Assignment 1, Construction Analysis - ABPL20033

Page 1

ABPL20033 CONSTRUCTION ANALYSIS SEMESTER 2, 2017 Case Study : JCB HAMPTON HOUSE Section : 4b Nesia Cahyono 813807


ABPL20033 CONSTRUCTION ANALYSIS SEMESTER 2, 2017 PROJECT TITLE: 1255 DOUBLE STUDS AT THE CORNER

OVERLAPPING CLADDING MATERIALS TO PREVENT WATER LEAKS IN

600

ASSIGNMENT 1

POOL PAINTED 50x50 TREATED PINE BATTEN

RTW CONCRETE BLOCKWORK WITH CEMENT RENDER

POOL SEAT

DOUBLE STUD NEXT TO AN OPENING A S01

BULK INSULATION

12. FINAL PAINTING POLISHING FLOOR AND LANDSCAPE

DRAWING TITLE:

BUILDING PAPER OUTSIDE PWB ADJUSTED STUD TO CONNECT 2 WALLS

PWB W G-12

FLASHING AT THE INTERSECTION

BULK INSULATION

GROUND FILL

PLAN

DS

N

RFSO1

9. ROUGH IN AND INSULATION

PB WB BUILDING PAPER OUTSIDE WB

INTERNAL NON-LOADBEARING WALL

BED 1 FF01

2. GROUND FLOOR WALL FRAME

SCALE:

NOT A FULL LENGTH STUD C3 NOT A FULL LENGTH STUD

FFL 20.600

SCALE 1:50 @A3 W G-13

A S01

10. LININGS

1255

DATE:

8. WINDOWS AND DOORS 900

D G-04

1 AUGUST 2017

7. RAIN SCREEN

PB STUDS ARE NOT FULL LENGTH

DS1

DRAWN BY:

D G-05

INTERNAL LOAD BEARING WALL 3688

90

NESIA CAHYONO 813807

140

LEGEND

01

GROUND FLOOR PLAN SCALE 1:50 TIMBER WALL FRAMING SCHEDULE (EXCEPT FOR STUDS SPECIFIED ON PLAN) EXTERNAL STUD WALLS & INTERNAL LOAD BEARING STUD WALLS: HEIGHT = 0-3.2m 45 x 90 MGP10 TOP & BOTTOM PLATES 90 x 45 MGP10 STUDS @ 450 MAX. CTS. PROVIDE NOGGINGS @ 1350 MAX. CTS. INTERNAL LOAD BEARING STUD WALLS: HEIGHT = 0-3.2m 35 x 90 MGP10 TOP & BOTTOM PLATES 90 x 35 MGP10 STUDS @ 600 MAX. CTS. PROVIDE NOGGINGS @ MIDHEIGHT

RFSO1 DS DS1 C3 PB R1 RTW RB12 EF01 WB PWB FF01

METAL DECK ROOFING 2/90 x 45 MGP10 2/90 x 45 F17 KDHW 89 x 89 x 6.0 SHS PLASTERBOARD 190 x 45 MGP10 RAFTERS @450 CTS BLOCKWORK RETAINING WALL 2/190 x 45 MGP10 TIMBER CLADDING PAIR OF DIAGONAL STEEL STRAP PANEL OF STRUCTURAL PLYWOOD SELECTED TIMBER FLOOR


ABPL20033 R1 INTERSECTS WITH RB12 AND R1 FROM ANOTHER DIRECTION

RB12

PAINTED 40x40 TREATED PINE BATTEN EF01

FLASHING OVERLAPS WITH 2 CORRUGATED METAL TO ENSURE WATER DOES NOT LEAK

R1

RFSO1

ASSIGNMENT 1 9. ROUGH IN AND INSULATION

BED 4

DRAWING TITLE: WALL INTERSECTION BED (SHOWN IN CERTAIN ANGLE)

FLASHING OVERLAPS WITH BOX GUTTER TRIP-L-GRIP

DOWNPIPE

IRON STRAP WITH NAILS

RFSO1

4. FIRST FLOOR WALL FRAME

PB

40x40 BATTEN FOR CEILING

BOX GUTTER

FIRST FLOOR LEVEL FFL 23.650

PROJECT TITLE:

