant to give perspective on this matter. Figure 3.17. PPC Performance
page 32
PARTNERSHIP STRATEGY AND IMPLEMENTATION
Identification
Level 1 - Traditional
After selecting the subcontractors and suppliers, partnership is commenced by defining the aim, scope, and responsibilities of each party. A new entity can be set up after unanimous goal and strategy are well defined. The technical strategy to consolidate the supply chains is adopted from the Construction Extension PMBOK (2016).
Implementation
Step 1 - Design and Construct Contract
Monitoring and
Strategy
Initiation
Planning
Execution
based on
Identify partners
Plan partner management
Manage partner engagement
Control and improve partner engagement
Due diligence
Web-based communica-
Information/ progress
Consultation and discussion
tion strategy
updates
Partner engagement
Partner engagement
Updated engagement
plan
matrix
matrix
PMBOK
Controlling
Step 2 - Reduction in number of partners
Industry Application
Step 3 Consolidation in supply chains
Partner register
Outcome/ Output
Mutually beneficial partnership
(see at Appendix G)
(see at Appendix H)
(see at Appendix I)
Dissimilar to the JIT, strategy for partnership is a process that requires longer preparation time. A bit too long is better than a bit too short time because it is critical to ensure MP Construction and its partners are ready to engage in partnership. It is not only their commitment that matters, but also their management, administration, technology, etc. The proposed timeline is shown as follows: July 2020
July 2021
July 2025
Dec 2025
JIT practices Partnership: subcontractors assessment process Partnership: Step 1 - D&C implementation Partnership: Step 2 Reduction in numbers
Partnership: Step 3 - Consolidation of Level 2 - Basic Partnership towards Level 4 - Alliancing
page 33
SUCCESS STORY
SKANSKA & ROCKWOOL
(IMD, 1996)
Skanska was suffering a recession that forced them to lay off 17% of their workers. Its partnership with Rockwool optimised the resources and cost and reduce the lead time. On the other hand, Rockwool was benefited by the reduction of inventory on the factory, hence manufacturing process can be optimised. For both parties, this partnership leads to long-term security, material flows improvement, cost efficiency, and knowledge improvement.
75 %
Partnership
70-80
Reduction of company retailers from 1000 to around 70 to 80
Construction Cost
10 %
Reduction of cost by 10% on 3,000 construction sites
Loading Time
Waste Emissions
Reduction of 75% in loading time by using palette
Reduction of waste due to the effective packaging
BAA HEATHROW T5
(Pyrke, 2009)
British Airport Authority (BAA) established partnership with its subcontractors in T5 project. BAA took a decision to bear the risks of the other parties so that they did not focus on increasing their profits. A set of guidelines called Continuous Improvement of the Project Process (CIPP) was made to ensure consistency in the project. The performance of all parties is monitored by BAA through a data capturing system for continual improvement. Turned out, this partnership resulted in favourable outcome as no one expected.
Construction Cost
40 %
The project was on budget, while it was estimated to experience 40% cost overruns Construction Time
2 years
The project was on time despite the estimation of 2 years late
Effective applications of JIT and partnership results in a better performance of the business. After successfully implementing JIT and partnership, MP Construction will have a more effective supply chain map as shown on the next page.
REDESIGNED SUPPLY CHAIN MAP
page 35
page 36
4.0
STEP 3: CONTROL Monitoring and Control
4.1 Significance of Monitoring and Control “the Monitoring and Control Process Group consists of those processes performed to observe project execution so that potential problems can be identified in a timely manner and corrective action can be taken, when necessary, to control the execution of the project.�
~~ Project Management Body of Knowledge, 2016 Following the execution of the strategies, monitoring and control (M&C) process needs to be carried out. At a high level, this process aims to make sure that the execution is still on the track to achieve the desired goals. This sentence emphasises how excellent planning will be fruitless without a good M&C. As much as possible, M&C tries to eliminate the element of surprise during the execution; ensuring each process is under control. Hence, identifying potential problems and keeping everyone informed are keys in this instance. The process of M&C commences as the project commences. It is made possible by assessing the undertaken works against the predetermined standards. The non-conformances in M&C output will be reported, and preventive and/or corrective actions will be taken accordingly (Figure 4.1). Monitoring & Control
Initiation
Planning
Execution
Reporting
Closing
Change Request
Figure 4.1. Model of a Project Flow
During the M&C process, the best outcome is achieved when the problem is identified before it becomes a mistake. However, it has to be balanced with a team who is capable to analyse and propose effective preventive actions. The importance of these aspects is emphasised by Bernold and Abourizk (2010) that summarised three characteristics of an effective M&C system:
Provides real-time feedback
Provides feed forward predictions
Provides data for trend analysis
page 37
& L O R T VE N CO PRO IM IH P S R E N T R E PA M I T TS IN JU
CONTINUOUS IMPROVEMENT
KPIs TO CONTROL
SUPPLY CHAINS CONSOLIDATION
REDUCTION IN NUMBER
D&C CONTRACTS
PREFABRICATION
LINE OF BALANCE
KANBAN SYSTEM
LAST PLANNER SYSTEM
page 38
4.2 Implementation In order to identify the performance, MP Construction should establish Key Performance Indicators (KPIs). The KPIs can be adopted from the relevant guidance and standards, generally, or developed from MP Construction’s values, specifically. MP Construction should establish two sets of KPIs to exclusively assess the overall project performance and the performance of each partner. The two sets facilitate the management team to identify the areas of improvement at the project level and at the organisational level. Table 4.1. Assessment Criteria Project Level
schedule
quality
safety
