Pipeline Trail Preliminary Design - Pierce County Parks

Page 1

AGENDA Introductions Project Background Project Schedule Presentation Open House Discussion Wrap Up

STAKEHOLDER MEETING #1

Pipeline Trail Preliminary Design DECEMBER 17, 2019


History • • •

Unofficial recreation access Community & Transportation planning support (1990’s) Feasibility Study (2007)

• • •

City: Tacoma Dome Station to City boundary County: 72nd and Waller to 94th Ave Future: South Hill Community Connections/Foothills Trail

• • • •

2019 – project kickoff 2020 – public engagement, preliminary design, grant funding 2021 – public engagement, complete design 2022-2023 – begin construction (funding dependent)

Trail Development Project Timeline

Pipeline Trail

PROJECT CONTEXT

Project Background


72nd Street East and Waller Road

94th Street East

Pipeline Trail

PROJECT EXTENTS

Project Background


Objectives • • • • • • •

Provide separated shared use path Incorporate equestrian trail where conditions allow Provide safe crossings Maintain TPU’s service road access Identify trailhead parking opportunities Maintain residential primary driveway access Pursue grant funding for construction

Pipeline Trail

OBJECTIVES

Project Background


Preliminary Design

nov

dec

analysis & inventory stakeholder meeting #1

jan

feb

alternatives evaluation

mar

preliminary design

may

grant application

stakeholder meeting #2 public meeting #1

Pipeline Trail

apr

public meeting #2

Project Schedule


Project Corridor • • • • •

5.5 miles – 6 sheets 12 road crossings Multiple driveway crossings 2 parks Multiple destinations

1 2 3 4 Half Dollar Park

9

5 6

12

Pipeline Trail

MAPPING

Project Inventory/Analysis


Project Corridor

from

72nd St E/Waller Rd E to

Vickery Ave E

1 Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Project Corridor

from

72nd St E/Waller Rd E to

Vickery Ave E

1 Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


(Average Daily Trips)

Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Project Corridor

from

Vickery Ave E past

Orangegate Park

2 Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Project Corridor

from

Vickery Ave E thru

Orangegate Park

2 Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Parking location undetermined at Orangegate Park

(Average Daily Trips)

Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Parking location undetermined at Orangegate Park

(Average Daily Trips)

Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Project Corridor

from

Canyon Rd E to

63rd Ave E

3 Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Project Corridor

from

Canyon Rd E to

63rd Ave E

3 Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Project Corridor

from

64th Ave Ct E to

S Fruitland

4 Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Project Corridor

from

64th Ave Ct E to

S Fruitland

4 Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Verify: Future intersection improvements

Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Project Corridor

from

S Fruitland/SR 512 to

87th Ave Ct E

5 Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Project Corridor

from

S Fruitland/SR 512 to

87th Ave Ct E

5 Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Project Corridor

from

87th Ave Ct E to

94th Ave E

6 Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Project Corridor

from

87th Ave Ct E to

94th Ave E

6 Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Project Corridor

Pipeline Trail

EXISTING CONDITIONS

Project Inventory/Analysis


Project Corridor to the North Trail width and surfacing Separation from service road Barrier treatments Crossing treatments Signage/striping

Pipeline Trail

RECENTLY CONSTRUCTED

Tacoma Segment


Orangegate Park and Half Dollar Park Parking Restrooms/shelter Signage/wayfinding Park master plans in future

Pipeline Trail

PRECEDENTS AND STANDARDS

Trailhead Components


Street Crossings Vehicular Bicycle/Pedestrian Equestrian

Pipeline Trail

MIXED MODES

Crossing Options


Branding Mountain/territorial views Rural and agrarian Utility/history Other?

Pipeline Trail

BRANDING

Trail Identity


Pipeline Trail

Questions?


Pipeline Trail

Contact: Brianne Blackburn brianne.blackburn@piercecountywa.gov www.piercecountywa.gov/PipelineTrail