5. ROOF FRAMING

SARKING AND INSULATION TO BE INSTALLED WITHIN ALL ROOF CAVITIES

6. GUTTER AND FLASHING

CONSTRUCTION ANALYSIS SEMESTER 2, 2017

SECTION

FINISHED TIMBER FLOOR CHIPBOARD

45x90 MGP10 TOP & BOTTOM PLATES

3. FIRST FLOOR FRAME

10. LININGS FIRST FLOOR LEVEL FFL 23.650

FLOOR JOIST (SHOWN IN CERTAIN ANGLE)

BUILDING PAPER OUTSIDE WB

SCALE: FCL 23.255

FCL 23.255

FL1 WB

W G-13

PB BULK INSULATION

PAINTED 50x50 TREATED PINE BATTEN

2. GROUND FLOOR WALL FRAME

40x40 BATTEN FOR CEILING

WINDOW (SHOWN IN CERTAIN ANGLE)

NOGGINGS @ 1350 MAX. CTS BEHIND THE WINDOW

EF01 FLASHING TO BE PUT ON TOP OF WINDOW W G-12

7. RAIN SCREEN FLASHING BELOW WINDOW SILL

HARDWOOD WINDOW SILL

BED 1

RTW DOWNPIPE TO BE INSTALLED BETWEEN CEMENT RENDER CORRUGATED METAL AND TIMBER RAIN SCREEN

GROUND FILL GROUND FLOOR LEVEL FFL 20.600

POOL TILES

TOP OF POOL POOL SEAT

BED (SHOWN IN CERTAIN ANGLE)

FINISHED TIMBER FLOOR

P50 MDF SKIRTING

FOAM TO COVER PVC PIPE FROM CRACKING

CONTROLLED FILL AS REQUIRED (a) 800 MAX. SAND IN 300 LAYERS (b) 400 MAX. NON-SAND IN 150 LAYERS OR ROLLED FILL (a) 600 MAX. SAND IN 300 LAYERS (b) 300 MAX. NON-SAND IN 150 LAYERS

SECTION SCALE 1:50

8. WINDOWS AND DOORS

DATE:

1 AUGUST 2017

GROUND FLOOR LEVEL FFL 20.600

DRAWN BY: 35x70 MM FLOOR BATTENS N25 CONCRETE SLAB 0.2 mm VAPOUR BARRIER

A

11. PAINITNG, JOINERY AND FITTING

PACKER

50 SAND BED

POOL STRUCTURE BY INDEPENDENT CONTRACTOR

WALL INTERSECTION

SCALE 1:50 @A3

450 DIAMETER RC BORED PIPE SPECIFIED IN STRUCTURAL DRAWINGS

12. FINAL PAINTING POLISHING FLOOR AND LANDSCAPE

1. GROUND PREPARATION, PIPES AND CONCRETE SLAB

NESIA CAHYONO 813807 LEGEND RFSO1 L1 EF01 RTW PB R1 RB12 WB

METAL DECK ROOFING LINTEL - 90 x 45 MGP10 TIMBER CLADDING BLOCKWORK RETAINING WALL PLASTERBOARD 190 x 45 MGP10 RAFTERS @450 CTS 2/190 x 45 MGP10 PAIR OF DIAGONAL STEEL STRAP