Organisational Level (partner)
cost
collaboration & engagement
trust & transparency
innovation & improvement
PPC Performance from JIT on site productivity
scope and variations
reworks on project
Referring to Table 4.1, MP Construction should set benchmarks for the parameters set on the first row. The benchmark should provide a clear line between a good a bad performance. For these parameters, the performance of each partner is assessed against the benchmarks. The three measurements on the second row: on site productivity, scope and variations, and reworks on project are to be assessed at both project level and organisational level. For these parameters, the performance of each partner is assessed relative to the performance of particular criterion at the project level. Performance that is below the project performance is considered as bad performance, and the performance above the project performance is considered as a good performance. It should be noted that all these parameters are to be measured in addition to the PPC performance from the JIT practice. The example of performance indicators can be seen on Table 4.2 and Table 4.3 on the next page. Another important thing in M&C process is the stakeholders, especially those who are involved on their interests, such as unions, local communities, government authorities, environmental organisations, and NGOs. Their satisfactions are crucial to ensure the project moves forward (PMBOK, 2016). Chinyio & Olomolaiye (2010) further emphasise that a failure to meet stakeholder’s requirements often leads to project failure.
page 39
Table 4.2. Project Performance Indicators PROJECT PERFORMANCE Category Schedule
Parameter
Description
SPI - Schedule
the work earned
Performance Index Quality
Performance Indicators U
NI
ME
S
E
<2
<1
=1
>1
>2
>0.8%
>0.5%
>=0.3%
<0.3%
<0.2%
>=7
>=6.8
<6.8
<6.3
<5.5
>=16
>=15.3
<15.3
<14.8
<14.3
>=35
>=33.5
<32.5
<31.5
<30
<2
<1
=1
>1
>2
>=2.3%
>=1.7%
<1.7%
<1%
<0.6%
<-5.0%
<0%
=0%
>0%
>5.0%
<-1.5%
<0%
=0%
>0%
>1.5%
the work scheduled
Rework %
total rework cost total scheduled cost
Safety
Cost
LTIFR: Lost Time Injury
total lost time injury per million
Frequency Rate
hours worked
TRIF: Total Recordable
total recordable injury per
Injury Frequency
million hours worked
SIF: Serious Incident
total serious incident per
Frequency
million hours worked
CPI: Cost Performance
the work earned
Index
the actual cost spent
Productivity FDS: Foreman Delay Survey Variations
based on questionnaire in the Appendix A and Appendix B
CV%: Cost Variance %
earned work - actual cost earned work
SV%: Scheduled
earned work - scheduled work
Variance %
scheduled work
Table 4.3. Partner Performance Indicators PARTNER PERFORMANCE Category
Parameter
Description
Performance Indicators U
NI
ME
S
Low
Med
High
Trust
transparency
openness to the partnership
Collaboration
No. of disputes
disputes between parties
>5
>2
1-2
0
Communication
% of information received
<70%
<=85%
>85%
>90%
E
>95%
correctly within the time Innovation Quality
Engagement
actively engaged in partnership
Low
Med
High
Shared knowledge
eager to share knowledge
Low
Med
High
Improvement
innovation to improve
Low
Med
High
>0.8%
>0.5%
>=0.3%
<0.3%
<0.2%
>=2.3%
>=1.7%
<1.7%
<1%
<0.6%
<P
=P
>P
<P
=P
>P
Rework % (compare to project)
Productivity Variations
total scheduled cost
FDS: Foreman Delay
based on questionnaire in the
Survey
Appendix A and Appendix B
CV%: Cost Variance %
(compare to project)
total rework cost
earned work - actual cost earned work
SV%: Scheduled Variance %
U : Unsatisfactory NI : Need improvement
earned work - scheduled work scheduled work ME : Meet Expectation S : Satisfactory
E : Excellent
page 40
STEP 4: IMPROVE
5.0
Continuous Improvement
The last step in the supply chain management strategy is to preserve what has been learnt at the organisational level (kaizen). Often, this step is the most challenging after all. In this section, the proposed suggestion is based on the Japanese philosophy of jishuken. Jishuken literally means study group, or in the manufacturing industry can be defined as a means of learning with subcontractors or suppliers. Jishuken is introduced in Toyota Production System where Toyota supplier association is established consisting of the core Toyota’s suppliers. They regularly meet during the year, share practices, information and concerns. Research shows that this practice results in positive feedback on the overall Toyota production (Dyer & Hatch, 2004). In MP Construction, jishuken will be implemented in the form of a workshop involving the partners in the partnership. There are two types of workshop to be conducted:
Obeya meeting
main partners
1-2
representatives per partner
1-2x
per month
1
partner
1-2
representatives
Regular Partnership Workshops The general purpose of the workshop is to resolve views and opinions regarding partner’s interests. During this workshop, MP Construction will review the highlights occurred in the project: the issues and the achieved milestones. The project performance and the overall partners’ performance will be discussed based on the predetermined criteria (Table 4.2, Table 4.3). From this workshop, MP Construction and every partner are able to get general feedback for improvement. The presence of this workshop is expected to: » ensure a balance between the use of communication technology and the amount of information delivered » maintain trust and transparency » share knowledge » increase understanding about the project » regularly follow up partners and keep them updated » create a culture among the partners to collaboratively think about the project as a whole One-on-one Partnership Meeting In addition to the regular collaborative workshop, occasional one-to-one workshop is suggested to be carried out when needed. MP Construction is suggested to arrange this workshop with partner that gets “NI” or “U” for the same criterion two times in a row (Table 4.3). The workshop is to accommodate consultancy and collaboration with the partner; supporting them to continuously improve as an entity and as a partner in the partnership. If the partner does not show improvement, or more importantly a good intention to improve, MP Construction may consider reassessing the partnership with this partner.
