Work Sample of Chunyi Ho

Page 1

Neihu Biomass Power Plant & Environmental Education center NTUST-Arch Thesis

Instructor / Chinwei Lee Year / 2018-2019 Area / 258,000 SF Location / Taipei, Taiwan Software / Revit, Photoshop, Illustrator A product’s life cycle has alway been linear, quick born and straight to the long dying porcess. What if we can make it into a sustainable cycle by connecting two ends, turn the kitchen waste into mycelium brick for architecture, biofuel for garbage truck, heat for green houses, and clean water for firefly restoration. We add some different programs into this new waste to energy plant, such as science institute, NGOs, product design firms, start-up incubator... and also a restaurant supported by the food grown by the machine in the greenhouse. We design two interlocking dounut-like masses, running in and out the original building. And use colors to differentiate the target user of each space.


REVISIO

Chunyi Ho chunyiho@cpp.edu 012852359

West Hollywood Apartment Cal Poly Pomona 3rd Grade

Instructor / Barry Milosfky Year / 2017 Area / 13,000 SF Location / W Hollywood, CA Software / Revit, Photoshop

REVISIONS

WEST HOLLYWOOD HOUSING PETER HO

West Hollywood is a city known for the big amount of population of the LGBT community.

SHEET LIST

REVISIONS

W10

7' - 2"

2' - 6"

8' - 6"

5' - 0"

8' - 6"

2' - 0"

6' - 10"

8 A5.01

AREA OF STACK 5' - 9"

6' - 0"

Roof 40' - 0"

6' - 0"

6' - 0"

6' - 0"

W12 W12X

FLOOR PLAN_4F 30' - 0"

6' - 0"

2' - 11"

Roof 40' - 0"

FLOOR PLAN_3F 20' - 0"

FLOOR PLAN_4F 30' - 0"

D3

W6

W8

8'

16'

32'

West 1/8" = 1'-0"

4

2' - 0"

FLOOR PLAN_1F 0' - 0"

ARC303 WEST HOLLYWOOD HOUSING

North 1/8" = 1'-0"

ELEVATIONS

2018/05/30

2018/05/30

Peter Ho Barry Milofsky

Peter Ho Barry Milofsky

A1.22

1/8" = 1'-0"

30 May 2018 3:00:03 AM

4'

3

0'

4'

Chunyi Ho

GARY L MCGAVIN G0.00 TITLE SHEET 3801 W TEMPLE AVE, POMONA, CA 91768 G0.01 GENERAL NOTES GMCGAVIN@CPP.EDU G1.01 FIRE RESISTING RATING G1.02 FIRE RESISTING RATING MECHANICAL ENGINEER G1.03 FIRE RESISTING RATING HOFU WU A1.01 SITE PLAN 3801 W TEMPLE AVE, POMONA, CA 91768 A1.02 LANDSCAPE PLAN HWU@CPP.EDU A1.11 FOUNDATION PLAN A1.21 PARKING LEVEL PLAN CODE ANALYST A1.22 FIRST FLOOR PLAN ANDREW J. THUL A1.23 SECOND FLOOR PLAN 5' - 0"

2' - 6"

4' - 2"

43' - 10"

2' - 0"

12' - 3"

4' - 6"

SIDEWALK

PARKWAY G S W E

G

S

W

E

G

S

W

E

100' - 0"

DEMOLISH EXISTING SINGLE FAMILY HOUSE

G

G

PLYWOOD WHITE FIBER CEMENT PANEL

ALUMINUM WINDOW FRAME

SLEEPER 2 X 6 SILL PLATE

S

S

W

W

E

E

11

S

W

OUTDOOR WOOD DECK 1 1/2" = 1'-0"

10

WINDOWS DETAIL 1 1/2" = 1'-0"

GYPSUM BOARD

2 X 10 RIM JOIST

WHITE FIBER CEMENT PANEL

WHITE FIBER CEMENT PANEL

WOOD SIDING

0' - 2"

SLIDING WALL PANEL

0' - 2"

FLASHING WOOD SIDINGS

WHITE FIBER CEMENT PANEL

WHITE FIBER CEMENT PANEL PLYWOOD

8

E

FIBER CEMENT PANEL @ CANTILEVER 3" = 1'-0"