THE STUDS ARE 90 x 45 MGP10 @ 450 MAX CTS


1 3 5 7 9 11

GROUND PREPARATION, PIPES AND CONCRETE SLAB - Prior to the construction process, existing site has to be clear (no buildings and vegetations) as excavation needs to be commenced. - Excavation should be matched with the footings specification in soil test report. In this instance, deep excavation is required because deep footings are used (concrete edge beam with pile). All topsoil containing grass roots and organic matter has to be removed. - Plumber, electrician, gas fitter come on site to do the installations. - After all are finished, the site should be covered with compacted filling for leveling purposes. Specifications refer to soil test report and AS 2870-1996 clause 6.4.2. - It can be seen that some areas have lower levels which are exactly where series of wall will be erected. - Formwork is made on site; blinding layer of 15MPa concrete, 50 mm thick minimum is to be provided if required; 0.2 mm polyethylene sheeting as the waterproof membrane is laid; min. of 25MPa concrete as the footing is poured FIRST FLOOR FRAME - Timber floor joist is erected as the structural component of the first floor. In connection to timber frame, the joist is connected at its bottom flange to top of the top plate using trip-l-grip, yet in the case where steel component is combined, floor joist is installed at the top (see figure beside). Joist should not touch any top plates of internal non load bearing wall. - Some parts which use steel are specified in detail in structural drawings. - Chipboard is nailed on top of joist to brace the joists and facilitate the builder to walk on it. The direction should be perpendicular to the joist to optimize the strength. Each sheet of chipboard should start and end exactly at the joist

ROOF FRAMING - Two materials for rafter: timber and steel. In the particular section of 4b, 190x45 MGP10 rafter is erected on top plate @ 450 cts by trip-l-grip. The rafter has little notch at the lower end to accommodate box gutter - Between rafters are bulk insulation. Below and above the rafters are battens run in perpendicular direction to the rafter for ceiling lining and rain screen respectively.

RAIN SCREEN - Metal cladding as the rain screen is fixed to the battens. Fixed to metal cladding is another layer of battens for the timber cladding. Space between these battens are used for downpipes which run from the gutter to the ground - Connection between rain screen required flashings and has to be overlapping.

ROUGH IN AND INSULATION - Trade people come on site to install services. Some studs are intentionally holed to accommodate cables and pipes. Sometimes fixtures are added for rough in purpose. Clear joist web is used for services as well. - Bulk insulation between studs, ceiling and roof is installed to perform as an acoustic insulation and thermal insulation. Bulk insulation cannot be very tight, otherwise air gap which prevents heat transfer is lost. Fiber glass material is used prevalently as the bulk insulation

PAINTING, JOINERY AND FITTING - Plasterboard is painted in white - Joinery as specified by the architect are installed, as well as fittings such as power points and tabs

2 4 6 8 10 12

GROUND FLOOR WALL FRAME - Steel portal frame is installed by anchoring it to the slab. Lateral stability is supported by temporary framing. - 45x90 MGP10 and 45x90 F17 KDHW are used in this site as the standard studs for timber framing (bottom plate, stud, top plate, noggings), additionally SHS and RHS grade 350 as well as CHS grade 250 and 350 are used where required. Noggings are not installed in line to give way to the nails. - Double studs are used next to an opening and lintel is used above the opening. In this case, most lintels are installed below the top plate to allow height changes for windows - Permanent bracing for the framing is either steel cross bracing or plywood bracing. 30-60 degree is the optimal angle for steel cross bracing, otherwise plywood bracing should be used

FIRST FLOOR WALL FRAME - Similar components to the second stage - Bottom plate is nailed to the top plate and connected to the components below with metal straps. - Top plate is nailed to the studs and tightened with metal strap to prevent suction.

GUTTER AND FLASHINGS - Gutter is bended on site from an aluminium sheet. Flashings are required at each connection with other components. In this house box gutter is concealed by timber cladding from the facade - Next to windows and doors opening are double studs, and above the opening is lintel as specified. - Flashing and overlapping materials are required at every opening and every section that might caused unexpected opening. Sealant is used to seal gap between materials. - Sarking on the roof is installed above the battens, and pops out just below the flashing (overlapping materials). Building paper on the wall is to be placed between bracing and battens for metal cladding, and should also pop out below the flashings. Lapping between sarkings should not less than 200mm. WINDOWS AND DOORS - Window and door are specified in window and door schedules. In my section (4b), the windows are G-12 and G-13, while the doors are G-04.

LININGS - 10 mm plasterboard is used as the internal linings. It is attached to the studs by nails. Perforated metal bead is used to generate smooth connection between plasterboards - Below the plasterboard is MDF skirting. - Polished timber finishing are used as the internal floor linings

FINAL PAINTING POLISHING FLOOR AND LANDSCAPE - Finalisation and defect checking are conducted. Final painting and floor polishing are required to minimize defects. - Little detail for landscape might be added to enhance the appearance prior to the completion


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.