page 41
SUCCESS STORY
Continuous improvement is about establishing a culture. The improvement strategies need to be assessed against the predetermined objectives (Figure 5.1). The strategies that are evident to bring the intended outcome should be adopted a new standard. By implementing this standard, MP Construction is forced to carry out a better normal that leads to continual improvement. set the reviewed strategies as companyâ&#x20AC;&#x2122;s standards continuous improvement review the standards for improvement Figure 5.1. Continuous Improvement
As has been elaborated in this report, a partnership, or rather alliancing, will be able to deliver a project in shorter time, higher profit, and better quality. Hence, balancing the golden triangle of time-costQUALITY quality.
COST
COST
MPC
MPC
TIME
QUALITY
TIME
Figure 5.2. The Golden Triangle
JAPANESE CONTRACTOR (Bennet, 1993) The observation has been done by Bennet in one of the big five contractors in Japan.
TAISEI
KAJIMA
OBAYASHI
SHIMIZU
TAKENAKA
Within the subcontractorâ&#x20AC;&#x2122;s site-based team, a small group of 5-6 people is created. They met 5-12 times within 2 to 5 months to discussed work-related problems. The solutions are then brought up to a bigger presentation with other subcontractors in which report were made into a book of 76 pages.
5-6
people
5-12x
in 2-5 months
10
subcons.
76
pages report
page 42
6.0
TOWARDS RESILIENT BUSINESS Builder and Developer
The strategies to improve the business performance have been discussed. When these strategies are carried out side by side with the implementation of M&C, continual improvement can be achieved in the business. MP Construction and partners will perform as a leading supply chain in construction industry. My big commitment with MP Construction has made me go beyond the business performance improvement that the board requested. Despite the benefits that it brings, establishing a supply chain in construction industry is not yet the ultimate goal. This is because alliancing still relies on the demand from the client. Alliancing encourages MP Construction to forge as many good relationships as possible in the industry. The more relationships it builds, the healthier the alliancing will be. Without demand from the market, the business will not run smoothly. Based on these circumstances, for MP Construction to be a resilient business, a slight shift in the nature of the business should be made in the long run. After having much experience and mastering in alliancing, MP Construction can
I
&
II
II
1. 2. 3. 4. 5. 6.
longer time bigger unexpected risk constrained by the workers availability labour intensive and labour expensive more expensive compromised quality on the final product 7. low profit margin 8. wasting time and money 9. inefficient expenses
&
consider to concurrently provide construction service as well as initiate a project. In other words, the next step is to be a builder and a developer. The benefits of being both developer and builder are: » loosen MP Construction’s dependency to the project demand; be more resilient in the industry » shorten the overall project timeline by eliminating the time to tender the project to the contractor » reduce potential disputes between client and contractors » speed up communication and clarification of information While this strategy maintains MP Construction sustainability in the long run, the implementation of this strategy is not urgent. This is also not the core actions to improve the business performance. Therefore, in the illustration, it is depicted as a building envelope that supports the function of a building but does not affect the structural integrity (see the next page). This practice does not change the overall supply chain map except the number of clients that can be reduced.
III
1. non transparent relation between project stakeholders
2. project-to-project basis 3. separated from the design teams 4. no incentive for the contractor to innovate
5. long time because of sequential process
6. few points of responsibility 7. unbuildable design
Solutions / Strategies Just-In-Time (JIT)
towards resilient business
Long Term Strategy Partnership
Builder + Developer
page 43
T C E J O N R P TIO A I T INI & L RO E T N OV O C PR IM IP H S R E N T R E PA M I T TS IN JU
INITIATE PROJECTS
CONTINUOUS IMPROVEMENT
KPIs TO CONTROL
SUPPLY CHAINS CONSOLIDATION
REDUCTION IN NUMBER
D&C CONTRACTS
PREFABRICATION
LINE OF BALANCE
KANBAN SYSTEM
LAST PLANNER SYSTEM
RESILIENT SUPPLY CHAIN MAP
MP Construction becomes less dependent with the client as it starts to initiate its own projects. MP Construction can focus on few clients that MP Construction is comfortable to work with or big clients that own prestigious projects
page 45
page 46
7.0
FINANCIAL PLAN
The cost estimated in the Financial Plan only
$890,000
considers the indirect capital cost. Direct cost such as labour, materials, and task-related equipment are excluded from the estimation.