7

BALCONY OPENING_BOTTOM 3" = 1'-0"

6

BALCONY OPENING_TOP 3" = 1'-0"

5

3' - 0"

W

CAP SHEET

ARC303 WEST HOLLYWOOD HOUSING

LANDSCAPE PLAN

SITE PLAN

Peter Ho Barry Milofsky

A1.02

1/8" = 1'-0"

0'

4'

8'

16'

32'

SELF HEALING WATER PROOF SHEATING

COPING

BACE SHEET

SHAPED WOOD CAP NAILER RIGID INSULATION

ARC303 WEST HOLLYWOOD HOUSING

2018/05/30

WOOD NAILER

TOP PLATE

Z FLASH

VAPOR BARRIER PROTECTION BOARD

WHITE FIBER CEMENT PANEL

FLASHING

PLYWOOD DIAPHRAGM

2018/05/30 Peter Ho Barry Milofsky

A1.01 1/8" = 1'-0"

GRAVEL

4

CEMENT PANEL @ WOOD SIDING TOP 6" = 1'-0"

3

CANT STRIP & ROOFING 3" = 1'-0"

2

PARAPET DETAIL 3" = 1'-0"

1

FOUNDATION DETAIL 3" = 1'-0"

40'

30'

FIRE RATING WALL_FIRST FLOOR 1/8" = 1'-0"

DETAILS

2

ARC303 WEST HOLLYWOOD HOUSING

OUTDOOR AREAS (SECTION 1004.5:) YARDS, PATIOS, COURTS, AND SIMILAR OUTDOOR AREAS ACCESSIBLE TO AND USABLE BY THE BUILDING OCCUPANTS SHALL BE PROVIDED WITH MEANS OF EGRESS AS REQUIRED BY THIS CHAPTER EXCEPT:

WALL SECTION

1. OUTDOOR AREAS USED EXCLUSIVELY FOR SERVICE OF THE BUILDING NEED ONLY HAVE ONE MEANS OF EGRESS. 2. BOTH OUTDOOR AREAS ASSOCIATED WITH GROUP R-3 AND INDIVIDUAL DWELLING UNITS GROUP R-2.

2018/05/30 Peter Ho Barry Milofsky

A3.11 1/2" = 1'-0"

STAIRWAYS (SECTION 105.1:) FOR OTHER THAN GROUP H AND I-2 OCCUPANCIES, THE CAPACITY, IN INCHES, MEANS OF EGRESS AND STAIRWAYS SHALL BE CALCULATED BY MULTIPLYING THE OCCUPANT LOAD SERVED BY SUCH STAIRWAYS BY A MEANS OF EGRESS CAPACITY FACTOR OF 0.2" PER OCCUPANTIN A BUILDING EQUIPPED WITH AN AUTOMATIC SPRINKLER SYSTEM INSTALLED IN ACCORDANCE WITH SECTION 903.3.1.2 AND EMERGENCY VOICE/ALARM COMMUNICATION SYSTEM IN ACCORANCE WITH SECTION 907.5.2.2.

STUDIO UNIT: 493 SF / 200 GROSS = 2.465 TOTAL OF 1 PERSON 1 * 0.2 = 0.2 1 BEDROOM UNIT: 830 SF / 200 GROSS = 4.15 TOTAL OF 1 PEOPLE 1 * 0.2 = 0.2

REVISIONS

-

FO 0" RT H

Studio

30'

FL OO R

- 0"

FO RT

H

FL OO R

1 Bed

ø 5'

1

T

- 0"

20

TH

'-

IR

0"

D

20'

FL OO R

TH

10'

ND

FL

OO

R

10'

- 0"

OO

= 49 PEOPLE = 16 PEOPLE = 17 PEOPLE = 10 PEOPLE = 10 PEOPLE

EXTERIOR BEARING WALL -1 HR. FIRE RATING INTERIOR BEARING WALL -1 HR. FIRE RATING

EGRESS STAIR ENCLOSURE -2HR FIRE RATING SEPARATION PARTITION -1 HR. FIRE RATING

PATH OF TRAVEL

S-2 ABOVE R-2 -3 HR. FIRE RATING

PATH OF TRAVEL LEGEND 12" = 1'-0"

FIRE WALL / EGRESS LEGEND

R

- 0"

R

FL OO R

HOLD DOWN POST BASE

0'

TIE DOWN

- 0"

FIRS

T

- 0"

NUMBER OF EXITS REQUIRED: 51 OCCUPANTS = 2 EXITS

2 BEDROOM UNIT: 1054 SF / 200 GROSS = 5.27 TOTAL OF 2 PEOPLE 2 * 0.2 = 0.4

FL OO

SE CO ND

FL OO R

5 C

C

6

FSA STRAP

B

3 B

6

FIRE RATING WALL_SECOND FLOOR 1/8" = 1'-0"

NUMBER OF OCCUMPANTS: SF OF PARKING LEVEL / OCCUPANT LOAD FACTOR = 9703 SF / 200 SF / PER OCCUPANT SF OF FIRST FLOOR / OCCUPANT LOAD FACTOR = 3172 SF / 200 SF / PER OCCUPANT SF OF SECOND FLOOR / OCCUPANT LOAD FACTOR = 3389 SF / 200 SF / PER OCCUPANT SF OF THIRD FLOOR / OCCUPANT LOAD FACTOR = 1826 SF / 200 SF / PER OCCUPANT SF OF FORTH FLOOR / OCCUPANT LOAD FACTOR = 1826 SF / 200 SF / PER OCCUPANT

D

- 0"

SE CO

0'

FIRS T FL

- 0"

IR

2 Bed

A

5

A

ARC303 WEST HOLLYWOOD HOUSING

1

FIRE RESISTING RATING

S3_FRAME 3D_VIEW NE

2

1/4"=1'-0"

ARC303 WEST HOLLYWOOD HOUSING

S3_FRAME 3D_VIEW SW

STACK STRUCTURE FRAMING

1/4"=1'-0"

2018/05/30

2018/05/30 Peter Ho Barry Milofsky

G1.02 As indicated

Peter Ho Barry Milofsky 0'

2'

4'

8'

S1.01 1/4" = 1'-0"

8" COPING WATER PROOFING RIDGID INSULATION CANT STRIP

Chunyi Ho

ROOF R-VALUE THROUGH JOIST(10%) OUTSIDE AIR FILM 0.17 WATERPROOF MEMBRANE 0.06 3" TAPERED RIGID INSULATION 11 3/4" PLYWOOD 0.93 2X10 I JOIST@16"O.C. 10 INSIDE AIR FILM 0.61 TOTAL R-VALUE 22.77

chunyiho@cpp.edu 012852359

REVISIONS

THROUGH INSULATION(90%) OUTSIDE AIR FILM WATERPROOF MEMBRANE 3" TAPERED RIGID INSULATION 3/4" PLYWOOD 9.25" HIGH DENSITY FIBER BATT INSULATION INSIDE AIR FILM TOTAL R-VALUE TOTAL U-VALUE 1/(22.77X10%+42.77X90%)=

0.17 0.06 11 0.93 30

0.61 42.77 0.022

FLOOR R-VALUE 3/4" LIGHT WEIGHT CONCRETE 0.08 3/4" PLYWOOD 0.93 INSIDE AIR FILM 0.68 OUTSIDE AIR FILM 0.17 TOTAL R-VALUE 1.86 TOTAL U-VALUE 1/1.86 =

ANCHOR BOLT

10% DRIVING SLOPE

EARTH TJI HANGER WOOD SIDING

-

PA 6" RA PE RO OF

Studio

2 X 6 PT BOOTTOM PLATE

CANT STRIP

WHITE FIBER CEMENT PANEL

REVISIONS

Studio

FIBER CEMENT PANEL @ WOOD SIDING BOTTOM 6" = 1'-0"

BLACK FIBER CEMENT PANAL

E

6' - 0"

S

30 May 2018 3:00:01 AM

LANDSCAPE PLAN 1/8" = 1'-0"

2' - 6"2' - 9"

30 May 2018 3:00:01 AM

1

G

7' - 0"

43'

IT

1 Bed

BATT INSULATION

GYPSUM BOARD

GYPSUM BOARD

FLASHING

IP

40 '-

RO 0" OF

- 0"

- 0"

21' - 0"

chunyiho@cpp.edu 012852359

6"

RR

1 Bed

PLYWOOD

WOOD SIDING

WOOD SIDING CAP FLASHING

PLYWOOD

DEMOLISHED DRIVEWAY

2' - 6"