Kanban - JIT
Prefabrication - JIT
$250,000
$400,000
The cost is calculated based on 30 subcontractors on site (refer to the redesigned supply chain map) times the estimated cost to provide kanban stillage at $5,000 each, and a warehouse to store the stillage.
The cost includes the price of software and hardware, machinery cost (loading-unloading equipment, vertical transportation) and on-site storage. It excludes additional cost of delivery, extra supervisors, maintenance etc. The estimation is based on the research study by Hong et al. (2018) and Antillon, et al. (2014).
Line of Balance - JIT
$40,000 This cost includes the cost of new software and hardware needed. The cost of employees who will do the monitoring and reporting is excluded.
Last Planner System - JIT
$50,000 Last planner system needs a dedicated large room on site to display the VMC and hold daily and weekly meetings.
Partnership
$150,000 The cost is estimated for EDI and single model environment (SME). The cost of specialised consultant or employees required are excluded.
S S E
page 47
N I S
T C E J O N R P TIO IA T I IN & L O R T VE N CO PRO IM IP H S R E N T R E PA IT M IT N S U J
E
I L I
S E R
NT
BU
INITIATE PROJECTS
CONTINUOUS IMPROVEMENT
KPIs TO CONTROL
SUPPLY CHAINS CONSOLIDATION
REDUCTION IN NUMBER
D&C CONTRACTS
PREFABRICATION
LINE OF BALANCE
KANBAN SYSTEM
LAST PLANNER SYSTEM
page 48
REPORT LIMITATIONS
8.0
Despite the evident-based data that have been presented, this report has several limitations:
Limitation 1 - Just-In-Time (JIT) This report only covers four areas which are seen as the most significant aspects to support the Just-In-Time practice in MP Construction. Jidoka philosophy (autonomation) which is another pillar of lean thinking in TPS is not explored. This concept helps in achieving excellent quality by ensuring that product flow is stopped when defects are identified.
Limitation 2 - Partnership This report focuses on the partnership of the downstream actors. The upstream actors are not included in the partnership. As a result, the reduction of time occurs only on the downstream. Further time saving is possible to achieve if the upstream supply chains are also establishing partnership.
Limitation 3 - Supply Chain Map The supply chain map provided in this report is the simplified version and only considers the general nodes on projects. It is not comprehensive nor project specifics. Hence, the understanding about the flows might be limited. The supply chain map should not be referred as a sole foundation to conduct an action.
Limitation 4 - Constraints This report starts the timeline in June 2020. It does not consider internal or external problems that might hinder MP Construction to delay the implementation of the strategies. The neglected constraints include the unfavourable condition due to COVID-19 pandemic, resources availability and resources capability (workers, fund, materials). It is recommended that MP Construction conducts feasibility study before implementing the strategies
page 49
CONCLUSION
9.0 “Strength and growth come only through continuous effort and struggle.” – Napoleon Hill
MP Construction shows excellent performance in product quality but low performance in cost and time. The underlying reasons are MP Construction’s current practices of traditional contracts, competitive tendering, project-by-project based, traditional on-site construction method, and poor workmanship. MP Construction’s efforts to maintain the quality gives up its performance in cost and time. This report has assessed the root causes and proposed two strategies to solve the problems. Just-In-Time (JIT) and partnership are considered as the most effective methods to increase MP Construction performance on cost and time, while keep maintaining the quality. JIT is made possible by implementing four key actions: the use of kanban, line of balance, last planner system, and prefabrication. They enable MP Construction to have bigger control on site, and hence increase productivity and efficiency on site. Partnership is implemented by reducing the number of partners followed by the consolidation of supply chains. This scenario will be facilitated by the comprehensive understanding on the process of delivering a project. Therefore, it is suggested that MP Construction enters the D&C market before going into a partnership. The implementation of JIT and partnership are expected to cut the unnecessary cost and time used by MP Construction to increase the quality. Going side by side with the improvement strategies, monitoring and control process needs to be carried out. Key performance indicators have to be established, and performance assessment against these KPIs has to be made regularly. Improvement strategy that results in better performance should be adopted to a new company standard to allow for continuous improvement. Additionally, after these two strategies are entrenched in day-to-day practices, MP Construction may consider striving for a resilient business by being a developer as well as a contractor.