32' - 5"

8'

ø 5'

- 0"

1 Bed

HANGER & TRACK @ SLIDING DOOR 9 3" = 1'-0"

7' - 0"

18' - 0" 7' - 4"

TREE

4'

ø 5'

ø 5'

TRACK

7' - 6"

10' - 2"

GYPSUM BOARD

WOODECKING

CONCRETE SLAB

NEW SIDEWALK & LANDSCAPE

G

WOODDECKING

2'

NAILS

SPAULDING AVE

5' - 0"

SPAULDING AVE

14' - 2"

14' - 4"

7' - 3"

ALUMINUM PROFILE CONNECTOR

PEDESTAL SYSTEM ADJUSTABLE FEET

- 0"

12' - 0"

3'

6' - 7"

10' - 1"

2' - 6"

15' - 5"

1 X 1 TILE

1'

4 X 10 HEADER

REVISIONS

9' - 1"

17' - 8" 6' - 9"

8' - 0"

6' - 3" 19' - 10"

28' - 7" 13' - 0"

13' - 6"

3' - 6"

0'

0' - 2"

11' - 0"

B-B' 1/2" = 1'-0"

15' - 0"

WHEEL

17' - 6"

8' - 9"

13' - 6"

PLANTER

2

chunyiho@cpp.edu 012852359

21' - 0"

G S W E

1' - 10"

A2.01

A-A' 1/2" = 1'-0"

Chunyi Ho

GRASS

2' - 2"

32'

1

Sheet Name

15' - 0"

REVISIONS

13' - 10"

16'

130' - 0"

chunyiho@cpp.edu 012852359

13' - 7"

8'

1/8" = 1'-0"

Sheet Number STRUCTURAL ENGINEER 13' - 3"

FLOOR PLAN_2F 10' - 0"

1' - 0"

FLOOR PLAN_1F 0' - 0"

0'

7' - 7"

FLOOR PLAN_3F 20' - 0"

W1

W9

MICHAEL FOX 3801 W. TEMPLE AVE. POMONA, CA 91768 MICHAELFOX@CPP.EDU FIRST FLOOR PLAN

2 A4.31

30 May 2018 3:00:09 AM

SHEET LIST 3' - 6"

5' - 10"

W4

4' - 0"

7' - 5"

6' - 0"

7' - 11"

4' - 0"

7' - 5"

6' - 0"

7' - 5"

W1

FLOOR PLAN_1F 1/8" = 1'-0"

8

WOOD SIDING

3/4" ACOUSTIC CHANNEL

3' - 3"

7' - 5"

W5

ARC303 WEST HOLLYWOOD HOUSING

OUTDOOR DECK

2X10 TJI @ 16" O.C.

9 A5.01

2x12 TJI @ 16" O.C.

FLOOR PLAN_2F 10' - 0"

8' - 9"

3/4" PLYWOOD

South 1/8" = 1'-0"

2' - 2"

5' - 0" 8' - 5" 4' - 6"

3' - 6" 0" ø 5' -

12' - 3"

7' - 5"

CONSTRUCTION MANAGER

13' - 5"

10' - 9"

1/4" ACOUSTIC MATT

-

D3

1

2

2X12 RIM JOIST

1 1/2" LIGHT WEIGHT CONCRETE

FLOOR PLAN_1F 0' - 0"

REVISIONS

TJI HANGER 43 '-

PE

0" ø 5' -

123 STUDIO UNIT 480.75 SF

7 A5.01

FLOOR PLAN_2F 10' - 0"

D1

---

12' - 10"

20' - 3"

W3

ANTS

East 1/8" = 1'-0"

6' - 1"

W3

D1

W15

3' - 0"

4' - 0" 7' - 9"

8' - 2" 4' - 6"

122 STUDIO UNIT 471.22 SF

D3

FLOOR PLAN_1F 0' - 0"

4' - 6"

21' - 2"

0" ø 5' -

74' - 11"

5' - 11"

FLOOR PLAN_2F 10' - 0"

DOUBLE INSULATING GLASS

Chunyi Ho

chunyiho@cpp.edu 012852359

- 0"

8' - 9" 30' - 0"

W4

REVISIONS

1 M1.01

HURRICANE STRONG TIE

Chunyi Ho

ø 5'

9' - 10"

W2

1/2" GYPSUM BOARD

chunyiho@cpp.edu 012852359

0" ø 5' -

17' - 2"

D1

2X6 STUDS @ 16" O.C. 1 A4.31

Chunyi Ho

- 0"

D3

W2

13' - 4" 25' - 0"

D1

W14

W7

1

- 0"

W2 D1

W6

D1 D1

ø 5'

121 1 BED UNIT 723.64 SF

W14

111 GYM 272.29 SF

112 1 BED UNIT 747.68SF

W2

W1

FLOOR PLAN_3F 20' - 0"

6 A5.01

3/4" PLYWOOD

ø 5'

15' - 9"

- 0"

W3

W2

BARRY MILOFSKY 3801 W TEMPLE AVE, POMONA, CA 91768 BARRY@M2A-ARCHITECTS.COM

W6

12' - 0"

ø 5'

W8

14' - 10"

W1

W13

W9

4' - 6"

5' - 6"

W1

FLOOR PLAN_3F 20' - 0"

3' - 7"

AREA OF STACK

24' - 7"

SLIDING WALL PANEL

DOUBLE TOP PLATE

6' - 8"

12' - 7"

2' - 0"

5' - 5"

CANT STRIP

4X12 RIM JOIST

chunyiho@cpp.edu 012852359

7' - 0"

10' - 9"

WATER PROOFING RIDGID INSULATION B310 BEAM HANGER

Chunyi Ho

0.54

WALL R-VALUE THROUGH STUDS(10%) OUTSIDE AIR FILM 0.17 FIBER CEMENT PANEL 1.23 3/4" AIR SPACE 1 WATERPROOF MEMBRANE 0.06 3/4" PLYWOOD 0.93 2X6 I STUDS@16"O.C. 5.5 INSIDE AIR FILM 0.68 TOTAL R-VALUE 9.57 THROUGH INSULATION(90%) OUTSIDE AIR FILM FIBER CEMENT PANEL 3/4" AIR SPACE WATERPROOF MEMBRANE 3/4" PLYWOOD 5 1/4" HIGH DENSITY FIBER BATT INSULATION INSIDE AIR FILM TOTAL R-VALUE TOTAL U-VALUE 1/(9.57X10%+25.07X90%)=

Chunyi Ho

Chunyi Ho

REVISIONS

REVISIONS

chunyiho@cpp.edu 012852359

chunyiho@cpp.edu 012852359

FIBER CEMENT PANEL 3/4" AIR SPACE

B310 BEAM HANGER 4X12 RIM JOIST

DOUBLE TOP PLATE

0.17 1.23 1 0.06 0.93 21

2

3/4" PLYWOOD

1/2" GYPSUM BOARD

6"

DETAILS 2018/05/30 Peter Ho Barry Milofsky

A5.01 As indicated

6"

1 1/2" 1 1/2" 1 1/2" 1 1/2"

INFILTRATION 8540/60=

4" 4" 1 1/2" 1 1/2"

1 1/2" 1 1/2"

1 1/2"

3"

2

4"

0.28

1

4"

SEWER & VENT_3D NO SCALE

4"

1 1/2"

6"

R-VALUE 142.3

R-VALUE ESTIMATION 1 1/2" = 1'-0"

2

4"

0.043

1

3"

4"

GLASS R-VALUE Soft Coat Low-E insulated Glass 3.50 TOTAL U-VALUE 1/3.50=

6"

1 1/2"

0.68 25.07

1 1/2" 1 1/2" 1 1/2"

3"

1 1/2" 2

4"

VENT STACK SEWER

1 1/2" LIGHT WEIGHT CONCRETE 1/4" ACOUSTIC MATT 3/4" PLYWOOD 2X10 I JOIST @ 16" O.C.

ARC303 WEST HOLLYWOOD HOUSING

SEWER & VENT_PLAN 1/4" = 1'-0"

2X6 STUDS @ 16" O.C.