page 50
BIBLIOGRAPHY
10.0
Aalto, O. S. E. (2005). A case study of line-of-balance based schedule planning and control system. Adrian Wilkinson, T. R., Ed Snape and Mick Marchington. (1998). Managing with total quality management: Theory and practice. London: Macmillan Press Ltd. ak, S. C. G. e. (1993 ). Logistics of production and inventory (Vol. 4). Oxford: Elsevier BV. B.A. Temel, H. B. B., M. Uluçay Temel, G. Kamber Yılmaz, & M.M. Nasery. (2019). Big room concept in project management and control. Construction Engineering, Management & Innovation, 2(4), 204214. Bennett, J. (1993). Japan’s building industry: The new model. Construction Management and Economics, 11, 3-17. Bleby, M. (2 January 2018). Turning construction on its side: Probuild cuts building time, labour costs. Financial Review. Burer, C. (2016). Workmanship in construction of small and medium hospitality enterprises in nairobi central business district. C.P. Schimanski, C. M., G.P. Monizza, and D.T. Matt. (2020). The last planner® system and building information modeling in construction execution: From an integrative review to a conceptual model for integration. Applied Sciences, 10, 29. Construction giant probuild strives for zero purchaser defects. (22 August 2018). Construction stakeholder management. (2010). (P. O. Ezekiel Chinyio Ed.). West Sussex, UK: Wiley Blackwell. Dekker, N. (2017). Supply chain in construction – why implement supply chain management. Djebarni, P. H. R. (2017). Criteria choice for procurement methods. 9. Essays, U. (November 2018). Just in time manufacturing: Toyota. Retrieved from https://www.ukessays. com/essays/marketing/just-in-time-manufacturing-for-toyota-marketing-essay.php?vref=1 Farmer, M. (2016). The farmer review of the uk construction labour model: Modernise or die. (17/10/16), 80. Retrieved from CIOB website: https://policy.ciob.org/wp-content/uploads/2016/10/The-Farmer-Reviewof-the-UK-Construction-Labour-Model.pdf French, E. F. F. K. R. (2000). Forecasting profitability and earnings. The Journal of Business, 73, 16. Galsworth, G. D. (1997). Visual systems: Harnessing the power of visual workplace. New York, USA: AMACOM. Government, A. (September 2015). National alliance contracting guidelines: Guide to alliance contracting. Canberra, Australia. Greif, M. (1991). The visual factory: Building participation through shared information. Portland, USA: Productivity Press. Hackitt, D. J. (2017). Building a safe future: Independent review of building regulations and fire safety. Hampson, D. W. K. (2003). Procurement strategies – a relationship base approach. Blackwell, Oxford. Hatch, J. H. D. N. W. (2004). Using supplier networks to learn faster. MIT Sloan Management Review, 45(3), 9. Hui, L. S. P. M. S. (1999). The application of jit philosophy to construction: A case study in site layout. Construction Management and Economics, 17(5), 757-668.
page 51
Janaka, N. H. K. a. Y. R. (2006). Carpentry workers issues and efficiencies related to construction productivity in commercial construction projects in alberta. Canadian Journal of Civil Engineering, 33, 15. Jon Gunn, S. C., & Minter Ellison. (2002). The effective use of partnering and alliancing. 19. Jones, M. (2018). Is constructing excellence still relevant? Retrieved from Constructing Excellence delivered with bre website: https://constructingexcellence.org.uk/is-constructing-excellence-stillrelevant/ KIHONG KU, P. B., ANTHONY COLONNA. (2012). Towards on-site fabrication: A case study on multitrade prefabrication. M. Soini, I. L., & O. Seppänen. (2004). â&#x20AC;&#x153;Implementation of line-of-balance based scheduling and project control system in a large construction company. Retrieved from Elsinore, Denmark: M.M.A. Khalfan, P. M., A.S. Oyegoke, M.T. Dickinson, X. Li, & D. Neilson. (2008). Application of kanban in the uk construction industry by public sector clients. Paper presented at the 16th Annual Conference of the International Group for Lean Construction, United States. MacDonald, C. (2005). What are the important differences between partnering and alliance procurement models and why are the terms so seldom confused?, 8. Malo, J. (15 June 2018). Probuild pioneers new apartment construction method, but will consumers benefit? Miller, S. E. D. (1995). Beyond adr, working towards synergistic strategic partnerships. Journal of Management in Engineering, 6, 44-54. PMBOK. (2016). Construction extension of pmbok guide. In. Pyrke, S. (2009). Construction supply chain management. Oxford, UK: Wiley-Blackwell. S. Chopra, P. M. (2007). Supply chain management: Strategy, planning, and operation (3 ed.). Upper Saddle River, NJ: Pertice Hall. S. P. Dozzi, S. M. A. (1993). Productivity in construction. In (pp. 54). Wadel, O. P. G. (2011). Environmental impacts of prefabricated school buildings in catalonia. Habitat International, 35, 11. Wild, T. (2018). Best practice in inventory management (3 ed.). New York: Routledge Taylor & Francis Group. Williams, B. C. P. (2009). Construction planning, programming and control (3rd ed.). West Sussex, United Kingdom: Wiley Publisher. Y. J. Gandu, A. A. A., and P.G. Chindo. (2009). Bidding model for sustainable projects using the traditional procurement method. The Information Manager, 9, 8. Yusof, N. W. S. A. M. (2006). The success factors of design and build procrement method: A literature visit. Paper presented at the Proceedings of the 6th Asia-Pacific Structural Engineering and Construction Conference, Kuala Lumpur, Malaysia. Yusof, N. W. S. A. M. (2006). The success factors of design and build procurement method: A literature visit. Paper presented at the In Proceedings of the 6th Asia-Pacific Structural Engineering and Construction Conference.