DOUBLE INSULATING GLASS

8" 1 1/2"

CLEANOUT

R-VALUE ESTIMATION 2018/05/30 Peter Ho Barry Milofsky

M1.01 1 1/2" = 1'-0"

1 1/2"

1 1/2"

SEWER PIPE SIZE BASEMENT10” PIPE FIRST FLOOR 8” PIPE SECOND FLOOR 6” PIPE THIRD FLOOR 4” PIPE

ARC303 WEST HOLLYWOOD HOUSING

EXHAUST VENT 1- 1/2” FROM FIXTURE MAIN 4" UP TO ROOF 6"

ARC303 WEST HOLLYWOOD HOUSING

SEWER & VENT

10"

2018/05/30 UNIT SEWER & VENT DIAGRAM 4 12" = 1'-0"

10"

sanitary sewer

3

SEWER & VENT_SECTION 1/4" = 1'-0"

Peter Ho Barry Milofsky

P1.02 12" = 1'-0"

30 May 2018 3:06:00 AM

W11

FLOOR PLAN_4F 30' - 0"

5' - 0"

3' - 6"

15' - 9"

W11

Roof 40' - 0"

W4

30 May 2018 3:05:54 AM

48' - 2"

6' - 10"

76' - 10"

W12X W12

8' - 0"

Roof 40' - 0"

FLOOR PLAN_4F 30' - 0"

TITLE SHEET GENERAL NOTES FIRE RESISTING RATING FIRE RESISTING RATING FIRE RESISTING RATING SITE PLAN LANDSCAPE PLAN FOUNDATION PLAN PARKING LEVEL PLAN FIRST FLOOR PLAN SECOND FLOOR PLAN THIRD FLOOR PLAN FORTH FLOOR & ROOF PLAN ELEVATIONS SECTION SECTION WALL SECTION UNIT PLAN INTERIOR ELEVATION ENLARGED WALL SECTION DETAILS DOORS & WINDOW SCHEDUAL REFLECTED CEILING PLAN VERTICAL CIRCULATION VERTICAL CIRCULATION DETAILS 6' - 0"

W11

30 May 2018 3:00:15 AM

W11

chunyiho@cpp.edu 012852359

2' - 0"

W4

Chunyi Ho

ER HO

68

10" COPING

AREA OF STACK

MAIN PROJECT MANAGER

G0.00 G0.01 G1.01 G1.02 G1.03 A1.01 A1.02 A1.11 A1.21 A1.22 A1.23 A1.24 A1.25 A2.01 A3.01 A3.02 A3.11 A4.01 A4.11 A4.31 A5.01 A6.01 A7.01 A8.01 A8.02

30 May 2018 3:00:12 AM

WEST HOLLYWOOD HOUSING -

---

Sheet Name

30 May 2018 3:09:47 AM

Sheet Number

CHUNYI HO 3400 POLY VISTA, POMONA, CA 91768 PETERHO0103@GMAIL.COM

30 May 2018 3:00:22 AM

PROJECT CONSULTANTS

Different from most of the apartment complex around here, I propose a new concept to provide more opportunity for gay people to walk out of their comfort zone, have more social activities with people. OWNER


Concrete Oasis Syracuse University

Instructor / Roger Hubeli Year / 2020 Software / Rhino, Grasshopper, Photoshop Modern cities are described as a concrete jungle, where nature is away from our everyday lives and only row after rows of concrete buildings left in our view. While developing a new method of construction, we can use easily accessible natural material to minimize the waste created during construction. As time goes by, the earth mold became stronger and stronger while the root expands. This pavilion is not just a planter to grow trees, it’s an architecture that integrates with nature and supported by the root system of plants.

18~ 20°

2”

V Shape Storage Bin Mixing Blade

0.25~2”

Print Nozzle

Earth

Bubble man

18~ 20°

2”

V Shape Storage Bin 0.25~2”

Mixing Blade Print Nozzle

Slurry

Earth as Lostmold


unity rfect and hway

Air Pavillion

Hostel and patio

View from the seventh floor

East entrance

Hostel and patio

View from the seventh floor

East entrance

Guang-Fu Market / Hostel

NTUST 2nd Grade

Interaction between patios of market and hostel

Market indoor space

Interaction between market user and hostel user

Instructor / Yiting Tseng Location / Taipei, Taiwan Year / 2016 Software / SketchUp, Photoshop

Interaction between patios of market and hostel

Market indoor space

Interaction between market user and hostel user

NTUST 2nd Grade

Instructor / Yuanchun Lan Location / Taipei, Taiwan Year / 2017 Software / Revit, Photoshop

Treasure hill is an artist community located at the river bank. This perfect location has beautiful view and environment, except the lifted highway overpass its skyline.