page 52
APPENDICES
page 53
11.0 Appendix A - FOREMAN DELAY SURVEY (FDS) FORM
54
Appendix B - SAMPLE FOREMAN DELAY SURVEY (FDS) RESULT
55
Appendix C - PROJECT PERFORMANCE INDICATORS
56
Appendix D - PARTNER PERFORMANCE INDICATORS
57
Appendix E - PARTNER PERFORMANCE COMPARISON
58
Appendix F - WEIGHTED AVERAGE SCORE
59
Appendix G - PARTNER REGISTER
62
Appendix H - PARTNER ENGAGEMENT PLAN
63
Appendix I - PARTNER ENGAGEMENT MATRIX
64
page 54
Appendix A FOREMAN DELAY SURVEY (FDS) FORM Person-Hours Lost Problem Causing Area Redoing work (design error or change) Redoing work (prefabrication error) Redoing work (field error or damage) Waiting for materials (warehouse) Waiting for materials (vendor furnished) Waiting for tools Waiting for construction equipment Construction equipment breakdown Waiting for information Waiting for other crews Waiting for fellow crew members Unexplained or unnecessary move Other: Comments:
Made by:
Date:
No. of Hours Lost
No. of Workers
Total PersonHours
page 55
Appendix B SAMPLE FOREMAN DELAY SURVEY (FDS) RESULT Person-Hours Lost
Percentage
Redoing work (design error or change)
122
2.3
Redoing work (prefabrication error)
24
0.5
Redoing work (field error or damage)
52
1.0
Waiting for materials (warehouse)
33
0.6
Waiting for materials (vendor furnished)
22
0.4
Waiting for tools
12
0.2
Waiting for construction equipment
56
1.1
Construction equipment breakdown
15
0.3
Waiting for information
12
0.2
Waiting for other crews
14
0.3
Waiting for fellow crew members
10
0.2
Unexplained or unnecessary move
20
0.4
Other:
70
1.3
Total
462
8.9
Total Work in person-hours
5210
Problem Causing Area
Comments:
Made by:
Date:
page 56
Appendix C PROJECT PERFORMANCE INDICATORS Category Schedule
Parameter SPI - Schedule Performance Index
Quality
Rework %
Performance Indicators
Description the work earned
U
NI
ME
S
E
<2
<1
=1
>1
>2
>0.8%
>0.5%
>=0.3%
<0.3%
<0.2%
>=7
>=6.8
<6.8
<6.3
<5.5
>=16
>=15.3
<15.3
<14.8
<14.3
>=35
>=33.5
<32.5
<31.5
<30
<2
<1
=1
>1
>2
>=2.3%
>=1.7%
<1.7%
<1%
<0.6%
<-5.0%
<0%
=0%
>0%
>5.0%
<-1.5%
<0%
=0%
>0%
>1.5%
the work scheduled total rework cost total scheduled cost
Safety
Cost
LTIFR: Lost Time Injury
total lost time injury per million
Frequency Rate
hours worked
TRIF: Total Recordable
total recordable injury per
Injury Frequency
million hours worked
SIF: Serious Incident
total serious incident per
Frequency
million hours worked
CPI: Cost Performance Index
Productivity FDS: Foreman Delay Survey Variations
CV%: Cost Variance %
the work earned the actual cost spent based on questionnaire in the Appendix A and Appendix B earned work - actual cost earned work
SV%: Scheduled Variance % U : Unsatisfactory NI : Need improvement
earned work - scheduled work scheduled work ME : Meet Expectation S : Satisfactory
E : Excellent
page 57
Appendix D PARTNER PERFORMANCE INDICATORS Category
Parameter
Description
Performance Indicators U
NI
ME
S
Low
Med
High
Trust
transparency
openness to the partnership
Collaboration
No. of disputes
disputes between parties
>5
>2
1-2
0
Communication
% of information received
<70%
<=85%
>85%
>90%
E
>95%
correctly within the time Innovation Quality
Engagement
actively engaged in partnership
Low
Med
High
Shared knowledge
eager to share knowledge
Low
Med
High
Improvement
innovation to improve
Low
Med
High
>0.8%
>0.5%
>=0.3%
<0.3%
<0.2%
>=2.3%
>=1.7%
<1.7%
<1%
<0.6%
<P
=P
>P
<P
=P
>P
Rework % (compare to project)
Productivity Variations
FDS: Foreman Delay
based on questionnaire in the
Survey
Appendix A and Appendix B
CV%: Cost Variance %
(compare to project)
total rework cost total scheduled cost
earned work - actual cost earned work
SV%: Scheduled Variance %
U : Unsatisfactory NI : Need improvement
earned work - scheduled work scheduled work ME : Meet Expectation S : Satisfactory
E : Excellent
page 58
Appendix E PARTNER PERFORMANCE COMPARISON
Category
Performance Indicators (U / NI / ME / S / E)
Parameter Partner 1
Trust
transparency
Collaboration
No. of disputes
Partner 2
Partner 3
Partner 4
Communication Engagement Innovation
Shared knowledge Improvement
Quality
Rework % (compare to project)
Productivity
FDS: Foreman Delay Survey
Variations
CV%: Cost Variance %
(compare to
SV%: Scheduled
project)
Variance % U NI
TOTAL
ME S E
Score Average Score Partner with the most U Partner with the least U Partner with the most E Partner with the least E U : Unsatisfactory NI : Need improvement
ME : Meet Expectation S : Satisfactory
E : Excellent
Partner 5
Partner 6
page 59
Appendix F H - Criteria and Weighted Average Score Appendix 6 Power Avenue, Hawthorn VIC 3122 WEIGHTED AVERAGE SCORE Request for EOI No.
Criteria
Weight Rating
Scoring Method
Score
Assessed By
A. TECHNICAL 1.0 Corporate Capabilities 1.1 Does the contractor's competency
25 4
0-3 3pts = Yes
in engaging design consultants
2pts = Yes, meets tender dates but some detail
provide practicality that assists
missing & needs more information
design feasibility and
1pt = Yes, but lacks detail and logic is
constructability
incomplete/incorrect
0 0
MP Construction
0pts = No, fails to to meet requirements 1.2
Has the contractor provided their
4
3pts = Yes, well demonstrated
experiences in mobilising multi-
2pts = Yes, but lacks certain detail
residential projects while still
1pt = Yes, but more information required to
managing normal project risk, cost
confirm understandings
effectiveness, scope and quality
0pts = No, fails to to meet requirements
0
MP Construction
considerations 1.3
Has the contractor provided
3
3pts = Yes, well demonstrated
documentation or statistical data to
2pts = Yes; considered with minor information to
represent their construction quality
be clarified
and performance
1pt = Yes, but not fully demonstrated and
0
MP Construction
requires for detail 0pts = No, fails to to meet requirements 1.4
Has the contractor provided the
3
3pts = Yes, well demonstrated
evidence of adherence to municipal,
2pts = Yes, but lacks certain detail
state and federal Environmental and
1pt = Yes, but more information required to
Occupational Health and Safety
confirm understandings
policies with all licences of operation
0pts = No, fails to to meet requirements
0
MP Construction
currently valid 1.5
Has the contractor furnished certain
4
3pts = Yes, well demonstrated
financial information demonstrating
2pts = Yes, but lacks certain detail
the Proponent’s (and its financier’s)
1pt = Yes, but more information required to
financial capability, including the
confirm understandings
Tenderer’s proposed funding
0pts = No, fails to to meet requirements
0
MP Construction
approach to the Project. 1.6
Has the contractor provided
3
3pts = Yes, well demonstrated
information showing their
2pts = Yes, but lacks certain detail
understanding of the issues in
1pt = Yes, but more information required to
operating multi-residential projects
confirm understandings
of similar size and character tot the
0pts = No, fails to to meet requirements
0
MP Construction
Project 1.7
Does the contractor demonstrate
4
3pts = Yes
their quality of working relationships
2pts = Yes, meets tender dates but some detail
with all relevant stakeholders as well
missing & needs more information
as accreditation to relevant industry
1pt = Yes, but lacks detail and logic is
bodies
incomplete/incorrect
0
MP Construction
0pts = No, fails to to meet requirements 2.0 Project Delivery Capability 2.1 Does the contractor's proposed
25 5
0-3 3pts = Yes, well demonstrated
program make sense and support
2pts = Yes; considered with minor information to
the given milestones and timeline
be clarified 1pt = Yes, but not fully demonstrated and requires for detail 0pts = No, fails to to meet requirements
0 0
MP Construction
page 60
Appendix F H - Criteria and Weighted Average Score Appendix 6 Power Avenue, Hawthorn VIC 3122
WEIGHTED AVERAGE SCORE (cont.) Request for EOI No.
Criteria
Weight Rating
Scoring Method
Score
Assessed By
A. TECHNICAL 2.2 Does the contractor have sufficient
5
3pts = Yes, well demonstrated
resources which are capable to
2pts = Yes; System appears adequate but need
deliver the project from the
more information
planning stage to the final
1pt = Yes; System demonstrated but actions are
completion stage
not well elaborated
0
MP Construction
0pts = No, fails to to meet requirements 2.3 Has the contractor done due
5
3pts = Yes, well demonstrated
dilligence and disclosed the possible
2pts = Yes; System appears adequate but need
constraints.