51

Guang-Fu Market is a 30 years old traditional market that vendors gather, locates in the center of the newly developed district right next to the Taipei 101 tower. To meet the modern lifestyle and sanitize quality, I proposed a new complex that has three levels for retails, three levels for a hostel, and a civic plaza in between.

I use air packs as the material of the pavillion, to pack the invisible air. Not only delivers the character of air that is light, and invisible, but also intends to remind people that air pollutionhas no profile, it can be spread as easy as air.

To encourage people entering this market, we create a shortcut on the groundfloor by proposing a special layout and add minor entrances on each side to attract potential customers who did not plan to buy food to enter.

The clearance of each space is defined by the activity take place. The entrance height is 3m, and the space in the activity area is 6m. Differentiating spaces with clearence can extend the experience of walking in the village of treasure hill.

5F Plan

North Elevation

FIFTH FLOOR PLAN

North Elevation 1F Plan FLOOR PLAN FIRST 0

5

10 m

48

There are three types of rooms. For one, four, and twelve people, and are mostly bunk beds.

To create view interaction between indoor and outdoor, you can see activities happen in the tubes from the other tube structure, upper level FIFTH FLOOR PLAN can see levels below, hostel can see the market. 5F Plan

Section 50 Chunyi Ho Portfolio

50 Chunyi Ho Portfolio

Section

South Elevation

South Elevation

7F Plan

SEVENTH FLOOR PLAN

Guang-Fu Market / Hostel 45

38 Chunyi Ho Portfolio

Taipei Treasure Hill Temporary pavillion 39

51

7F Plan

SEVENTH


Bubble Up / Bottle Up Syracuse University

Instructor / Fei Wang Partner / Yixuan Xin Location / XiongAn, China Year / 2019 Software / Rhino, SketchUp, Illustrator, Adobe Fresco The development of human civilization has been through stone age, bronze age, iron age. And now we have entered the plastic age. Our reliance on plastic has increased dramatically globally. It is like a sugar-coated poison, not necessary but difficult to leave it. We collect PET, PP, HDPE, and LDPE which are safe for melting, and these types of plastics will be transported through underground vacuuming systems to the river bank and packed into different bubbles before being discharged into the river. The bubble will collect more waste along the journey to the plastic upcycling factory. As it arrives, we transform plastic wastes into several types of bubbles according to the kind of plastic. Some of the bubbles will be used as the construction component of this growing tower, the more plastic human throw away, the height and quantity of these towers will increase.

Water

water quality

factory pollution

less amount of trash

upcycling facilities

trash pollution

new resident

increase the amount of trash

water related activity

better environment

fishing

boating

incineration

skiing

lack of knowledge of sorting

landfill

water farming

better life

increase health

Trash

low recycling rate

increase health

provide space and oppotunities

increase awareness

Electronic Devices visualize

New City

lack of environmental awareness

truck

underground waste storage

Automation

bubble

tower

cost less money

use less energy

Recycled Plas�c Shell Reed Fiber Film

Plas�c Waste


Starlight Ceiling

Graduation Exhibition Head Coordinator

Instructor / Yunshang Qiu Location / Taipei, Taiwan Partner / Powell Huang, Rio Chen Year / 2017 Software / Grasshopper, HDRScope

Partner / 2019 TTDA Graduation Association Location / Taipei, Taiwan Year / 2019

We create a three-dimensional surface composed by glass fiber to lit up a classroom without electricity and analyze the results using the software “HDRScope” by taking 10 different exposure picture of the physical testing model.

The experience of being the coordinator of an exhibition gives me the ability to use every second of my time wisely, let me learn how to listen to everyone’s opinion, make me understand the importance of the connection between people. The position of leadership has never been easy, it is not a task that one person can achieve by themself, it is group work. To me, the skill of communication is the most important. It is an art of how to negotiate between people and make things work.

NTUST 2nd Grade

The model is created by Grasshopper and labeled the length of each fiber automatically into AutoCAD to laser cut, and reduce the labor work of assembling the model.

NTUST Thesis


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.