more information
0
MP Construction
1pt = Yes; System demonstrated but actions are not well elaborated 0pts = No, fails to to meet requirements 2.3 Are the contractor's preventive and
5
3pts = Yes, well demonstrated
represive actions to deal with their
2pts = Yes; System appears adequate but need
possible constraints feasible and
more information
effective
1pt = Yes; System demonstrated but actions are
0
MP Construction
not well elaborated 0pts = No, fails to to meet requirements 2.4 Does the contractor consider asset
5
3pts = Yes, well demonstrated
management on site, and is the
2pts = Yes; System appears adequate but need
asset management system effective
more information
in increasing on-site productivity
1pt = Yes; System demonstrated but actions are
0
MP Construction
not well elaborated 0pts = No, fails to to meet requirements 3.0 Stakeholders Management 3.1 Does the contractor provide
15 3
0-3 3pts = Yes, well demonstrated
predictions on how the project can
2pts = Yes, but lacks certain detail
impact the stakeholders and vice
1pt = Yes, but more information required to
versa
confirm understandings
0 0
MP Construction
0pts = No, fails to to meet requirements 3.2 Are the contractor's strategies to
3
3pts = Yes
manage stakeholders effective and
2pts = Yes, with minor acceptable conditions
believed can reduce both predicted
1pt = No, but with acceptable alternatives
and unpredicted issues between
0pts = No, fails to to meet requirements
0
MP Construction
stakeholders? 3.3 Does the contractor demonstrate
3
3pts = Yes
their quality of working relationships
2pts = Yes, with minor acceptable conditions
with all subcontractors and
1pt = No, but with acceptable alternatives
upstream suppliers
0pts = No, fails to to meet requirements
3.4 Does the constractor show its
4
3pts = Yes
credibility not to compromise
2pts = Yes, with minor acceptable conditions
sustainability and quality, while keep
1pt = No, but with acceptable alternatives
maintaining good relationship with
0pts = No, fails to to meet requirements
0
MP Construction
0
MP Construction
all stakeholders 3.5 Has the contractor demonstrated
2
3pts = Yes
resource management procedures
2pts = Yes, with minor acceptable conditions
and experiences from past and
1pt = No, but with acceptable alternatives
current projects which satisfy
0pts = No, fails to to meet requirements
industry standards
0
MP Construction
page 61
Appendix F H - Criteria and Weighted Average Score Appendix 6 Power Avenue, Hawthorn VIC 3122
WEIGHTED AVERAGE SCORE (cont.) Request for EOI No.
Criteria
Weight Rating
Scoring Method
Score
Assessed By
A. TECHNICAL 4.0 Risk Management 4.1 Does the contractor provide
20 6
0-3
0 0
3pts = Yes
predictions on on-site and off-site
2pts = Yes, with minor acceptable conditions
risks that potentially impact on the
1pt = No, but with acceptable alternatives
project delivery
0pts = No, fails to to meet requirements
4.2 Does the contractor propose clear
7
3pts = Yes
0
strategies to eliminate or mitigate
2pts = Yes, meets tender dates but some detail
the risks
missing & needs more information
MP Construction
MP Construction
1pt = Yes, but lacks detail and logic is incomplete/incorrect 0pts = No, fails to to meet requirements 4.3 Does the contractor show capability
7
3pts = Yes
0
to do its strategies. This also
2pts = Yes, meets tender dates but some detail
considers financial capability,
missing & needs more information
resource capability (labour,
1pt = Yes, but lacks detail and logic is
equipment, materials)
incomplete/incorrect
MP Construction
0pts = No, fails to to meet requirements B. COMMERCIAL 5.0 Commercialisation 5.1 Does the contractor provide a
10 3
0-3
0 0
3pts = Yes
convincing justification on how their
2pts = Yes, meets tender dates but some detail
objectives increase the project's
missing & needs more information
profitability
1pt = Yes, but lacks detail and logic is
MP Construction
incomplete/incorrect 0pts = No, fails to to meet requirements 5.2 Does the contractor provide
3
3pts = Yes
0
strategies to maximise project profit
2pts = Yes, meets tender dates but some detail
margin and ROI
missing & needs more information
MP Construction
1pt = Yes, but lacks detail and logic is incomplete/incorrect 0pts = No, fails to to meet requirements 5.3 Are the contractor's management
4
3pts = Yes
0
strategies effective and can provide
2pts = Yes, meets tender dates but some detail
reliable predictions on how the
missing & needs more information
project can impact the stakeholders
1pt = Yes, but lacks detail and logic is
and vice versa
incomplete/incorrect 0pts = No, fails to to meet requirements
Total Weighted Rating Score =
95
Total Contractor's Score = Maximum Score =
MP Construction
0 285
Appendix G PARTNER REGISTER Project Manager
Partner
P
Contact
Category (Internal / External)
Interest
page 63
Project Phase
Influence
Communication Requirements
Expectations
Low
Medium
High
Appendix H PARTNER ENGAGEMENT PLAN Partner organisation, group or individual
Potential role in the activity
Engagemen engage the
nt strategy: How will you e partner in the activity
page 65
Follow-up strategy plans for feedback or continuous improvement
Appendix I PARTNER ENGAGEMENT MATRIX
Partner
Low
Risk
Medium
Influence (Project Level)
High
Interest (Project Level)
(
Initiatio
page 67
Project Phases (Informed / Consulted / Responsible / Accountable)
on
Planning
Execution
Low
Control
Medium
Close
Engagement Level
High